HomeMy WebLinkAboutConcurrency Report (Revised)Proposal No 06-03 rev
Date: 5/11/06
CONCURRENCY MANAGEMENT ANALYSIS
CITY OF MIAMI PLANNING DEPARTMENT
IMPACT OF PROPOSED AMENDMENT TO LAND USE MAP
WITHIN A TRANSPORTATION CORRIDOR
AMENDMENT INFORMATION
CONCURRENCY ANALYSIS
Applicant, Lucia A. Dougherty, Esq on behalf of
Address: 100, 1012 & 1022 NW 1st Avenue
Boundary Streets: North: n/a East: NW 1st Avenue
South: NW 10th Street West: n/a
Proposed Change: From: High Density Multifamily Residential
To: Restricted Commercial
Existing Designation, Maximum Land Use Intensity
Residential 0.44 acres @ 300 DU/acre 132 DU's
Peak Hour Person -Trip Generation, Residential 66
Other sq.ft. @ FAR 0 sq.ft.
Peak Hour Person -Trip Generation, Other 0
Proposed Designation, Maximum Land Use Intensity
Residential 0.44 acres @ 300 DU/acre 132 DU's
Peak Hour Person -Trip Generation, Residential 66
Other sq.ft. @ FAR 0 sq.ft.
Peak Hour Person -Trip Generation, Other 0
Net Increment With Proposed Change:
Population 0
Dwelling Units 0
Peak Hour Person -Trips 0
Planning District Overtown
County Wastewater Collection Zone 308
Drainage Subcatchment Basin K1
Solid Waste Collection Route 16
Transportation Corridor Name Miami Ave
RECREATION AND OPEN SPACE
Population Increment, Residents 0
Space Requirement, acres 0.00
Excess Capacity Before Change 182.80
Excess Capacity After Change 182.80
Concurrency Checkoff OK
POTABLE WATER TRANSMISSION
Population Increment, Residents 0
Transmission Requirement, gpd 0
Excess Capacity Before Change >2% above demand
Excess Capacity After Change >2% above demand
Concurrency Checkoff OK
SANITARY SEWER TRANSMISSION
Population Increment, Residents 0
Transmission Requirement, gpd 0
Excess Capacity Before Change See Note 1.
Excess Capacity After Change See Note 1.
Concurrency Checkoff WASA Permit Required
STORM SEWER CAPACITY
Exfiltration System Before Change On -site
Exfiltration System After Change On -site
Concurrency Checkoff OK
SOLID WASTE COLLECTION
Population Increment, Residents 0
Solid Waste Generation, tons/year 0
Excess Capacity Before Change 800
Excess Capacity After Change 800
Concurrency Checkoff OK
RELEVANT MCNP GOALS, OBJECTIVES, AND POLICIES
Land Use Policy 1.1.1
CIE Policy 1.2.3
TRAFFIC CIRCULATION
Population Increment, Residents 0
Peak -Hour Person -Trip Generation 0
LOS Before Change B
LOS After Change B
Concurrency Checkoff OK
NOTES
1. Permit for sanitary sewer connection must be issued by
Metro -Dade Water and Sewer Authority Department (WASA).
Excess capacity, if any, is currently not known
CM 1 IN mil
ASSUMPTIONS AND COMMENTS
Population increment is assumed to be all new residents. Peak -period trip
generation is based on ITE Trip Generation, Sth Edition at 1.4 ppv average
occupancy for private passenger vehicles. Transportation Corridor capacities and
LOS are from Table PT-2(R1), Transportation Corridors report.
Potable water and wastewater transmission capacities are in accordance with
Metro -Dade County stated capacities and are assumed correct. Service
connections to water and sewer mains are assumed to be of adequate size; if not,
new connections are to be installed at owner's expense.
Recreation/Open Space acreage requirements are assumed with proposed
change made.