ARTICLE I — GENERAL CONDITIONS
SECTION ] . BACKGROUND
SECTION 2. SCOPE
SECTION 3. GENERAL
SECTION 4. DEFINITIONS
ARTICLE II —FUNDING
'SECTION 1.
SECTION 2.
SECTION 3.
SECTION 4.
PROCEDURES
FUNDINGCYCLES;
.APPLICATION SUBMISSION PERIODS
FUNDING APPLICATION
ELIGIBILITY REQUIREMENTS
ELIGIBILITY DETERMINATION AND EVALUATION
ARTICLE ill — GRANT ADMINISTRATION
SECTION 1. FUNDING ALLOCATION ADMINISTRATION •&
REIMBURSEMENT POLICY
SECTION 2. COMPLIANCE RESPONSIBILITIES
SECTION 3. REPORTS
SECTION 4. PROJECT CLOSE-OUT
SECTION 5. INTERPRETATION; ADMINISTRATION
Page 2
Page 2
Page 2
Page 2
Page 2
Page 5
Page 5
Page6
Page 7
Page 9
Page 11
Page ] 1
Page 18
Page 21
Page 21
Page 22
Building Bernet Ccnu*nunitie,F Adrrunistr iwe Rules
1 of 24
ARTICLE I - GENERAL CONDITIONS
SECTION I. I3ACIiG1 OUND
These administrative rules gol-ern the implementation by Miami -Dade County (the "County") of its
Building Better Communities General Obligation Bond Program as established by Ordinance No.
05-47 (the "Ordinance"),
SECTION 2. SCOPE
These administrative rules have been prepared to address the -administration and allocation of funds
for the projects and programs identified in the Building Better Communities General 'Obligation
Bond Program (BBC GOB Program). In addition to the funding of Projects specifically listed in the
BBC GOB Program, eligible projects may be funded through the -application process described in
these administrative rules with monies from four (4) funds. The funds are the Historical
Preservation Fund, the Economic Development Fund, the Not -for -Profit Community Organization
Capital Fund and the Primary Health Care Facilities Fund (collectively. the "Funds").
SUCTION 3. GENERAL
All recipients of funding for specific projects identified in the BBC GOB Program and for projects
,approved for funding from one of the Funds are required to follow these administrative rules.
Failure to do so may lead to disqualification.
Additional copies of the administrative rules. and/or application materials may be obtained by
contacting the County Managers Office. All inquiries; correspondence and applications for the
BBC GOB Program should be addressed to:
Miami -Dade County
County Manager's Office.
l l 1 NW 1 Street
Suite 2910
Miami, Florida 33128
Attention: Roger T. Hernstadt
or to a Department or agency of Miami -Dade County, -nerving as the County Manager's Designated
Representative.
SECTION 4. DEFINITIONS
The following is a list of terms and definitions that are used in these administrative rules:
"Acquisition" means the act of obtaining real property and/or capital assets or interests and rights
in real property .and/or capita] assets by various legal means to serve public purposes.
"Applicant" means a Public Agency, not -for -profit organization, 1•'4unicipality or other etatity
eligible to participate in the BBC GOB Program, which submits .a Funding Application Package to
the County during an .announced Application Submission Period.
Building Better Ccrrrnunities AdirrJristrative Rules
2of2'2
"Application" means the process described in these rules to make a formal request for Funding
Allocation which remains open until the execution of a Grant Agreement or triter/peal Agreement,
as the case may be, or a decision by the. County not to provide a Total Fundig Allocation.
"Application Submission Period" means the formally announced period of time for The
submission of a Funding Application Package in a given Funding Cycle.
"Board of County Comrnissi.oiters" or "Board" means the legislative and the :governing'bodyof
the County.
"Community -Based Organization (CB0)" shall refer to any not -for -profit 501c)(3) .agency,
group, organization, society, association, partnership or individual whose primary purpose is to
provide a community service designed to improve or enhance the well-being of the community of
Miami -Dade County at large or to improve or enhance the well-being of certain individuals within
this community who have special needs.
"County" means Miami -Dade County, Florida.
"County l\9anag•er" or ",Manager" means the head of the administrative branch of the County
government or his/her designated representative.
"Development" means the act of physically improving an area, facility, resource or site to increase
its ability or capacity to serve the public.
"Designated Projects" means the specific Projects approved by the Board in the Ordinance and the
electors on November 2. 2004 for inclusion in the BBC GOB Program.
"Fixtures, Furniture and Equipmenr (FF&E)" means l) Fixtures - items that are permanently
affixed to the building or property, i.e.; doors, bathroom stalls, A/C units, .etc.; 2) Furniture - indoor
furnishings needed to allow proper use of a building, i.e., desks, chairs, tables, workstations, etc.;
and 3) Equipment • non -consumable tangible properly with a life of at least one year that is directly
related to the funded project, such as bleachers for courts, audio/visual equipment for community
MOMS; computers for computer labs, port -able basketball goals for gyinnasiurris,.etc.
"Fund Projects" means the specific Projects approved by the County pursuant Ito these
administrative rules for a Funding Allocation from one of the Funds.
"Funds" means any and/or all of the following four funds included in the BBC GOB Program to
address grant requests for Fund Projects: the Economic Development Fund, the Historical
Preservation Fund, the Not -for -Profit Community Organization Capital Fund and the Primary
Healthcare Facilities Fund.
"Funding Cycle .Allocation" means Building Better Communities General Obligation Bond funds
approved by the Board in a given year for use by a Recipient for implementation of a Project
pursuant to these administrative rules.
"Funding .Allocation" mean (i) the total amount of Building Better Communities General
Obligation Bond funds approved by the Board on July 20, 2004 for use by a Recipient for a specific
Bi flding Better Communities Adnlinistretive Ruler
of -)2
Project; or (Si) the total amount approved by the County from a Fund for use by a Recipient for a
specific Project.
"Funding .Application Form" means the base application form provided by the County Manager
to be completed by the Applicant and submitted as part of the Funding Application Package.
"Funding .Application Package" means the complete submittal package required by these
administrative rules and submitted by an Applicant for a Project. (See Article 11, Section 2).
"Fundding Cycle" means the time between the opening of an Application Submission Period .and
the approval by the Board of the Projects to receive a Funding Cycle. Allocation from the next series
of general obligation bonds.
".Grant Agreement" means an executed grant agreement between the County and a Recipient
(other than a grant to a Municipality or Public .Agency, which grant will be evidenced by an
executed Interlocal Agreement) setting forth mutual obligations regarding a Funding Cycle
Allocation for a Project.
"l terlocal Agreement" means an executed grant agreement between the County and a Recipient
that is a Municipality or Public Agency setting forth mutual obligations regarding a Funding Cycle
Allocation for a Project.
"Match" means. cash committed by the Recipient, as stipulated in the approved Grant Agreement
or the Interlocal Agreement, as the case may be, to complement funding awarded from the BBC
GOB Program.
"Municipality" means a political unit, such as a city, town, or village; incorporated for local self-
government within the confines of Miami -Dade County.
"Ordinance" means the Building Better Communities Genera] Obligation Bond Ordinance No. 95-
47.
"Pre -Agreement Expenses" means e]ieible expenses identified in Article II1, Section 1(B) of these
rules incurred by a Recipient for -accomplishment of a Project prior to full -execution M a Grant
Agreement or an Interlocal Agreement, as the case may be.
"Project" means each Designated Project or Fund Project, as the case may -be, .identified in a
Funding Application Package and approved by the -County for a Funding Allocation.
"Public Agency or Public Agencies" means an agency or agencies or administrative division or
divisions of the United States government; the State of Florida, the County, or any municipality
within the County.
"'Recipient" means an entity receiving a Funding Allocation.
"Soft Costs" means real and verifiable expenditures for administration, project management (not
related to construction •supervision), indirect costs (accounting/purchasing/personnel, etc.), imposed
fees (e.g., permit processing fees) and those costs NOT related to construction ma€eria], labor,
equipment or construction sub -contractors. Soft Costs for the purpose of this Program are classified
Building Better Corr�nuniiie: r,aministrative Rules
4 of 22
by the following three areas:
• Project Administration - administration, project management (not related to construction
supervision), indirect costs (accounting/purchasing/personnel, etc.) and imposed fees (e,g.,
Professional Services Agreement selection/permit processing fees). Project management related
to construction supervision is not considered a sofi cost; and
• Planning Services - Master Plan development and approval and feasibility studies; and
• Design Services - schematic design, design development, ,construction documents, bidding or
negotiation and as built drawings.
Construction supervision and/or inspection are not considered soft costs. All costs associated with
land acquisition such as: appraisals, due diligence, cost of land, project administration related to
land purchase, legal fees, etc. are not part of the soft costs.
"Targeted Urban Areas" or "TUA" means the geographical communities which have been
designated by the Board of County Commissioners.
"UMSA" means Unincorporated Municipal Service Area -of the County, for which the County
provides municipal services. Projects occurring within areas defined as UMSA are subject to the
same administrative rules as any other project seeking Building Better Communities General
Obligation Bond funding, regardless of the entity involved in the project.
ART)CLE 11 — FUNDING PROCEDURES
'SECTION 1. FUNDING CYCLES: APPLICATION SU13 SSION PERIODS
A Funding Cycle shalt be established by the Board on a periodic basis related to the sale of bonds,
provided there are Building Better Communities General Obligation Bonds remaining to be sold.
Each Project may be funded during one or more Funding Cycles through a Funding Allocation.
Eligible entities must apply for these Funding Allocations. Eligible entities .existing on'or before
July 20". 2004, the date the General Obligation Bond Resolutions were approved by the Board, will
receive priority consideration for Project approval and Funding Allocation. A Grant Agreement or
1nterlocal Agreement between the County and the Recipient, es the case may be, implements the
Funding Allocations.
The Funding Application package shall be delivered on or before the last day of the announced
Application Submission Period. The County may announce an additional Application Submission
Period if funds remain or become available after the preceding Application Submission Period is
complete. Each Application Submission Period and other pertinent application information shall be
publicly announced in newspapers of genera] circulation in the County at least one (1) month prior
to the deadline for submission of the Funding Application Package, unless otherwise waived by the
Board.
Bui;d:ng Berter Con;mumties .Acirninistrrtti,.e Rules
5 0122
SECTION 2. FUNDING APPLICATION
An Applicant must submit a complete Funding. Application in order to •be .eii'gib4e Ito receive a
Funding Allocation award. A complete Funding Application Package means one that meets all the
requirernents of the Ordinance and these administrative rules and is supposed by proper
documentation required by these administrative rules. The Funding Application Package shall
consist of:
1) Completed Funding Application Form.
2) Completed line item budget. The line item budget must be submitted with budget
justifications for the Construction and Fixtures, Furniture and Equipment line items. The
justification should provide detailed descriptions of the project elements. Reimbursement
for Fixtures. Furniture & Equipment is contingent upon prior inclusion and approval of these
expenses in the Grant Agreement. (See Article III, Section 1(C)).
3) Letter(s) of commitment for matching. funds that cornplernent the Funding Allocation
request as may be required by the Application.
4) Projected completion date for the Project and if the Project will be constructed in phases, the
completion date of each phase.
5) Project location map.
6) For Development Projects, certification of ownership of a site by the Applicant or evidence
of land tenure sufficient to satisfy the County that the Project may be developed on the
designated site.
7) Written evidence (resolution or other legally required documentation), which•at a minimum:
(i) authorizes the execution of the Grant Agreement -or the Interlooal Agree ient,,as the oase
may be; (ii) commits the Applicant to complete the Project; (iii) .as applicable, commits the
Applicant to provide operating, maintenance and programming funds upon completion of
the Project, to the extent allowed by law; and (iv) provides that the Funding Allocation shall
not be used in substitution of other capital project funding available to .the Applicant,
8) Any other documentation that the Board may require from time to time.
An Applicant may request funding for a major Pro,- . phases. Each phase shall constitute a
distinct portion of the proposed Project. Each Ar ...ar.requesting funding :for a Project in phases
shall commit to completing the Project ar .:.fined in the Grant Agreement or the Interlocal
.Agreement, as the case may be, unless''' _•-• ise modified by approval of the Board inaocordance
with these rules and the OrdinancF
In the event an applicP. intends to submit a request for pre -agreement reimbursement, the applicant
shall . "ctcie III, 'Section 1(B)).
Building Berle; Communities Administrative Rules
6 of 22
SECTION 3, ELJC181L1TY 'REQUIREMENTS
A) Designated Projects
Eligibility requirements for Applicants:
• .Active and duly registered Florida not -for -profit 501 (c)(3) corporation. Comply with
the County's Administrative Order 3-15.
• Active and duly registered Florida for -profit corporation or recognized business
entity.
• Municipal entity or'eency based in Miami -Dade County.
• Owner or lessee of residential or commercial property located within Miami -Dade •
County on which the Designated Project shall be situated.
• Financially stable including financial commitments to complete the Designated
Project.
B) Fund Projects
1. Funds Objectives
The Economic Development Fund (the "EDF") is a component of .the Building Better
Comrnunities Bond Program and is available for the purpose of providing infrastructure
improvements to spur economicdevelopment and attract new businesses to the community
in order to create jobs. The EDF includes Si5 million that is -available countywide and SI5
million that is specifically focused on the County's designated Targeted Urban Areas.
Eligible uses of the EDF include but are not limited to: infrastructure funding for road
construction, water and sewer lines; fencing, sidewalks, entryways, lighting, and handicap
accessibility; acquisition of ]and or buildings; and new construction of buildings;
renovation of buildings. 1nelieible uses of the EDF include but are not limited to: working
capital; furniture and fixtures.. office equipment; and other non -capital related expenses.
The Historical Preservation Fund. the Primary Healthcare Facilities Fund and the Nat -for-,
Profit Community Organization Capita] Fund are a component of the Building Better,
Communities General Obligation Bond initiative for the purpose of funding projects that
support the County's historic preservation; primary healthcare, and community agency
infrastructure needs. These are capita] projects that improve the quality of life for the
County's citizens, enhance medical facilities, rehabilitate historic properties, save
irreplaceable historic venues, and serve as a catalyst for preserving and protecting Miami -
Dade County's future. Medical institutions, historically and culturaily significant
properties. and Community -Based Organizations needing capital funds for construction,
renovation; and expansion of facilities within the community that meet the criteria for the
following programs may be eligible for assistance from these funds.
2) Program Descriptions and Criteria
a) Economic Development Fund.
Ellilding Eerier Cornnunitier Adminisr Live Rules
7of22
This program includes c"5 million that is available countywide and 115 million that is
specifically focused on the Countv's designated Targeted Urban Areas to spur economic
development and attract new businesses in order to create jobs.
Eligibility Requirements for Applicants:
• Active and duly registered Florida not -for -profit 501(c)(3) corporation.
• Active and duly registered Florida for -profit corporation or recognized business
entity.
• Municipal entity or agency based in Miami -Dade County.
• Owner or lessee of residential or commercial property located within Miami -Dade
County on which the Designated Projects will be situated.
• Financially stable including financial commitments to complete the Designated
Project.
• Those listed in any Request For Proposal's related to this Fund.
b) Historic Preservation Fund
This program includes 'Sl0 million and is intended to provide matching funds to private
property owners, private nonprofit organizations, and municipal government agencies
for the acquisition; relocation and rehabilitation of designatedhistoric properties, or
properties eligible for designation -as a historic property or as a contributing historic
district property, which has applied for such a designation within Miami -Dade County.
Eliuibility Rectuirements for Applicants:
• Active and duly registered Florida not-for-profit.501.(c)(3) corporation.
• Active and duly registered Florida for -profit corporation or recognized business
entity.
• Municipal entity or agency based in Miami -Dade County.
• Owner of residential or commercial property located within Miattai-Dade County.
• Individually listed as municipal; County, State or National Register of historic
property located in Miami -Dade County.
• Contributing Properly within a designated municipal, County, State' or national
historic district located in Miami -Dade County.
• Property determined eligible for listing as an individual historic site oats a
contributing historic district property, and which.has applied for such designation, in
a Municipality, County, State or National Register, and located within Miami -Dade
County.
• Those listed in any Request For Proposal's related to this Fund.
c.) Not -for -Profit Community Organization Capita] Fund
The objective of this fund is to build and sustain the capability and capacity of the not -
for -profit sector and support entities that enhance the quality of life of Miami -Dade
County by 'delivering needed services. The S30 trillion allocated to this fund recognizes
the importance and continuing contributions that these organizations make to the future
of Miami -Dade County.
Building Better Communities Adminisnntive. Rules
'6 of 22
J=li�ibility Require -rents forApplicants:
• Legally incorporated 50] (c)(3) not -for -profit organization lacking access to
government sources of capital funding.
• Demnanstrable financial stability.
• Organization's_ mission is consistent with •goals identified in the M•iairri-Dade County
Strategic Plan.
• Demonstrate ownership of or intent to purchase a facility.
• Letter of Commitment confirming the resources necessary to accomplish the project.
• Architectural/engineering study andior equipment specifications and professional
•cosl estimate.
• Two (2) year management and budget plan for the facility.
• Those listed in any Request For Proposal's related to -this Fund.
c) Primary Healthcare Facilities Fund
The objective of this fund is to build and sustain the capability and capacity -of the not -
for -profit sector and support entities that enhance the quality of primary healthcare
within Miami -Dade County by delivering needed services. TheS25 r illion,alaocated to
this fund recognizes the importance and continuing contributions that these
organizations, and the care that they provide, make to the future ,of MMMiami-Dade County.
Eligibility Requirements for Applicants:
• Legally incorporated-----501(c)(3) not -for -profit org-aniz'ation lacking access - to
government sources of capital funding.
• Demonstrable financial stability.
• Organization's mission is consistent with goals identified in the Miami -Dade County
Strategic Plan.
• Demonstrate ownership of or intent to purchase a facility.
• Letter of Commitment confirming the resources necessary to accomplish the project. ,
• Architectural/engineering study andjor equipment specifications and professional
cast estimate.
• Two (2) year management and budget plan for the facility.
• Those listed in any Request For Proposal's related to this Fund.
SECTION 4. EL1Gf13ILITY DETERMINATION AND EVALUATION
Following closure of an Application Submission Period, the County Manager will review and
evaluate -each Funding. Application Package for funding eligibility or ineligibility. The County
Manager may use entities such as the following to assist him in the review and to create Project
Review Committees.
Economic Development Fund
• Empowerment Zone Trust Board
• Miarni•Dade Empov er rent Trust
• Office of Community' and Economic Development
Bung Berle! Communities .Adnvnistan e Rues
ef22
• Coalition of Chambers of Commerce
• Tasl, Force on Urban Revitalization
• Metro Miami Action Plan Trust
• Beacon Council
• Greater Miami Chamber of Commerce
• Dade League of Cities
Historic Preservation Fund
• Dade Heritage Trust
• Historic Preservation Board
Not -for -Profit Community Organization Capital Fund
• Alliance for' Human Services
• Dade Community Foundation
Primary Healthcare Facilities Fund
• Office of Countywide Health Care Planning
Any such entity shall adhere to public record protocols specified under Administrative Order No. 3-
1. Funding Allocations for eligible projects may be recommended to the County Manager by the
Project Review Committee. The County Manager and the Project Review Committee may
determine that a Funding Application Package be classified as:
A) ineligible. Declaration that the Project identified in 2 Funding Application Package, is
ineligible.
B) Conditionally Eligible. The Board may deterr line that a Project is eligible for funding upon
satisfaction of specified conditions. In the event that conditional approval is given, Board staff
shall verify that the conditions have been satisfied prior to executing a Grant Agreement or an
lnterlocal Agreement, as the case may be.
C) Eligible. Declaration that a Project identified in a Funding Application Package is fully
eligible.
Funding Application Pacl<ae-es determined ro be Eligible or Conditionally Eligible shall be reviewed
and competitively evaluated to recommend bond funding allocations. A listing of all Funding
Application Packages shall be reviewed by the GOB Sub -committee and presented to the Board by
the County Manager in the form of a Resolution stating the eligibility determination, presenting the
County Manager's funding recommendations based on the competitive :evaluation and seeking
approval for the disbursement of funds.
Building Better Communities Administrative Rules.
10of22
ARTICLE 1i1 - GRANT ADMINISTRATION
SECTION 1. FUNDING ALLOCATION ADMINISTRATION 'REIMBURSEMENT
'POLICY
A) Grant Agreement or lnteriocal Agreement
1) As a condition of award of a Funding Allocation, the BBC GOB Program and the
Recipient shall enter into a Grant Agreement or an lnterlocal Agreement, as the case may
be, which sets fonh the responsibilities and duties of each regarding administration of the
approved Project andapproved Funding Allocation.
2) The Grant Agreement or the lnterlocal Agreement, as the case may be, shall specify the
following and shall incorporate such other terms and conditions as may be required by
particular circumstances:
a) A Project Nan-ative/Description of Project, including location of Project, -and
beginning and end dates;
b) An overall budget for the Final Project, identifying additional sources oftevenue;
c) A Funding Allocation line item budget (proposed use of BBC GOB funds);
d) if the Recipient is a Community -Based Organization or other entity (not a
Municipality or Public Agency, a letter of commitment of matching funds validly.
executed committing the organization to raise any additional capital funds necessary to
complete the Project, and committing to provide operating, maintenance and
programming funds upon completion of the Project, all as authorized and approved by
the Recipient's Board of Directors or eoveniing entity;
e) If the Recipient is a Municipality or Public Agency, a letter of corrrmitment of
matching funds validly executed committing the organization to appropriate capital
funds necessary to complete the Project and to provide operating, maintenance and
programming funds upon completion of the Project, all as authorized and approved by
the governing board of such Municipality or Public Agency;
#) Certification ofownership, or evidence of lease or other use agreement for a
minimum un-expired term of 25 years;
g) Business plan and!or operating pro -forma; defining and identifyingstrategies 4o
address the impact the Project will have on the organizations operational structure; and
h) A list of consultants that will be involved in the development of the Project
Owner's project rnanager(s), Architecture and Engineering team, Specialty Consultants,
Developers: General Contractor or Construction Manager, etc.) as they become
available.
...•Buildin€ Better Coirmurities Adminisrrative Rules
11 of 22
B) Pre -Agreement Expenses The incuiTing. of Pre -Agreement Expenses creates no obligation on
the Counts' to -execute a Grant .Agreement or lnterlocal Agreement, as the case may be, or
other~ se satisfy those expenses. However, prior to the effective. date of the Grant Agreement.
or Intel -local Agreement, as the case may be„ a Recipient may incur eligible Pre -Agreement
Expenses as defined in Article ] - -Section 4, and then after the .effective date .of the Grant
Agreement or interiocal Agreement, as the case may be, be reimbursed for those costs, provided
that:
1) The costs and activities are funded as pan of the Funding Allocation award and are in
compliance with the requirements of the Ordinance and these rules.
2) For those Projects funded by bond proceeds from bond sales subsequent to the sale of the
Series 2005 Bonds; reimbursement of Pre -Agreement Expenses is limited to those Pre-
Agreernent Expenses incurred one (1) year prior to the first day of the Application
Submission Period, unless previously approved by the Board.
3) The Recipient has notified the County Manager in writh g of the intent to submit .eligible
Pre -Agreement expenses for reimbursement within 30-days of a Grant Agreement or
Interloca] Agreement being executed. Recipientsshall send a letter addressed to the County
Manager for his review and approval of eligible expenses.
C) Payment. Recipients are paid allocated funds subject to the following conditions:
1 Cost of Issuance of Bonds. Not more than one percent (1%) of the value of each Funding
Allocation award may be earmarked for all costs incidental to the preparation, issuance and
administration of the BBC GOB Program.
2 Timing. Project costs eligible for reimbursement shall be incurred between the effective
,date of, and the Project completion date identified in, the -Grant Agreement or the-Intetlocal
Agreement, as the case may be, with the exception of Pre -Agreement Expenses.
3) Soft Cosi. Limits. Protect Soft Costs for Planning Set -vices, Design Services and Project
Administration, as defined in Article ] Section 4, "Soft Costs", are eligible for funding
provided that bond proceeds utilized to pay for such costs do not exceed seventeen percent
(17%) of the total bond proceeds allocated to a given Project. This limitation may be
waived by the Board. Where a major Project is funded in phases, this cost limit may not
necessarily apply to each individual Project phase, but must apply to the Funding Allocation
for the Project.
4) Recipients will implement their own procurement process; however, they shall comply with
all applicable Federal, State and local laws and regulations, including the County ordinances
and regulations
5) Recipients are responsible for managing the day-to-day operations of Funding .Allocation
supported activities, and maintaining communications with the County Manager regarding
the Project. Recipients must monitor Funding .Allocation supported activities to assure
compliance with the Ordinance, these rules, the Grant Agreenr:ent or lnterloca] Agreement,
as the case may be, and all applicable Federal, State and local requirements.
Building Better Coro-nunities Administ:-ative Rules
12 of 22
(-) Payment_ to the Recipient may be withheld al any time that the Recipient fails Ay comply
with the terms of the Grant Agreement or the lnterloca] Agreement, .as the case may be.
Funds withheld for failure to comply with the terms of the Grant Agreement orthe inter -local
Agreement, as the case may be, but without suspension of the Funding Allocation shall be
released to the Recipient upon subsequent compliance. Recipients will -not be feguired tb
reimburse the County for payments already received by the County from the Recipient
unless the Recipient fails to develop andror operate the Project for the: purpose described in
the Funding Application Package.
7) Recipient's must complete the authorized signature form (Exhibit A).
8) in genera], payment shall be made on a reimbursement basis. A Funding Allocation
Recipient may submit a Request for Advance Payment forest (Exhibit 8) for -.review and
.approval by the County Manager. Approved recipients may receive an advance payment no
more that l SO days in advance of the allocation schedule approved by the Board, for up to
25% of the value of the Funding Allocation for the subject Project. Ail •advance payments
received by a Recipient shall be maintained in a separate interest bearing account and m•ay
not be co -mingled with other funds. All advances must be fully accounted for within on•e (1)
near of the date of the approval and before subsequent reimbursement requests are paid.
The recipient will be required to dose the account and submit a check to the County forthe
interest earned ac.c.ompanied by -an Interest Earned on Advance Form (Exhibit C). Upon
receipt of the check and supporting documentation all subsequent reimbursement requests
can be paid. Checks must be made payable to Miami -Dade County Board of County
Commissioners and forwarded to the Office. of the County Manager.
9) Recipients must submit reimbursement/payment requests no later than quarterly. If a
Recipient is unable to submit a reimbursement/payment request by the quarterly deadline, a
written justification indicating the reason for the delay and expected submission date is
required to be submitted by the deadline. Failure to comply with this requirement shall
render the Recipient in non-compliance with the Administrative Rules and may result in
reduction or forfeiture of payment, •ar the discretion of the County Manager. Failure to
submit two consecutive requests shall be deemed a forfeiture of all rights unless specifically
waived by the County Manager. The Recipient must submit a written explanation for -such
delays in order to be considered for a waiver of this requirement and ell such waivers shall
be made al the sole discretion of the County Manager.
10) Recipients -shall complete, sign, and submit to the County the appropriate Reimbursement
Request forms as necessary (Exhibits D through H) accompanied by ,supporting
documentation (i,e., copies of invoices, receipts and check payments).
11)Reimbursetnent requests for Fixtures, Furniture & Equipment items must be included and
approved in the Grant Agreement or the lnterloca) Agreement, as th•e case may be, prior to
acquisition. Written requests for Fixtures; Furniture & Equipment approval musi be
accompanied by Exhibit H.
12) In accordance with State ]aw. five (5%) of the value of the Building Better Communities
General Ob]ieation Bond funding for a given Project shall be retained by the County for,all
project's in excess of $100,000, unless otherwise recommended in writing by staff and
approved by the Board. Upon completion of a Project, -a signed project completion
Building )letter Comrrumtie: r,an:ininr.0 a Ruses
]2 of22
ceniftcate (Exhibit It must be submitted with the final reimbursement request forms in order
for the remaining retainage to be released.
1 }) The County Manager may require that reimbursement requests for any Funding Allocations
requiring a cash match must be accompanied by documentation of th•e expenditure of
committed match funds (i.e., copies of invoices, canceled checks, etc.).
14) Each Recipient will ensure that all contractors and consultants perform in accordance with
the terms, conditions, drawings and specifications of their contracts or purchase orders and
that all Federal, State and local contracting rules apply.
15) Each Recipient shall maintain an accounting system, which meets generally accepted
accounting principles, and sha]] maintain all required financial records to properly account
for all Building Better Communities Genera] Obligation Bond funds and any supplemental
funds used for the Project. The Recipient sha]] at all times maintain a separate accounting of
al] Building Better Communities General Obligation Bond funds.
16) Each Recipient shall be responsible for reporting, on a continuous, on -going basis, any
contractual relationship established to perform work on the project, start dates, progress
payments, completion dates, etc. in the system provided by the County.
1 i The Recipient sha]] be responsible for completing the Project. If the total cost of the Project
exceeds the value of the Funding Allocation, then the Recipient must provide any
supplemental funds required. In the event that supplemental funds are necessary for
completion of a Project, as of the point in time that it is known that supplemental funds are
needed, the Recipient must demonstrate that such supplemental funds have been committed
to the Project prior to and as a condition of disbursement or further disbursement of Funding
Allocations. The requirement for a Recipient to provide supplementa] funds may be
modified, in pan or whole, by the Board, to the extent that it approves in writing any
reduction or change to the Project scope of work in •accordance with the Ordinance.
Approval of any reduction or change in scope of work is at the sole discretion of the Board.
D) Acquisition Projects. Guidelines and requirements for administering Acquisition Project
Funding Allocations are as follows:
] Appraisal Required. Prior to acquisition of a Project site, ,a Recipient must obtain an
appraisal or appraisals supporting the fair market value of the land to be aoquired. Pursuant
to State law, if the property is $500,000 or less in appraised value, one appraisal is required.
If the property exceeds S500,000 in appraised value, two appraisals are required.
2 Amount .Authorized for Payment. The amount of Funding Allocation authorized for
payment for land acquisition shall in no case exceed the Funding Allocation available for the
Project. In the event that the negotiated .acquisition. price exceeds by ten percent or greater
the appraised value of the land, the disbursement of Funding Allocation shall be conditioned
upon a written justification for the purchase price and other conditions attendant to the
proposed purchase, which justification is declared satisfactory by the Board in writing.
Appraisal costs =are eligible Funding Allocation costs as long as the appraised property is
being realistically and .seriously considered for Acquisition, regardless of the outcome.
Buiiir,g Better Communities Administrative Rules
14 of 22
Environnjenial Surve-y. The Recipient may not acquire land fora BBC GOB Program
funded Project until a Phase 1 environmental survey is completed, which demonstrates that
the properly is suitable for its intended general use and for the specific Project GOB funds
may be used for the necessary clean-up a Phase 11 environment -al survey may require
provided the scope of the project is not impacted. Changes to the scope of the project
require BCC approval.
4 Signage. For sit: months following an Acquisition. the County shall post a 'sign, in the
general design provided by the County, containing the Building Better Communities
General Obligation Bond logo, identifying the source of Project funding. The cast of such a
sign is eligible for payment from the Funding Allocation.
5) Ownership. Title to land acquired with BBC GOB Program funds or facilities
constructed/developed with Building Better Communities General Obligation Bond funds
shall vest with a Public Agency or a legally incorporated 50l (c)(3) not -for -profit
Community -Based Organization,
E) Deveioprrrent Protects. Guidelines and requirements for administering Development Project
Funding Allocations are as follows:
1) Licensed Contractors; Contractor Bonds. Duly licensed contractors shall perform all
construction. Construction contracts for work in excess of the threshold am-ounts established
in Section 255.20 of the Florida Statutes shall require payment and performance bonds,
which comply with the requirements of Section 255.05, Florida Statutes.
2) Cost Elements.
a) Construction Equipment. Recipients are required to use their own equipment, if
available. If a Recipient's equipment is used; the maximum Funding. Allocation
payment shall cover operating and routine maintenance costs of such equipment; the
Funding Allocation excludes any depreciation or replacement cost from payment. If -a
Recipient's equipment is used, a report or source document must describe the work
performed, indicate the hours used and be rebated to the Project. If a Recipient does not
have needed construction •equipment available, then the Recipient may rent such
equipment.
b) Construction Supplies and Materials. Supplies and materials may be purchased for a
specific Project or may be drawn from a central 'stock, providing they are claimed at a
cost no higher than that which the Recipient paid. \\hen supplies and/or materialsaare
purchased with the intention of constructing a piece of equipment, structure or part of a
structure, the costs that are charged -as supplies and materials may be capitalized
•according to the Recipient's normal practice or policy. if capitalized; only the cost
reasonably attributable to the Project may be claimed under the Project.
c) Persoruie] or Employee Services. Services of the Recipient's employees who perform
work directly related to the accomplishment of the Protect are eligible costs payable
from the Funding .Allocation. These costs must be computed according to the
Recipient's prevailing wage or salary scales and rnav include fringe 'benefiit'costs, such •as
vacations, sick leave, FICA, MICA, health and life insurance, and workers compensation
Building Fever Corrrtur.i;ies Adnair.strativ.c Ru1e�
15 of22
at the Recipients established fringe benefit rate. Costs charged to the Project must i e
computed on the basis of actual time spent on the Project, and supported by titne and
attendance records describing the work performed on the Project. Overtime costs may
be allowed under the Recipient's established policy, providedthat the regularwork time
was devoted to the same Project. Salaries and wages claimed for employees working, on
allocation -funded Projects must not exceed the Recipient's established rates for similar
positions or rates per industry standards. Alternative methodologies for established
wage rates must be pre -approved by the Board.
d) Consultant Services. The costs of consultant services necessary for the Project are
eligible for payment from the Funding Allocation. The Recipient .must pay :consultants
according to the Recipient's customary or established method and rate. No consultant
fee may be paid to the Recipient's own employees.
3) Cost Activities.
a) Construction activities. The .cost of all necessary construction activities, from site
preparation (including demolition, survey, excavation and othersite work) to the
completion of a structure is eligible for payment from the Funding Allocation.
b) Fixtures; Furniture and Equipment. The cost of Fixtures, Furniture and Equipment
necessary to operate the facility are eligible for payment from the Funding Allocation if
approved in the Grant Agreement or the Interlocal Agreement, as the case may be, and a
detailed list of eligible items is submitted in writing and -approved by the County
Manager prior to its purchase (See Article III, Section I (c)). Costs for consumable
goods shall not be considered eligible for payment from the Funding Allocation. Also,
refer to Article I. Section A for a detailed definition of Fixtures, Furniture and
Equipment.
c) Interpretive Signs and Aids. The cost of signs, display boards or other interpretive .aids
relating to the Project art eligible for payment from the Funding Allocation.
d) Signage. During the time period of Development, the County shall post a sign in a
prominent location at the Project site in the general design provided by the -County
depicting the Building Better Communities General Obligation Bond logo and
identifying the source of funding for the Project. The cost of such a sign is eligible for
payment from the Funding. Allocation.
Recipients are encouraged to use value -engineering clauses in contracts for constriction
projects ofsufficient size to offer reasonable opportunities for -cost reductions.
4) The following is a nonexclusive list of costs ineligible for payment from the Funding
Allocation:
a) Funding Application costs.
b) Ceremonial expenses.
c) Expenses for publicity.
ilding Beim. Crrrununizier AdrrLnistrauve Rules
lbof22
d) Bonin payments unless specifically authorized by the Board.
e) Charges in e>:cess of the lowest responsive and responsible bid or proposal in accordance
with the governing rules and procedures of the Recipient, when the law requires the
Recipient to utilise competitive selection. in the event a selection process is used, other
than a low bid process any cost in excess of the cost of the highest ranked firm shall be
considered ineligible.
f) Charges for deficits or overdrafts.
2) Charges incurred contrary to the policies and practices of the Recipient.
h) Interest expense (May be reimbursed at the discretion of the Board if incurred during the
construction period arid is attributable only to the construction period).
i) Litigation expenses or judgments.
j) The cost of services, material or equipment obtained under any other program.
k) Costs of discounts not taken.
]) The cost of purchasing a non-refundable option when acquiring land.
F) Budget Changes.
1) Recipients shall adjust their Project budgets to reflect actual costs and updated cost estimates
and shall submit adjusted Project budgets to the.County Manager as soon as the recipient is
aware of a material budget change.
2) Budget adjustments may not exceed the ] 7% Soft Cost limitation for design, planning, and
program administration; nor exceed the Project Funding Allocation without approval of the
Board.
3) Recipients shall obtain the prior written approval of the Board whenever budget adjustments
are anticipated as outlined in a, b, and c below. The request must be in the same budget
format the Recipient used in the Grant Agreement or lnterlocal Agreement, as the case may
be, and shall be accompanied by a narrative justification for the proposed revision. Such
request for adjustment shall, if approved, amend the 'Grant Agreement or Interioca!
Agreement; as the case may be. Requests for budget changes shall be considered whenever
any of the following adjustments are required:
a) For any Project involving both .Acquisition and Development activities, any proposed
budget transfers from Deve]opment to Acquisition.
b) Any proposed reduction or revision of the scope or objectives of the Project (regardless
of whether there is an associated budget adjustment) that substantially changes the original
intent of a project.
Building Setter Corrmunis±es Adn-anistrstive Rules
17 of22
c1 Any change that would increase •Soft Costs for planning, design, and project
administration which exceeds the limit specified in Article 11] Section 3 (0(1)
In the event that a Recipient has completed the approved scope of work for a Project and has
unexpended funds, the Recipient may submit a request to the County Manager's Office to expend
these funds in an existing or new budget line item for the Project. The County Manager is
authorized to approve such budget changes and expenses not to exceed I `%o of the total budget.
G) Cost Overruns. Durine the execution of Nvork on a Project, the Recipient may find that actual
Project costs exceed the approved budget. For cost overruns that will require additional funding for
the Project, or otherwise require a budget adjusttnent for which prior Board approval is requited
pursuant to paragraph E above, the Recipient shall:
1) Provide a justification for the additional costs;
2) identify available. funds for the completion of the Project; and; if necessary
3) Request from the Board a change or revision in the Project scope consistent with the
terms of the Ordinance.
The Board, at its discretion, may authorize in writing a change or revision in the scope of the
Project: (i) where change or revision of the scope is consistent with the Ordinance; and (ii) where
the change or revision is justified by the Recipient; and (iii) where the Recipient does not have
sufficient funds to complete the Project. with the available funds. Under those circumstances. the
Board, in its sole discretion, may identify other funds available under the Ordinance for -the Project. —
SECTION 2. COMPLIANCE RESIPONSIBILITIES
The following constitute general requirements for program compliance:
A) An annual independent audit of the Building Better Communities General Obligation Bond
funds must be submitted by all Recipients to the County Manager's Office no faller than six
months after the close of the Recipient's fiscal year for which a Funding Allocation was
received and each year thereafter until Project completion. The audit report must include the
Fund Summary Status Report; Exhibit J. The audit must be performed by certified independent
auditors and include the following:
1) Test for compliance with the Grant Agreement or Interlocal Agreement, as the case rraay be,
Miami -Dade County Ordinance No. 05-47, applicable resolutions and the Building Bette!
Communities General Obligation Bond Administrative Rules.
2) Test to verify compliance with advance requirements.
3) Sufficient tests, as determined by the independent auditor to verify true -and ,accurate
reflection of Project expenditures.
4) Tests to verify expenditure of required match dollars.
5) Verification of the Fund Summary Status Repr,ii.
Building ]✓tile! Conan un3;:es Adm;nisin:Ive Rules
18of22
B) Land and facilities acquired. developed, improved or rehabilitated by Funding Allocation shall
be dedicated and maintained in perpetuity for the use and benefit of the general public except
where leases are in effect. Any land, facilities, or equipment acquired with Building Bettor
Communities Genera] Obligation Bond funds may not be 'sold or transferred without the written
consent of the County and may require an equitable reimbursement of bond funding based on
residual value. All projects shall be open to the public at reasonable threes and s iall•be managed
in a safe and attractive manner -appropriate for public use.
C) Funding Allocation for the. purposes of development, improvement, rehabilitation or restoration
shall be expended for these purposes only on lands owned by a Recipiertt•or on lands for which
the Recipient holds a lease or other use agreement. Such lease or other use agreement must be
for an unexpired minimum term of 25 years. The Funding Ai-ocation Recipient may
demonstrate the eligibility of the Project to the reasonable satisfaction of the Board, through a
joint ownership, use, franchise or other agreement, evidencing that the lands and/or the Project
will be utilized for the public benefit, consistent with the terms of this Ordinance, for a term of
at leas' 25 years in duration. The lease must not be revocable at will.
D) Recipient shall maintain all financial and programmatic records, supporting documents and
other records pertinent to the Funding Allocation for a period of three years :from the starting
date defined below. if any litigation, claim, negotiation, audit or other action involving the
records has been starved before the expiration of the three year period, the records must be
retained until completion of the action and resolution of all issues which arise •f rorn it, or until
the end of the regular three year period, whichever is later. When Funding Allocation support is
continued or renewed al annual or other intervals, the retention period for the records .of each
funding period stares on • the day the Recipient submits to the County its single or last
expenditure report for that period. In al] other cases, the retention period starts on the day the
Recipient submits its final expenditure report.
E) The Board and the County, or any of their authorized representatives, shall have ,the right of
access to any pertinent books, documents, papers or other records of the Recipient in order to
make audits, examinations, excerpts and transcripts.
Office of the Miami -Dade County inspector General (1G) (MDC Code Section 2-1076) shall
have the authority and power to review past, present and proposed County programs, accounts,
records, contracts and transactions. The lG -shall have the power to subpoena witnesses,
administer oaths and require the production of records. Upon ten (10) days written notice to the
Recipient from 1G, the Recipient shall make all requested records and documents available to
the 1G for inspection and copying. The 1.G shall have the power to report.and or iecornmend to
the Board whether a particular project, program, contract or transaction is or was necessary and,
if deemed necessary; whether the method used for implementing the project or program is or
was efficient both financially and operationally. Monitoring .of an existing project or program
may include reporting whether the project is on time, within budget -and inconformity with
plans, specifications. and applicable law. The 1G shall have the power to analyze the need for,
and reasonableness of, proposed change orders.
The iG may, on a random basis, perfon-n audits on all County contracts throughout the duration
of said contract (hereinafter "random audits"). This random audit is separate -and distinct from
any other -audit by the County. To pay for the functions cf the Office of the Inspector General,
Building Better Con-muniiits Administrative Rules
19of_2
an, and all payments to be made to the Recipient under the Grant .Agreement wi;ll.be.assessed
one quarter of one percent of the total amount of the payment,, 4o be deducted . from each
progress payment as the same becomes due unless, as stated in the Code cr the Grant
.Agreement, the Project is federally or state funded and federal or state iew .,or regulations
preclude such a charge. The Recipient shall in stating its agreed prices be mindful of this
assessment.
The IG shall have the. power to retain and coordinate the services of an independent private
sector inspector genera] (IPSJG) who may be engaged to perform said random audits, as well -as
audit, investigate, monitor, oversee; inspect, and review the operations, activities and
performance and procurement process including, but not limited to, project design,
establishment of bid specifications, bid submittals, activities of the contractor, its ,officers,
agents and .employees, lobbyists. County staff and elected officials in order to ensure
compliance with contract specifications and detect corruption and fraud.
F) ]f a Recipient materially fails to comply with, any term of an award, the Board or the County
Manager may lake one or more of the following actions; as appropriate inthe circumstances:
]) Temporarily withhold cash payments pending correction of the deficiency by the Recipient;
2) Disallow all or part of the cosi of the activity or action not in complianee;
-) wholly or partly suspend or terminate the current award for the Recipient's Project;
4).-Withhold further Funding Allocation awards from the Recipient; or
5) Take other remedies that may be legally available.
G) Any of the enforcement actions listed in paragraph F above, taken by cite County -Manager,
which are contested and unresolved between the Recipient and the County within Marty days of
such action, will result in the Board providing the Recipient with an oppottunityto be heard on
the issue. Said hearing will occur within sixty days of the Board receiving the Recipient's
written request. Staff will recommend appropriate action to the Board.
H) Costs to Recipient resulting from obligations incurred by the Recipient during a suspension or
after termination of an award are not eligible for reimbursement unless he County Manager
expressly authorizes them in the notice of suspension or termination or -subsequently authorizes
reimbursement in writing. Other costs incurred by the Recipient during suspension 'or after
termination which are necessary and not reasonably avoidable are eligible for reimbursement if:
]) The costs result from obligations which were properly incurred by the Recipient before the
effective date of suspension or termination, were not in anticipation of it, and.in the case.of a
termination, are non -cancelable; and
2) The costs would be eligible for reimbursement if the award was not suspended or if the
award expired normally at the end of the funding period in which the termination takes
effect.
I) Inspections. Staff of the Board or the County, or both, shall periodically inspect each Project to
•Euiddine Fetter Communities Adminintative Rules
20 of 22
ensure compliance these rules, the Ordinance, and the Grant Agreement or lnterlocal
Agreement, 4. the case may be. Staff shall perform an inspection of the Project site to ensure
compliance prior to release of the final Funding Allocation payment.
SECTION 3. REPORTS
Recipients are required to submit the Project Status Report no dater than monthly (Exhibit E), in the
formai stipulated by the County Manager. Additional reports that shall be due upon request of the
County Manager may include, but are not limited to:
.A) Actual accomplishments of each Funding Allocation;
B) Problems encountered in implementation ofeach Funding Allocation; and
C) Anticipated start and/or completion dates of each Funding Allocation.
Recipient may be required to meet with the Board to discuss the Project.
SECTION 4. PROJECT CLOSE-OUT
A) A Recipient has up to forty-five (45) days after the expiration or termination of the Fundine
Allocation to submit all final documentation including final reimbursement requests and project
completion certificates.
B) The close-out of a Funding Allocation does not affect:
1) The County's right to disallow costs and recover funds on the basis of a later -auditor review;
2) The Recipient's obligation to return any funds due as a result •of later refunds; corrections •or
other transactions;
3) R.ecords retention responsibilities set forth above;
4) Continuing responsibilities set forth in the Ordinance and these rules; and
5) Audit rights set forth in these rules.
C) Any amounts paid to Recipient in excess of the amount to which the Recipient is finally
determined to be entitled under the terms of the Grant Agreement or lnterlocal .Agreement; as
the case may be, constitute a debt to the County. If not paid within a reasonable period after
demand, the County may reduce the debt by:
1) Making an administrative offset against other requests 'for reimbursement;
2) Withholding payments otherwise due to the Recipient; 'or
3) Takingother action provided by law.
Any overdue debt of the Recipient shall accrue interest at the maximum rate allowed by law.
"SECTION 5. INTERPRETATION; ADMINISTRATION
These administrative rules have been promulgated under the Ordinance. In the event of a conflict
. uildi•rag Better Con mriiie5 AdministTmrive Rules
21 of 22
between these rules and the pro', isicrns cif the Ordinance, the Ordinance shall prevail.
The County Manager.shall he authorized to interpret the provisions of these administrative rules -and
their interpretation of any rnatters governed hereby shall be :final and may only ,oventurned by a
majority vote of the Board. The County Manager shall submit recommendations emending these
administrative rules to the Board, which may approve or reject such recommendations by majority
vote.
The County Manager shall be authorized and required to administer the Building Better
Communities General Obligation Bond Program consistent with the Ordinance and these:
administrative males.
--- Building Bette! Communities Administrative Rules
22 Of 2'?: