HomeMy WebLinkAboutProposalCONSULTANT WORK ORDER PROPOSAL
July 31, 2005
HDR Engineering, Inc. proposes to provide the services Identified below for the project entitled
"Program Management/Specialty Services Miami Streetcar", pursuant to its Professional
Service Agreement with the City of Miami for Transportation and Transit Professional Services
services, dated July 31, 2005.
1 1. GENERAL
This scope of work provides the services necessary to progress the City of Miami Streetcar
project forward through the completion of an Alternatives Analysis and an Environmental
Assessment for approval by the Federal Transit Administration (FTA), the selection of a Design
Build Operate and Maintain (DBOM) contractor, and an application to FTA to enter Preliminary
Engineering:
1. Program Management;
2. Alternatives Analysis;
3. Agency Agreements;
4. Florida East Coast Railway coordination;
5. Certification of City of Miami with FTA; and
6. Financial analysis support.
Project Description
The project entails the construction of a streetcar system operating in mixed traffic on the
streets of downtown Miami. The initial recommended project phase for streetcar service is a bi-
directional (i.e., two-way) circulator route that connects Downtown Miami to the Miami Design
District, primarily via NE 2nd Avenue.
. Attributes of the project are:
6.75 miles of in -street trackwork including trackbed structure.
Street reconstruction as necessary.
Intersection and signal system modifications.
Utility modifications, relocations, coordination and agreements as necessary.
A traction power system consisting of substations connected to the public utility and
feeder cables to the overhead wire system.
An overhead wire system consisting of support poles and a single contact wire.
A communications system including on -board radios for streetcar operation and a
passenger information system at station stops.
Infrastructure such as street lighting, underground duct banks, manholes, hand holes,
service panels and all other related electrical components as required.
Station/stop platform areas with shelters, ADA treatments, passenger information
systems, and other passenger amenities.
A Maintenance and Operations Facility (MOF) to accommodate the vehicles to be
utilized in the Miami Streetcar project and the proposed Bay Link project and the
additional trackwork and systems infrastructure improvements to reach the MOF from
the main alignment.
2. SCOPE OF WORK
Task 1.0 Program Management — Program Management activities will include
the management of all activities on this project performed by HDR and other consultants
working for the City of Miami on the project, progress reporting, invoicing, and other support
activities necessary to manage the project. This task will include preparation of schedules, cost
estimates, budgets, progress reports and other miscellaneous activities that will be necessary
on the project. These efforts will include such things as assisting the City in getting the project
approved by the MPO as a part of the cost -constrained Miami -Dade 2030 Long Range
Transportation Plan, preparation of an application to enter Preliminary Engineering to the FTA,
development of a Project Management Plan for submittal to FTA as part of the request to enter
PE, and public involvement activities as necessary.
This also includes management of efforts by other industry partners of the City, who will be
completing tasks such as:
• Utility agency agreements
•
• "Exempt project" New Starts submittal;
• Design Build Operate Maintain (DBOM) Procurement documents;
• Ridership sensitivity analysis; and
• Specific work elements within the Alternatives Analysis
Task 2.0 Alternatives Analysis — Alternatives Analysis (AA) is the backbone of
the National Environmental Policy Act of 1969 (NEPA) process for federal agencies. This
process identifies, analyzes and ranks potential alternatives under consideration for the protect.
The AA involves three alternatives: the No -Build; the Transportation Systems Management
(TSM); and one or more Build alternatives. FTA gives the local jurisdiction the option of
including a Draft Environmental Impact Statement or an Environmental Assessment in the
Alternatives Analysis effort. A New Starts application can be submitted after the Alternatives
Analysis is completed as long as the locally preferred alternative (LPA) has been adopted by the
local MPO in its financially constrained, long-range transportation plan.
Given this, our approach is to complete the Alternatives Analysis before submitting an "Exempt
Project" application to FTA, along with the completed AA, supplemented by the activities
required to complete the "Exempt Project" application. This will allow the "Exempt Project'
application to be completed In the most expeditious timeframe.
The AA will document the existing environmental, social and economic conditions that pertain to
the project. These data will be described in an Existing Conditions Report that will present the
environment potentially affected by the project alternatives, or the environmental conditions that
could affect the development and selection of alternatives. This report will provide the basis for
the Existing Conditions chapter of the AA. Consistent with CEQ Regulations in 40 CFR 1502.15,
descriptions will be concise and the focus will be on those resources that may potentially suffer
significant negative effects from the proposed project. Whenever possible, detailed background
or support material will be incorporated by reference or placed in an Appendix.
The following topics, as applicable, would be addressed in the Existing Conditions Report
• Existing and Future Land Use
• Consistency with local, State and Federal Planning
• Social, Economic and Community Profile
• Transportation Network
• Environmental Justice Considerations
• Historic, Archaeological and Cultural Resources
• Parklands
• Geology and Soils
• Water Quality and Wetlands
• Floodplalns
• Navigable Waterways and Coastal Zones
• Endangered Species
• Visual Impacts/Aesthetics
• Air Quality
• Noise and Vibration
• Hazardous Materials & Brownfields
The proposed Miami Streetcar project will then be compared to the No -Build Alternative and a
Transportation System Management (TSM) Alternative. It is assumed that the TSM Alternative
will be a bus circulator alternative. This analysis is to determine the relative Impacts and
benefits of these three alternatives with respect to the existing environment. Specific activities
to be included in the AA effort include:
• Alignment modifications as necessary.
o Miami Design District terminus (dead end on 41'4 versus loop on 38th and 40th)
o Shift west from N. Miami Ave. to NW 1 st Ave. for Overtown connectivity
• Finalize station locations
• Finalize MDT bus/streetcar interface at Government Center
• Traffic impact analysis, comparing the impacts (and benefits) of:
o No -Build
o Build (Streetcar)
o Transportation System Management (TSM) (In all likelihood a bus circulator)
• FTA coordination
• Public Involvement
o Businesses
o Property owners
o Residents
o Other Interested/Potentially Affected Parties, i.e., community -based, business
and other non -governmental organizations
• Agency Coordination including elected and appointed officials
To accomplish this, HDR's approach would focus on documentation of the proposed the Miami
Streetcar project (the Build Alternative), particularly its responsiveness to the stated project
purpose and need. A successful outcome of this task would enhance the likelihood of FTA's
support for the project. The AA will address NEPA requirements for demonstration that all
reasonable Build alternatives were considered -- and eliminated as a result of the screening
process — to arrive at the recommended Build alternative. The documentation of the proposed
Build, No -Build, and TSM Alternatives will include agency coordination and public involvement,
and other efforts necessary as part of the AA, as described further within the AA Scope to be
approved by FTA.
NOTE: A separate scope has been developed for the Alternatives Analysis for review and
approval by FTA.
Task 3.0 Agency Agreements — As currently planned, the Miami Streetcar will
include stations or stops, trackwork, overhead catenary system (OCS), traction power
substations, and a combined maintenance facility. The Miami Streetcar project must be
coordinated closely with a number of agencies, such as several departments of FTA, Miami -
Dade County, City of Miami, Florida Department of Transportation (FDOT) Central Office and
District 8, and utility providers such as Florida Power & Light (FPL), to ensure successful,
efficient and timely implementation of the project.
This effort includes coordination and development of potential agreements necessary between
the City of Miami and Miami -Dade County. For instance, it Is expected that an agreement will
be needed with Miami -Dade County for any modification to traffic signal control systems and
operations. This may include:
• development of streetcar operations, policy issues (Le., push-button or automatic pre-
emption)
• additional signals at some intersections needed for streetcar (Le., NE 9th St. and NE 1`t
Ave.)
• signal system modifications to be done when streetcar is implemented
Since the Miami Streetcar project has the potential to impact utilities along its alignment, the
agency coordination effort will include the various utility companies that may be affected by the
project. This effort includes meetings and development of agreements with the utility providers
for the project's design and construction. The intent of this effort Is to document the cost of
utility impacts and relocations as part of the Miami Streetcar project costs to the extent required
by FTA within the New Starts application. This effort is expected to address both policy and
technical issues.
Since several of the traction power substations for the streetcar are proposed to b located on
FDOT right-of-way, this effort also includes the development of agreements with FOOT for use
of property.
Since the project will need support from a number of elected officials and representatives at the
local, state, and federal level, this effort also includes agency coordination with:
1. Miami -Dade Board of County Commissioners
2. City of Miami Commission
3. Local state representatives
4. Local members of Congress
5. State Senator's transportation staffs
The agency coordination activities will also include agencies from which the project will need
support, acceptance, or NEPA review. Among these agencies are Department of Community
Affairs, Department of Environmental Protection, and Corps of Engineers.
The agency coordination effort with utility companies will be completed by one of the City's
industry partners, under HDR's management. HDR will provide all other agency coordination
efforts.
Task 4.0 FEC Railway Coordination — As currently planned, the Miami Streetcar
project will cross the Florida East Coast Railway (FEC) In more than one location. While the
Alternatives Analysis includes coordination on such crossings in the planning process, It will be
necessary to formalize a Memorandum of Understanding (MOU) with FEC for such crossings as
part of the project. Since the project will be seeking FTA approval, It expected that FTA will
Submitted by:
require that the 'Exempt Project" application include documentation of agreement from FEC that
the Miami Streetcar can cross their rail line. Therefore, this effort provides for the effort
necessary to develop an MOU for the crossing of the FEC rail line by the Miami Streetcar. This
effort does not include engineering efforts that may be necessary to resolve design issues such
as signalization, communications, and special trackwork.
Task 5.0 Certification of the City of Miami — This task involves assisting the City
of Miami in becoming certified by FTA so that the City may receive grants from the FTA to
implement the Miami Streetcar project.
Task 8.0 Financial Planning Support — Although the Alternatives Analysis
includes a financial plan, it is anticipated that additional financial support efforts will be required
in the development of a final Finance Plan for the Miami Streetcar within the context of the AA
and an "exempt project" application to FTA. These efforts Include the development of a
financial model for FTA review.
3. SUBCONSULTANTS
LTK Engineering Services, Nick Serianni, Holland + Knight, and Planning Innovations, Inc. will
be subconsultants to HDR Engineering on this task. Nick Seriannl will utilize subconsultants on
this task, including Parker and Associates and a cost estimating firm that has not been identified
at this point in time.
4. SCHEDULE OF WORK -- TIME OF PERFORMANCE
SCHEDULE OF WORK
Task
1
2
3
4
5
6
Task Name and/or Activity Description ' Hours
Program Management
Alternatives Analysis
Agency Agreements
FEC Coordination
Certification of City with FTA
Financial Analysis
5. COMPENSATION
-41
1,538
3,308
646
240
408
460
TOTAL 6,601,
Deliverable
None
Final AA Report
Meetings, Agreements
Meetings, Draft MOU
Meetings, Application
Report
o
Schedule
6 to 8 months after NTP
8 to 10 months after NTP
4 to 8 months after NTP
10 to 12 months after NTP
6 to 8 months after NTP
Consultant shall perform the Work detailed in this Proposal for a Hourly Rate, Not to Exceed fee
of $1,500,198.50 — One Million, Five Hundred Thousand One Hundred Ninety -Eight dollars
and fifty cents.
6. PROJECT MANAGER
CONSULTANT'S Projianag
his Work Order assignment will be Robert E. Cone, P.E.
William H. Wadsworth, P.E., Executive Vice -President, HDR Engineering, Inc.