Large Scale Development Review -
2121 Biscayne Boulevard
REFERENCES:
ENCLOSURES:
The Public Works Department has reviewed the Large Scale Development plans for the
development entitled 2121 Biscayne Boulevard and has the following comments.
1. A 25 foot corner radius dedication is required at the intersections of the
base building lines at N.E. 215t Street with Biscayne Boulevard. The
proposed stairs are not permitted to encroach beyond the 25 foot corner
radius.
2. The proposed structure and stairs encroach into the required corner
visibility triangle at the corner of Biscayne Boulevard and N.E. 21st Street.
The Lobby level at 3 ft. above grade is not permitted to encroach into the
25 ft. visibility triangle.
3. All transitions from the established street profile grade to the building
floor elevation must be accomplished on private property. Stairs, ramps,
retaining walls, etc. will not be permitted in the public right of way and the
record profile street grade can not be changed to accommodate the
proposed building ground floor elevation.
4. All stormwater must be retained on site including the driveways, interior
courtyards and plazas on private property adjacent to the public streets.
All common areas, plazas and driveways must be graded or trench drains
provided to prevent "sheet flow" from entering the right of way. If deep
drainage wells are selected for stormwater disposal, they must be located
on -site in an open area to accommodate future maintenance access.
5. An agreement between the City of Miami and the property owner is
required for any landscaping and decorative sidewalk treatment located in
the public right of way. Public Works approval and permit is required for
any landscaping improvements in the right of way. A F.D.O.T. permit is
required for improvements along Biscayne Boulevard.
6. Standard parking spaces are 8.5 feet wide and 18 feet long and require a 23
foot back-up distance. A Special Permit is required to reduce the back-up
distance and for backing into the loading stall from the right of way.
Ana Gelabert-Sanchez
Director
Planning Department
Page 2
January 25, 2006
7. The maximum driveway approach width is 40 feet. City of Miami
driveway entrances, in compliance with A.D.A. standards, shall be
required. Continuous sidewalk is required across driveway entrances.
8. Public Works policy requires that no closures of vehicular travel lanes will
be permitted during the course of construction unless a temporary
replacement lane, approved by the Public Works Department, is
constructed and maintained by the Contractor throughout the duration of
the lane closure. A maintenance of traffic plan is required for any
temporary right of way closure request.
9. In order to mitigate traffic congestion and problems associated with
unregulated parking throughout the neighborhood, the
Contractor/Developer shall be required to provide approved, designated
off -site parking for workers and a shuttle service to the work site. The
parking/shuttle plan shall be coordinated with the local City of Miami
NET Service Center.
10. Since this project is less than one acre in total construction area a Florida
Department of Environmental Protection (DEP) Stormwater, Erosion and
Sediment permit is not required. However, the methods of construction
must comply with the City of Miami Municipal Separate Storm Sewer
Permit (MS4). For information concerning these requirements, please
contact our department at (305) 416-1200.
In addition to these comments, the Public Works Department will require the following
street improvements:
N.E. 215t Street: Construct new concrete sidewalk, curb and gutter along the 25' required
corner radius. Replace all broken sidewalk, curb and gutter on both sides of the street
adjacent to the project site. Mill and resurface the entire width, curb to curb, adjacent to
the project site. Coordinate improvements with the "Paramount" development.
Biscayne Boulevard: Construct new sidewalk at the corner with N.E. 21 Street in order
to comply with the 25 foot corner radius dedication requirement. Coordinate with the
Florida Department of Transportation for replacement of all broken and damaged
sidewalk and curb and gutter adjacent to the project site. Please contact the City's
Planning Department and the City's CIP/Transportation Department for any Burle
Marx Decorative Sidewalk implementation requirements.
In addition, pavement restoration for all water and sewer extensions, existing damaged
pavement and pavement damaged during construction, as determined by the City
inspector, shall include milling and resurfacing of the full pavement width, curb to curb,
along the entire length of the excavation and/or damaged pavement area. A thorough
cleaning of all stormwater drainage inlets and storm sewer pipes adjacent to the
building site shall be required at the completion of the project. The streets and avenues
adjacent to the project site must be clear of dust and construction debris at all times. A
Ana Gelabert-Sanchez
Director
Planning Department
Page 3
January 25, 2006
handicap ramp, in compliance with ADA standards, is required at the corner adjacent to
the project site.
If you have any questions concerning these comments, please call Elyrosa Estevez,
Professional Engineer III, at extension 1217.
SNG/LJH/EE
c: ARCHITECTONICA
801 Brickell Avenue Suite 1100
Coral Gables, Florida 33131
Stephanie Grindell, P.E., Director of Public Works
Lourdes Slazyk, Assistant Director, Planning Department
Manuel A. Vega, P.E., Zoning Department