HomeMy WebLinkAboutExhibit 3EXHIBIT `B' Project Schedule Health District Circulator Study - Phase 2 Task 1: Project Coordination — completion within 60 days of Notice -To -Proceed Task 2: Route Finalization — completion within 90 days of Notice -To -Proceed Task 3: Finalize Cost Estimates — completion within 120 days of Notice -To -Proceed Task 4: Management Plan — completion within 120 days of' Notice -To -Proceed Task 5: Financing Plan — completion within 120 days of Notice -To -Proceed Work Product: Health District Circulator — Detailed Management and Financial Plan Final Draft Document due within 120 days of Notice -To -Proceed to the Consultant