Contract Change Order
Project Name: ORANGE BOWL PARKING LOT
REPAIRS ADA
Project No.: B-30521
Contractor: MIGUEL LOPEZ JR. INC
7711 NW 74TH AVE,, SUITE #3
MEDLEY, FL 33166
Change Order No.: 1
Contract Award Date: 12/ 0812006
Completion Date: 1/22/07
Revised Completion Date (prior to this change): N/A
Extension(s) of Time Previously Approved:
0 days
Revised Completion Date (including this change): 1/29/07
The Contractor and the City hereby agree to modify the Contract as follows; (Attach additional pages as necessary)
Item No.
Description of Change
Contract Price
Contract Tme
Increase
Decrease
Increase
Decrease
1
Increase in the scope of work for the patching of
additional 3170 SF of asphalt, including the
removal of existing asphalt, limerock
replacement, root removal, and new asphalt.
This area was not captured in the original
design documents used for bidding.
11,642.5
7 days
Difference (Net)
11,642.50
7 days
SUMMARY OF CONTRACT AMOUNT
Reason for Change
Regulatory Change
Original Contract Amount
96,146.00
City Requested
Cost of Construction Changes Previously Ordered
0.00
Design Error
X
Adjusted Contract Amount Prior to this Change Order
96,146.00
Unforeseen/Unforeseeable
Cost of Construction Changes in this Change Order
16,642.50
Less Contingency Used
-5,00Q.00
Adjusted Contract Amount Including this Change
107,788.50
Percentage Increase this Change Order
12.11%
Total Percent Increase to Date
12.11%
Contingency Funds Used Yes
Contingency 5,000.00 Contingency Balance 000.00
Extension of Time Allowed by this Change - 7 days
This change order is hereby incorporated
Accepted By Contrac
Accepted By CIP Director
Distribution:
CIP Form 101
and becomes a part of the Contract Documents.
Date:
Date: s-fa►/A7