Boundless Playground for Bryant Park, Completion Timeline
City of Miami, July 2007
Project entails demolition of the existing playground unit at Bryant Park and replacing it with a
Boundless Playground approved unit. This new plpy structure will be accessible to children in
wheelchairs and the able-bodied, allowing them tb play side -by -side. Children in wheelchairs will not
have to abandon their special equipment in orderto enjoy the playground.
In addition the project includes site preparation, demolition, construction and the installation of a
rubberized safety surfacing.
Development Stages
Begin
.
Contract Execution
4 months
Planning, Procurement, Permitting
7 months
Demolition, Disposal, Site Preparation
Construction, Pour -in -place safety surfacing, Concrete base, Recreational
equipment (delivered and installed)
6 months
TOTAL '
17 months