HomeMy WebLinkAboutExhibit 13Boundless Playground for Bryant Park. Boundless Playground for Bryant Park, Completion Timeline City of Miami, July 2007 Project entails demolition of the existing playground unit at Bryant Park and replacing it with a Boundless Playground approved unit. This new plpy structure will be accessible to children in wheelchairs and the able-bodied, allowing them tb play side -by -side. Children in wheelchairs will not have to abandon their special equipment in orderto enjoy the playground. In addition the project includes site preparation, demolition, construction and the installation of a rubberized safety surfacing. Development Stages Begin . Contract Execution 4 months Planning, Procurement, Permitting 7 months Demolition, Disposal, Site Preparation Construction, Pour -in -place safety surfacing, Concrete base, Recreational equipment (delivered and installed) 6 months TOTAL ' 17 months City of Miami, July 2007