HomeMy WebLinkAboutII. Project Description-A-Zoning Ordinance No. 11000.11. PROJECT
DESCRIPTION
PROJECT DESCRIPTION
ARTICLE II.
Project Description
A. Zoning Ordinance No. 11000
1. Section 1304.2.1 Application forms; supplementary
materials
2. Section 1702.2.1 General Report
3. Section 1702.2.2 Major Use Special Permit Concept Plan
4. Section 1702.2.3 Development Impact Study
MAJOR USE SPECIAL PERMIT
1. Section 1304.1.1 Application forms; supplementary materials
(a) Statements of ownership and control of the proposed development
of activity.
The Disclosure of Ownership and Ownership Affidavit are provided in
Article I.
(b) Statement describing in detail the character and intended use of
the development or activity.
This project comes as result of the Related Companies continuing
efforts to bring workforce housing to the City of Miami. Lofts III is similar
in purpose and style to Lofts I & II. The architecture is meant to be bold
and modern, complementing the city skyline.
Lofts III consists of 495 residential units and 14,100 s.f. of retail space.
The project is 28 & 32 levels with the roof at 360' tall. The height and
F.A.R. are unlimited.
The project is bound to the North by NE 3rd Street. To the South is NE
2nd Street. The West boundary is NE 2nd Avenue. The Metro -Mover runs
along the East property line.
The ground floor residential lobby is oriented towards the pedestrian
traffic along NE 2nd Avenue. Loading and service functions are placed
along the east property line, parallel to the Metro -Mover shielding them
from view. The remainder of the ground level is dedicated to retail
space enhancing the pedestrian scale and experience.
The primary amenity space is located at the 28th Level. Provided are a
recreation deck, pool, spa, Health Club for the use of the project's
residents, and lockers. The clubroom is located on the 2nd level
overlooking the street.
(c) General location map, showing relation of the site or activity for
which special permit is sought to major streets, schools, existing
utilities, shopping areas, important physical features in and
adjoining the project or activity and the like.
The following exhibits are included with the Major Use Special Permit
Application:
(1) Aerial: Aerial photograph of the surrounding area with the
project projected on the site. (Sheet A.18)
1
(2) Area Context Map/Site Aerial: Map of the project site and
indicating adjacent buildings. (Sheet A.19)
(3)
Location Map: Map of the surrounding street system indicating
the project location. (Sheet A.0)
(d) A site plan containing the title of the project and the names of the
project planner and developer, date, and north arrow and, based on
an exact survey of the property drawn to a scale of sufficient size
to show:
The general information requested is shown on the Cover Sheet and
Site/1st Level Plan, Sheets A-0 and A-1. The site/1ST Level Plan includes
the following:
(1) Boundaries of the project, any existing streets, buildings,
watercourses, easements and section lines;
The boundaries of the project and the location of existing
streets and easements are shown on the site Survey.
(2) Exact location of all buildings and structures;
(3)
The exact location of all existing buildings located on the
property is shown on the site Survey. The location of the
building to be constructed is shown on the 1st Level Plan.
(Sheet A-1)
Access and traffic flow and how vehicular traffic will be
separated from pedestrian and other types of traffic;
Access for the project is primarily pedestrian from NE 2nd
Street. No parking facilities are provided in this project. The
service drive for the project, as well as the loading areas are
located along the East property line, along the Metro -Mover.
A detailed analysis of the site access and traffic flow is
provided in the Traffic Impact Analysis.
(4) Offstreet parking and offstreet loading areas;
There is no offstreet parking facility provided in this project.
The Zoning Ordinance requires (4) loading bays. There will be
(4) loading bays that are 12 ft. x 35 ft. The loading bays are not
located under or within the building. Service areas are shown
on the 1st Level Plan. (Sheet A-1)
(5) Recreational facilities locations;
2
Most of the recreational facilities will be located at the 28th
Level of the project. Exterior amenities will include a pool, spa,
and recreation deck with planters. Interior facilities will include a
Health Club with restrooms and lockers. These areas are
shown on Sheet A.9.
Clubroom facilities will be located at the 2nd Level. This area is
shown on Sheet A.2
(6) Screens and buffers;
(7)
(8)
Landscaped areas are indicated on the Landscape Plan, Sheet
LA-1 and the 1st Level Plan, Sheet A-1.
Refuse collections areas;
Waste collection will be provided by a containerized system
located within the service area. The building will include air
conditioned garbage rooms. These facilities are shown on the
1st Level Plan, Sheet A.1.
Access to utilities and points of utilities hookups.
Access and connections to site utilities are discussed in the
Site Utility Study.
(e) Tabulations of total gross acreage in the project and the
percentages thereof proposed to be devoted to:
(f)
3
(1) The various permitted uses:
Residential Sq. Ft. = 469,850 S.F.
Retail Sq. Ft. = 14,100 S.F.
(2) Ground coverage by structures:
Building Footprint = 20,240 S.F.
Ground coverage by the structure is 46.2 % of the total gross lot area.
Tabulation showing the following:
(1) The derivation of numbers of offstreet parking and
offstreet loading spaces shown in (d) above;
There is no requirement for offstreet parking in this project. Offstreet
loading is shown on the 1st Level Plan, Sheet A.1.
(2) Total project density in dwelling units per acre.
(g)
As per CBD zoning the maximum project density is 1,000 units
per acre. The designated site is .97 acres, which allows for the
construction of 970 units. This project will provide only 495
units.
If common facilities (such as recreation areas of structures, private
streets, common open space, etc.) are to be provided for the
development, statements as to how such common facilities are to
be provided and permanently maintained.
All common facilities provided will be maintained by the Owner.
(h) Storm drainage and sanitary sewerage plans.
(i)
Storm drainage, water distribution, waste water and solid waste
generation provisions are discussed in the Site Utility Study.
Architectural definitions for buildings in the development; exact
number of dwelling units, sizes, and types, together with typical
floor plans of each type.
Detailed information and breakdown of square footage of all uses are
found under Project Data located on the cover sheet A.O. Typical floor
plans for residential units are shown on the Typical Residential Floor
Plan and individual unit plans, Sheets A.1-A.12.
(j) Plans for signs, if any.
The project will obtain signage approval at a later date.
(k) Landscaping plan, including types, sizes and locations of
vegetation and decorative shrubbery, and showing provisions for
irrigation and future maintenance.
(I)
(m)
The landscape plans showing vegetation are found on Sheets LA-1.
Plans for recreation facilities, if any, including location and general
description of buildings for such use.
Most of the 28th Level of the project will contain the project amenity
space. There will be a pool, spa, recreation deck, Health Club, and
lockers. Additionally, a Clubroom will be located on the 2nd floor.
Such additional data, maps, plans, or statements as may be
required for the particular use or activity involved.
The details of the spaces and calculations used to compute the Floor
Area Ratio (FAR) are shown on Sheets A.1-A.11.
(n) Such additional data as the applicant may believe is pertinent to
the proper consideration of the site and development plan.
4
Elevations depicting the architectural character of the building are
shown on the Buildings Elevations. (Sheets A-13-A.15)
2. Section 1702.2.1 General Report.
(1)
Property ownership and beneficial interest within the boundaries of
the area proposed for Major Use Special Permit.
Statement of Ownership and beneficial interest within the boundaries of
the area proposed for Major Use Special Permit are provided in Article I.
The nature of the unified interest or control.
The nature of unified interest or control is indicated in Article I.
Survey of the proposed area showing property lines and
ownership.
A copy of the Surveys are included under Tab 5 of the Supporting
Documents.
(4) Map of existing features, including streets, alleys, easements,
utilities lines, existing land use, general topography, and physical
features.
(5)
The existing site features and utility lines are shown on the Boundary
Survey of the property located under Tab 5. The site features and the
utilities are also described in the Site Utility Study, located under Tab 3
of the Supporting Documents. The existing land use can be found on
the survey Sheet C-01 in Tab 6.
Materials to demonstrate the relationship of the elements listed in
(4) preceding to surrounding area characteristics.
The drawings submitted with this Application are located under Tab 6 of
the Supporting Documents.
(6) Existing zoning and adopted comprehensive plan designations for
the area on and around the lands proposed for Major Use Special
Permit.
The existing zoning designation for the property pursuant to City of
Miami Ordinance No. 11000 indicates the existing and surrounding
zoning. The zoning designations for the property is CBD. The
Comprehensive Plan Future Land Use designation for the property is
Central Business District. The zoning and the comprehensive plan
designations are consistent with one another.
5
3. Section 1702.2.2 Major Use Special Permit Concept Plan.
a. Relationships of the concept plan to surrounding existing and
proposed future uses, activities, systems, and facilities
(transportation, recreation, view corridors, pedestrian systems,
service systems and similar uses.
Article II contains a written narrative of this project outlining proposed
uses, activities and architectural character. This narrative also contains
descriptions of the project's relationship to traffic, pedestrian
movements, and transportation access. Building elevations, sections
and perspectives showing the proposed materials, vertical profile and
height, and orientation to streets are included in the drawings submitted
with this Application. The list of drawings submitted is found under Tab
6 of the Supporting Documents.
b. Existing zoning and adopted comprehensive plan principles and
designations.
The project conforms with the zoning district designation for the
property. The comprehensive plan future land use designation
conforms with the land use designation currently in effect for the
property.
4. Section 1702.2.3 Developmental Impact Study.
(a) A traffic analysis shall be submitted for an area within
approximately 1/4 mile of the site, or an area including the major
intersections to be impacted by the site, whichever is larger.
The Traffic Impact Analysis is included under Tab 2 of the Supporting
Documents.
(b) Economic impact data shall be provided, including estimates for
construction costs, construction employment, and permanent
employment and shall demonstrate that the proposed development
is favorable to the economy, public services, environment and
housing supply of the City.
The Economic Impact Study is included under Tab 4 of the Supporting
Documents.
(c) A housing impact assessment.
As fuel prices rise the demand for housing near employment centers will
grow. With the cost of single family homes unaffordable to the majority
of residents, condominiums become an attractive alternative to meet this
demand. With the continued increase in population the need for housing
will increase, putting additional pressure to supply housing in the urban
market at affordable prices.
6
(d) A description of proposed energy conservation measures shall be
provided, including only those measures that are proposed in
addition to the minimum requirements in State Energy Code.
Architecturally, the building envelope will be comprised of insulated
walls and roof. Low-E coated glass will be used throughout the building.
Electrically, all exterior and landscape lighting will be controlled by
means of time clocks and photocell switches. Energy saving lamps,
ballasts and fixtures are being considered at cores and public spaces.
(e) Historic Buildings
There are no historic structures located on the property.
(f). Environmental Zone
The property is not located within an environmental preservation district.
7