HomeMy WebLinkAboutContract Change Order 2Ql itp of lEiam
Contract Change Order
Project Name: ORANGE BOWL PARKING LOT
REPAIRS ADA
Project No.: B-30521
Contractor: MIGUEL LOPEZ JR. INC
7711 NW 74TH AVE., SUITE #3
MEDLEY, FL 33166
Change Order No.: 2
Contract Award Date: 12/ 08/ 2006
Completion Date: 1/22/07
Revised Completion Date (prior to this change):
1/29/07
Extension(s) of Time Previously Approved: 7
days
Revised Completion Date (including this change): 2/19/07
The Contractor and the City hereby agree to modify the Contract as follows: (Attach additional pages as necessary)
Item No.
Description of Change
Contract Price
Contract Tme
Increase
Decrease
Increase
Decrease
1
Increase in the scope of work for the repair work of
the SW parking lot including 300 SF of asphalt
patching, 22500 SF of pressure cleaning of parking
area, and the seal coating of 22500 SF area with
two coats of coal tar emulsion sealer. This work is
necessitated due to damage incurred during an
Orange Bowl event over the weekend of 1/20/07
6,510.00
21 days
t.
Difference (Net)
6,510.00
21 days
SUMMARY OF CONTRACT AMOUNT
Reason for Change
Regulatory Change
Original Contract Amount
96,146.00
City Requested
Cost of Construction Changes Previously Ordered
16,642.50
Design Error
Adjusted Contract Amount Prior to this Change Order
107,788.50
Unforeseen/Unforeseeable X
Cost of Construction Changes in this Change Order
6,510.00
114,298.50
• (Damage by others)
Adjusted Contract Amount Including this Change
Percentage Increase this Change Order
6.04%
Total Percent Increase to Date
18.88%
Contingency Funds Used No
Contingency 5,000,00 Contingency Balance 0 00
Extension of Time Allowed by this Change - 21 days
This change order is hereby incorporated into
Accepted By Contract
d becomes a part of the Contract Documents.
Date: vt" 'o7
Accepted By CIP Director Date: t D 7
Distribution:
CIP Form 101
❑ NE ❑ Finance ❑
Capital Improvements & Transportation
444 SW 2nd Ave, 8th Floor
Miami, Florida 33130
Project File 0 Page 1 of 2