HomeMy WebLinkAboutSite Utility StudyD. SITE UTILITY STUDY MIADOCS 888978 I Fekruary 2006 TIZIANO II MAJOR USE SPECIAL PERMIT SITE UTILITY STUDY PREPARED FOR Edgewater, LLC. KHA Project No.: 0427850001 Prepared by: KIMLEY-HORN AND ASSOCIATES, INC. 1691 MICHIGAN AVENUE, SUITE 400 MIAMI BEACH, FL 331.39 INKimley-Horn and Associates, Inc. Site Utility Study Introduction Tiziano 11 is a proposed mixed -use development to be located on the north-east comer of NE 4th Avenue and NE 23rd Street, in the City of Miami, Florida (see Site Location Map -Fig 1). The Tiziano 11 project shall consists of a multi -use tower on a single podium with a pool deck, office, retail and lobby space. The ground -level will include streetscape improvements, perimeter plantings and a landscape plaza. Table 1, below depicts the details of the proposed project. Table 1: Project Summary Retail 2,385 Office Space 8,150 Lobby & Corridors 3,182 Apartment 55 Cabanas @ Pool Deck 1,808 Parking (Gross) 98 I. Drainage Existing Drainage There is no visible on -site drainage system. The subject site sheet flows into the adjacent right of way and percolates into ground water table. Tiziano II Site Utility Study Page 2 Figure 1:, Site Location Map NE 25TH ST 1-- U z N w z Q rn NE 24TH ST w }- U cn m 23R1 TE 3RD ST 2ND TE NE 22N! ST NE 21 ST ST a w( PROPOSED PROJECT Proposed Drainage System The drainage system for the proposed development will consist of drainage wells, if possible, to facilitate on -site disposal of storm water runoff. The 5-year design storm event will be used to design the storm water management system, in accordance with Section D-4, "Water Control", of Part 2 of the Miami -Dade County Public Works Manual. Based on preliminary calculations, it is anticipated that thee (3) 24" drainage wells will provide sufficient capacity to dispose of the design 5-year 24-hour storm water runoff generated by the proposed development. Preliminary drainage computations for the project areas are provided in Attachment "A" Preliminary Drainage Well Calculations, which includes the basis for design. The final drainage design for the project should be in conformance with the requirements of the Miami -Dade County DERM Water Control Section, Florida Department of Environmental Protection, and other local, State and federal regulatory agencies having jurisdiction over the project. Tiziano II Site Utility Study Page 3 II. Water Distribution System The water mains owned and operated by the Miami -Dade Water and Sewer Department (MDWASD) in the vicinity of the project is shown in the Table 3. Table 3: Existing Water Mains NE 231d Street NE 4th Avenue and east side of the project 6" NE 23rd Terrace NE 4th Avenue and east side of the project None NE 4`h Avenue NE 23rd Street and NE 23rd Terrace 6" and 12" Per the MDWASD Water Atlas Sheet, a 12" water main fronts the property along NE 4th Avenue. In accordance with Miami -Dade Water and Sewer Department (MDWASD) criteria, the developer may be required to extend a new 12" water main along NE 23td St. (fronting the property). A final determination of the points of connection and requirements will not be provided by MDWASD until Water and Sewer Agreement is requested by the owner. Water service meters would need to be purchased at the owner's expense and installed by MDWASD forces. See Attachment "B" for a copy of the MDWASD water atlas sheet for the project area. III. Sanitary Sewer Collection System Table 4 depicts the sanitary sewer mains owned and operated by Miami -Dade Water and Sewer Department (MDWASD), within the vicinity of the project. Tiziano II Site Utility Study Page 4 OcatioY1.:;..:; NE 23`d Street Table 4: Existing Sanitary Sewer Mains Between NE 4th Avenue and east side of the project Sanitary Sewer Alain(s) N/A NE 23`d Terrace NE 4th Avenue and east side of the project 8" Gravity Main NE 46 Avenue NE 23`d Street and NE 23`d Terrace 72" Gravity Main The existing 8" gravity sanitary sewer main along NE 23'd Terrace may have sufficient capacity to accommodate the proposed development. However, this can not be verified until a downstream analysis of the existing 8" gravity line is completed. A letter of availability and further coordination with MDWASD is recommended to verify the proposed sanitary sewer service connection points and requirements for this project. MDWASD may require upgrades to the sanitary sewer system, but this can not be determined without a request for a water and sewer agreement. A copy of the MDWASD Sewer Atlas sheet has been attached (See Attachment B). MDWASD Pump Station #2 receives the flows from these mains. As of O1/06/06, this pump station is operating at an average yearly NAPOT hours of 3.02 which is 48% of its design capacity. Therefore, a new sanitary sewer pump station or upgrades to said pump station may not be required for the proposed development. A final determination regarding the status of the existing transmission system and the need for possible improvements will not be made until construction plans are submitted to the Miami -Dade County DERM Wastewater Section and a Sanitary Sewage System Capacity Certification Letter is issued. Please refer to Attachment "B" for the sewer atlas and Attachment "C" for Pump Station Monthly Information. Tiziano II Site Utility Study Page 5 Type f Occupancy Apartment Table 5: Water & Sewer Flow Generation 55 units 200 gpd per unit Total Average. Daily flow (gpd) 11,000 Retail 2,385 sf 5 gpd per 100sf 119 Office pace 8,150 sf 10 gpd per 100sf 815 Total Anticipated Flow 11,934 IV. Solid Waste Generation Solid waste generated by this project will be collected in standard on -site containers for refuse and recyclables. Regular pick-up service will be provided either by private hauling companies and/or by the City of Miami Solid Waste Department, who will transport the waste to Miami -Dade County' s or private disposal and recycling facilities. The volumes of solid waste projected to be generated by the project are shown in Table 6. Apartment Table 6: Solid Waste Generation 55 units 5 lbs/unitlday 0.138 Retail 2,385 sf 3 lbs/1000 sf/day 0.004 Office pace 8,150 sf 6 lbs/1000 sf/day 0.025 Total Anticipated Solid Waste Generated 0.167 Tiziano II Site Utility Study Page 6 Attachment A Preliminary Drainage Well Calculations TIZIANO II City of Miami, Florida )RAINACE CALCULATIONS: DRAINAGE WELLS (MASS DIAGRAM — DERM CRITERIA) 1. Site Data: A. Average Control Water Elevation (NGVD) _ B. County Flood Criteria Elevation (NGVD) = C. F.I.R.M. Base Flood Elevation (NGVD) D. Lowest proposed inlet elevation (NGVD) = 2. Total Property Area : A. Impervious Areas: a) Asphalt and concrete pavement = b) Roof areas = c) 1/3 of the NE building corner = Total Impervious Area (A) = B. Pervious areas: a) Green Areas = C. Total Contributing Area = 3. Weighted Runoff Coefficient (C): Runoff Coefficient Impervious (C 1) = Runoff Coefficient Pervious (C2) = C = [(Al x C1) + (A2 x C2)] / A; C x A = Total Contributing Area; C= CxA= 0.370 Acres Acres Acres Acres (in excess of property area) 0.835 Acres Acres Acres 0.890 0.76 Acres 4. Time required to generate one inch of runoff (per DERM Water Control Section D-4) Rainfall Intensity (I) = 308.5 / [(48.6 x F°'1 I) + t (0.5895 + F25)] Frequency (F) = e ;;;?rv'J '; ' years - Frequency Curve Q = CIA, V = Qt; Vey ; = Qtp ;n_), to ;= Time to generate 1 inch of runoff Vt2 in.) = CIAto in.) 1"xA=CIAt(I;,,) Solving for tit to in.) = 1" / (IC) Time to Generate one inch of run-off t(in) = 11.18 Min. Time to reach the inlet (tc.) -;;:`Min, Total Time required to generate 1 in of runoff: = 21.18 Min. D-WELLS.xls BASIN 5. Cumulative Runoff (Inflow Mass Diagram) Time CxA (acres) I (inches) Q (CFS) Accumulated Storm Runoff (CF) Min) Sec.) 8 480 0.756 6.405 4.84 2,325 10 600 0.756 6.166 4.66 2,798 15 900 0.756 5.641 4.27 3,839 21.18 1271 0.756 5.104 3.86 4,904 30 1800 0.756 4.493 3.40 6,115 40 2400 0.756 3.956 2.99 7,180 50 3000 0.756 3.534 2.67 8,017 60 3600 0.756 3.193 2.41 8,693 90 5400 0.756 2.477 1.87 10,113 120 7200 0.756 2.023 1.53 11,014 180 10800 0.756 1.480 1.12 12,089 6. Drainage Well Design Discharge Rate: Based on well discharge rate of: filAtia* GPM/ft. Head WeU No. DW-1 Lowest inlet Rim (NGVD) • 9.00 Oct. Water Table elev. (NOVI)) 2.00 lleadloss due to Higher SG of Salt Water 2.20 Head Acting on Well (ft.) 4.80 Vett:Discharge. Rate (CPS). 4.28 DW-2 DW-3 9.00 9.00 2.00 2.00 2.20 2.20 4.80 4.80 4.28 4.28 Well'Sutnre DiMeaskals wigtii-(fL.) Length (ft.) AT:171-7,00-g-Ef Well Structure Storage Volume (CF) 192 192 192 Well Discharge Rate (CFS)1 8.56 7. Detention Time: Total Storage (CF) The drainage well structure must be designed to detain runoff for a minimum of 90 seconds prior to discharge. Qd = Design Runoff Rate (CFS) = Vd = Detention Volume (CF) = Qd x 90 sec. = Vdi = Detention Volume Per Well (CF) = W = Width of Well Structure (ft.) = L = Length of Well Structure (ft.) = 3.86 CFS 347.34 CF 115.78 CF 5.0 ft. 8.0 ft. 384.00 }lin is the minimum depth required from the top of well casing to the floor of the well box to achieve 90 second detention time: 1-1„11„ (ft.) = Vdi ( W x L) = 2.90 ft.=Depth from top of casing to bottom of well box 8. Excess storm water runoff excluding well structure storage: Time: , Well Discharge Rate (CP'S),. Accumulated: Well Discharge Volume (CP) _ Accumulated : Storm Runoff (CP) Total Overflow Volume (CP) (Min.) (Sec.) 8 480 8.56 4,107 2,325 -1,782 10 600 8.56 5,134 2,798 -2,336 15 900 8.56 7,701 3,839 -3,862 21.18 1,270.70 8.56 10,872 4,904 -5,968 30 1800 8.56 15,401 6,115 -9,286 40 2400 8.56 20,535 7,180 -13,355 50 3000 8.56 25,668 8,017 -17,652 60 3600 8.56 30,802 8,693 -22,109 90 5400 8.56 46,203 10,113 -36,090 120 7200 8.56 61,604 11,014 -50,591 180 10800 8.56 92,406 12,089 -80,317 9. Excess storm water runoff including well structure storage: i.): 8 10 15 21.18 30 40 50 60 90 120 180 :(S 480 600 900 1,270.70 1800 2400 3000 3600 5400 7200 10800 Accumulated Storm:Runoff (CF) 2,325 2,798 3,839 4,904 6,115 7,180 8,017 8,693 10,113 11,014 12,089 Storage in Well Structure (CF) . . 384 384 384 384 384 384 384 384 384 384 384 Accumulated Well,. Discharge Volume (CF) 4,107 5,134 7,701 10,872 15,401 20,535 25,668 30,802 46,203 61,604 92,406 Total Overflow. Volufi (CF) -2,166.39 - 2,720.18 -4,245.65 -6,352.29 - 9,669.76 -13,739.07 -18,035.56 -22,493.49 -36,473.77 -50,974.77 -80,700.98 Safety Factor Safety Factor 2.22% 2.30% Attachment B Existing Utility Records *W. /.•••' 92 \ NE 25 ST • 9 1537 7 2 t-10" 9 II 79 a a, !622 1 91 f5371 so isNE 24 ST 2778 1 7 81 • El' 1 0 87 I 2620 '77 62/ 83 NE 23 CT / NE 23 ST-/ '----ThC: ." 1 2777 / {,1 1 13 ,. 4 86 SEWEa, ISTLAS 306 806 I4OP CL C'J z _1co crs wa-V2 1flU3 (Iz) 10881 2 604 \ 72 18s Ws r DIN 20O4—013 --' PLOTTED - K.F. 2/11/04 iv ;., 1( 604 y 79.i 9642 1 7916 Li? 1.1.1 1 (7815) NE 25 ST NE 22 TER /628 NE23CT 2 (I -io- 06) d4 f4 Attachment C Pump Station Monthly Information PLII-1113 StahonNunlhly Infoirnation Pump Slalom 3041047lacePegm MIALISDADEWATERIEWERDEPAATMEAT ""ts, AtitAMSAFJEta,041pai-E-Piag:,7.i„ Saction-Tomsrhip-Rang0 • Ig TOW Clat Krks 5yersdt Number of Puma: 5 Yea414APO T Tryst 3.62 lie, BomktpdT 2.570.260 NAN spot 4.11 hut X Cap 49 Generatar User: reArlIdd MIAMI-DADE Momimium it'll...I NICE blattl$N 'ifne,on....114NYWY Telemetry FM ET clock EN SINGtosarmacitylupd1 57.606E0 StreirmIlmItyMen Fadm 6 Stella. Cap Cert0Typrl SWIM Capactrigpl 34.560,000 IntrmatealFlowslgyel 4.340-000 ibo26r2005.1.95 .058D. . ILY . • 5 • .. ..,... : IRODSR .. . liV.i.1.1k :814111)Sli W.0030 .. ......,,:7.777.:.-,7-...3t.,:73.!'n.,-.:33.3--.•m•,..,3•52.4.Yrrotre.:Elstrm.e3,...YYYM-irt:ttmmtilmm.......„.. t....4.41mY..- ;.:,40,,,m.,.-:,-.,:-P,,,-...--- - " • EV2612005 200 11.19 '•5 -127* 6r23,02005 L,3.011 14.72. iY 5. Date: Mo.14APOT ADer3, Rik F10 a Purer Cesereentr- 060 Attachment D Maps 4 IIMI Kimley-Horn and Associates, Inc. 1691 Michigan Avenue Suite 400 Miami Beach, Florida 33139 Phone: 305-673-2025 Fox: 305-673-4882 TIZIANO 11 FLOOD CRITERIA MAP _ 1 4 NAN IS [43r S12L •kPTO #i f342 GT61 tvrtics pIY itt 4 CT IAws•ts •;e 4 6ND: r-wf (ESTJI4ATED) [NOTES 1. CONTOUR OUR INTERVAL 10 -FOOT (Except o* indicated) 2- DATUM IS MEAN $EA LEVEL. Kimley-Horn and Associates, Inc. 1691 Michigan Avenue Suite 400 Miami Beach, Florida 33139 Phone: 305-673-2025 Fax: 305-673-4882 TIZIANO !I AVERAGE OCTOBER GROUND WATER LEVEL 1960-75