HomeMy WebLinkAboutExhibitCOMMISSIONERS
CHARLES A. PADERA
CHAIR
ST. JOHNS COUNTY
MICHAEL D. MESIANO
VICE -CHAIR
DUVAL COUNTY
BRUCE D. BARKETT
SECRETARY
INDIAN RIVER COUNTY
S. NORMAN BRAY
TREASURER
NA$SAU COUNTY
GRAYCE K. BARCK
VOLUSIA COUNTY
GAIL A. BYRD
MARTIN COUNTY
DONN R. COLEE, JR.
PALM BEACH COUNTY
T. SPENCER CROWLEY, 111
MIAMI-DADE COUNTY
SUSAN M. ENGLE
BROWARD COUNTY
GEORGE L. KAVANAGH
ST. LUCIE COUNTY
JONATHAN S. NETTS
FLAGLER COUNTY
JERRV H. SANSOM
BREVARD COUNTY
DAVID K. ROACH
EXECUTIVE DIRECTOR
MARK T. CROSLEY
ASSISTANT EXECUTIVE DIRECTOR
FLORIDA INLAND NAVIGATION DISTRICT
September 24, 2007
Mr. Daniel Newhoff
Assistant Director
Dept. of Conferences, Conventions & Public Facilities
City of Miami
400 SE 2nd Ave
Miami, FL 33131
RE: Dinner Key Mooring & Anchorage Field Project — Phase I
Project #DA-MI-03-79, Project Agreement Extension
Dear Mr Newhoff:
On September 22, 2007 the District's Board of Commissioners
approved your requested time extension to complete your
Waterways Assistance Projects). All extensions are for a one (1)
year period, ending in September 2008, On or before September 01,
2008, you must submit your final closeout paperwork to complete
this project.
I am enclosing two originals of a Project Extension Agreement
Amendment for your execution. Please read this agreement carefully
and execute and return both agreements to me for final execution by
the Board. One fully executed original will be returned to you for
your records.
Should you have any questions or need additional information please
contact me.
Sinc
ark Crosley 1•
Assistant Executive Director
ADMINISTRATIVE OFFICE ON THE INTRACOASTAL WATERWAY IN PALM BEACH COUNTY
1314 MARCINSKI ROAD, JUPITER, FLORIDA 33477-9427 TELEPHONE 561-627-3386 FAX No. 561-624-6480
www.aicw.org
PROJECT AGREEMENT AMENDMENT
In consideration of the continuing mutual promises and covenants contained in that
certain PROJECT AGREEMENT No. DA-MI-03-79, Dinner Key Mooring & Anchorage,
between the FLORIDA INLAND NAVIGATION DISTRICT (F.I.N.D.) and The City of
Miami, hereafter known as the PROJECT SPONSOR. The parties hereby agree that
Paragraph 2 of said certain PROJECT AGREEMENT be deleted and the following be
substituted therefore:
2. TERM - The PROJECT SPONSOR shall not commence work on the PROJECT
prior to the execution of this Agreement unless specifically authorized by the DISTRICT
Board. The PROJECT SPONSOR shall complete and submit all required payment
reimbursement information on or before September 1, 2008. Pursuant to law in the
declaration of a natural disaster, the PROJECT period is extended beyond the original
three (3) years from October 1, 2003. This project has been granted an additional one (1)
year extension and therefore this PROJECT must be completed by September 30, 2008.
Because the completion of the PROJECT has been delayed by a declared natural disaster,
the F.I.N.D. Board authorizes an extension of the completion date based upon this delay.
In WITNESS WHEREOF, the parties have hereunto set their hands and seals
this of , 200_.
Attest: F.I.N.D.
EXECUTIVE DIRECTOR
Attest: PROJECT SPONSOR
CONTRACT ADMINISTRATOR