HomeMy WebLinkAboutArticle II - Project Description2121 BISCAYNE BOULEVARD
MAJOR USE SPECIAL PERMIT
PROJECT DESCRIPTION
ARTICLE 1I.
Project Description
A. Zoning Ordinance No. 11000
1. Section 1304.2.1 Application forms; supplementary
materials
2. Section 1702.2.1 General Report
3. Section 1702.2.2 Major Use Special Permit Concept Plan
4. Section 1702.2.3 Development Impact Study
•
•
•
•
•
MAJOR USE SPECIAL PERMIT
Section 1304.1.1 Application forms; supplementary materials
(a)
Statements of ownership and control of the proposed development of
activity.
The Disclosure of Ownership and Ownership Affidavit are provided in Article
I .
(b) Statement describing in detail the character and intended use of the
development or activity.
2121 Biscayne Boulevard (the "Project") is a mixed -use project designed by
Arquitectonica International Corp.
The proposed 2121 Biscayne Boulevard will be constructed on a site
located on the east side of Biscayne Boulevard at N.E. 21st Street, City of
Miami. The site has a Net Lot Area of 42,884 sq. ft. (0.98 Acres) and a
Gross Lot Area of 59,485 sq. ft. (1.36 Acre) with a zoning designation of C-1
with an SD-20/SD-20.1 Overlay.
The 16-story project will contain a total of 147 condominium units on the top
11 levels; 46,400 sq. ft. of office space on 4 levels and 6,682 sq. ft. of
retail/restaurant space on the ground level. A parking garage, accessed
from NE 21st Street with 376 parking spaces and an enclosed loading area
and building services (including enclosed trash room), is to the east side of
the building and is fully screened from Biscayne Boulevard by the
office/residential building.
The Project program and building design respond to the mixed -use urban
characteristics of this portion of Biscayne Boulevard, which has mid -rise
office buildings (including the historic Bacardi Building across the street),
residential buildings and commercial buildings. A covered entry plaza is
carved out of the building at the corner of Biscayne Boulevard and N.E. 21st
Street, creating a spacious entry to both the restaurant that extends along
the entire Biscayne Boulevard frontage and the lobby for the residential and
office levels. At the north end of the site along Biscayne Boulevard, another
plaza is created that provides outdoor seating for the restaurant. The
project provides an additional 5' of width to the existing 17' wide R.D.W.
sidewalk, creating a spacious pedestrian experience with landscaping and
paving provided in coordination with the FOOT Street Improvements and the
City of Miami Public Works Department.
The office levels of the tower extend the full length of Biscayne Boulevard
and approximately two-thirds of the N.E. 21st Street frontage, providing a
fully occupied liner along Biscayne Boulevard and most of N.E. 21st Street.
The elevation treatment of the office levels is echoed in the elevation
treatment of the three exposed sides (south, east and north) of the garage,
with the only change in material being the substitution of open louvers
•
instead of the glazing, while still maintaining the accent metal panels and
vertical fins of the elevation design.
Above the office levels, the elevations of the residential levels are designed
with the same materials and have a similar two story grid overlay as the
office levels while still providing a distinct personality with the provision of
asymmetrical balconies and sliding glass doors instead of full storefront
glazing. The west half of the garage, adjacent to the residential tower, is a
landscaped pool deck, providing outdoor amenities to complement the
indoor amenities.
The building height is as follows:
Ground Floor / Lobby: 28'-0" high, 2'-6" above grade
Office Component: 4 Levels a total of 53'-6" high
Residential / Amenities Level: 10'-6" high
Residential Component: 10 Levels a total of 112'-2"
The total building height from grade to top of roof is 206'-8".
Drawings showing the architectural character and location of the intended
uses are included under Tab 6 of the Supporting Documents.
(c) General location map, showing relation of the site or activity for which
special permit is sought to major streets, schools, existing utilities,
shopping areas, important physical features in and adjoining the
project or activity and the like.
The following exhibits are included with the Major Use Special Permit
Application:
(1) Aerial Location Map (A0.01): Aerial photograph of the surrounding
area indicating the project site.
(2) Aerial Context (A0.02): Enlarged Aerial photograph of the project
area indicating surrounding buildings and their relationship with the
project site.
(3) Site/Context Images (A0.03 — A0.05): Photos of the project site and
surrounding existing context.
(d) A site plan containing the title of the project and the names of the
project planner and developer, date, and north arrow and, based on an
exact survey of the property drawn to a scale of sufficient size to show:
The general information requested is shown on the Ground/Site Plan
(Al .01), provided under Tab 6 of the Supporting Documents. The site plan
includes the following:
•
•
•
(1) Boundaries of the project, any existing streets, buildings,
watercourses, easements and section lines;
The boundaries of the project and the location of existing
streets and easements are shown on the Survey located
under Tab 5 of the Supporting Documents.
(2) Exact location of all buildings and structures;
The exact location of all existing buildings located on the property is
shown on the Boundary Survey under Tab 5. The location of the
building to be constructed is shown on the Site Plan (A1.01),
located under Tab 6 of the Supporting Documents.
(3)
Access and traffic flow and how vehicular traffic will be
separated from pedestrian and other types of traffic;
Vehicular access for the project parking garage is at N.E. 21st
Street, as remote from Biscayne Boulevard and the pedestrian
entry as feasible. The service drive/access for the project, as well
as the loading areas and building service areas, are internalized in
the building and street access is provided through the parking
garage entrance at N.E. 21 st Street.
A detailed analysis of the site access and traffic flow is provided in
the Traffic Impact Analysis (A1.01a — A1.01c) located under Tab 2
of the Supporting Documents.
(4) Off-street parking and off-street loading areas;
The Zoning Ordinance requires 369 off-street parking spaces and
three (3) loading bays, each at 12 ft. x 35 ft.. The Project provides
376 parking spaces within the parking garage as well as the three
loading bays, each 12 ft. x 35 ft. The vertical clearance for all
loading bays is 15 feet. Building Service areas, including the
enclosed trash rooms, are also located within the building and
garage envelope, as shown on the Ground Floor Plan (Al .01),
under Tab 6 of the Supporting Documents.
(5) Recreational facilities locations;
Level 6 is the first residential levels and includes indoor recreational
facilities (Fitness/Party Room and restroorns) as well as outdoor
recreational facilities on the west half of the parking garage. This
elevated outdoor deck includes a heated pool and landscaping.
The ground level restaurant area also serves as a recreational
facility for the building occupants/residents and the public.
These facilities are shown on the 6th Floor Plan (A1.06) located
under Tab 6 of the Supporting Documents.
•
•
(8) Screens and buffers;
Shade trees are provided along Biscayne Boulevard and N.E. 21 S`
Street as per the FDOT Street Improvement Plan. The garage is
fully screened with decorative facade treatment that coordinates
with the office facade treatment as well as lush landscaping along
the north, east and south sides of the garage, as shown on the
elevations (A2.02 — A2.04) and Landscape Plans (LP-1 and LP-2)
located under Tab 6 of the Supporting Documents.
(7)
Refuse collections areas;
Waste collection will be provided by a containerized compactor
system located within the service area at the ground level of the
garage. Additionally, a recycling program will be implemented for
both office and residence. These facilities are shown on the
Ground Floor Plan (A1.01), located under Tab 6 of the Supporting
Documents.
(8) Access to utilities and points of utilities hookups.
Access and connections to site utilities are discussed in the Site Utility Study
located under Tab 3 of the Supporting Documents.
(e) Tabulations of total gross acreage in the project and the percentages
thereof proposed to be devoted to:
(1) The various permitted uses:
Gross acreage:
Total developable area:
Residential area:
Commercial area:
1.36 Acres (59,485 SF)
172,507 SF max, 170,566 SF proposed (99%)
115,438 SF proposed = 68% of total proposed
55,128 SF proposed = 32% of total proposed
(2) Ground coverage by structures
The Project building footprint (ground coverage) of 32,140 SF is 54% of the
Gross Lot Area.
(f)
Tabulation showing the following:
(1) The derivation of numbers of offstreet parking and offstreet
loading spaces shown in (d) above;
The total number of off-street parking spaces required is 369 spaces and the
total number of spaces provided is 376 spaces. Derivation of the number of
off-street parking is shown under the Project Data Sheet (A0.00), within the
Project Summary, located under Tab 6.
•
•
•
(g)
(2) Total project density in dwelling units per acre.
As per SD-20/SD-20.1 Overlay the maximum project density is 150 dwelling
units per acre. The designated site is 0.98 acres, which allows for the
construction of 147 dwelling units, which is the total amount proposed by the
Project.
If common facilities (such as recreation areas of structures, private
streets, common open space, etc.) are to be provided for the
development, statements as to how such common facilities are to be
provided and permanently maintained.
All common facilities provided will be maintained initially by the Owner.
Common facilities of the residential tower will be maintained by a
condominium association.
(h) Storm drainage and sanitary sewerage plans.
Storm drainage, water distribution, waste water and solid waste generation
provisions are discussed in the Site Utility Study located under Tab 3 of the
Supporting Documents.
(i) Architectural definitions for buildings in the development; exact
number of dwelling units, sizes, and types, together with typical floor
plans of each type.
The Project consists of 147 dwelling units, with a breakdown of 66 Studio
Units, 58 One -Bedroom Units and 23 Two -Bedroom Units. Detailed
information and breakdown of square footages of all uses are found under
the Project Data Sheet within the Building Statistics, included under Tab 6 of
the Supporting Documents. Typical floor plans for residential units are
shown on the Residential Floor Plans, Floors: 6th-17th (13th floor omitted)
(A1.06 — A1.09). All drawings are located under Tab 6 of the Supporting
Documents.
(j) Plans for signs, if any.
Proposed signage plans, consisting of the building name "2121," will be
submitted separately for approval.
(k) Landscaping plan, including types, sizes and locations of vegetation
and decorative shrubbery, and showing provisions for irrigation and
future maintenance.
(I)
The landscape plans showing vegetation are found on Sheets LP-1 and
LP-2. All landscape plans are located under Tab 6 of the Supporting
Documents.
Plans for recreation facilities, if any, including location and general
description of buildings for such use.
•
•
•
(m)
At the ground level there is the entry plaza at the corner of Biscayne
Boulevard and N.E. 21st Street and an outdoor plaza at the northwest corner
of the site for outdoor dining. The Residential Amenities Level is located on
the 6th floor. The enclosed amenities consist of the fitness/party room and
the pool restrooms. The exterior amenities include a heated pool and
landscaped pool deck.
Such additional data, maps, plans, or statements as may be required
for the particular use or activity involved.
The details of the spaces and calculations used to compute the Floor Area
Ratio (FAR) are shown on the Project Data Sheet (A0.00), provided under
Tab 6 of the Supporting Documents.
(n) Such additional data as the applicant may believe is pertinent to the
proper consideration of the site and development plan.
Elevations depicting the architectural character of the building are shown on
the Building Elevations (A2.01 — A2.04) as well as a 3D Montage (A2.05),
enlarged 3D Rendering of the Ground Floor (A2.06) and Building Sections
(A3.01 and A3.02). These sheets are located under Tab 6 of the Supporting
Documents.
2. Section 1702.2.1 General Report.
(1) Property ownership and beneficial interest within the boundaries of the
area proposed for Major Use Special Permit.
Statement of Ownership and beneficial interest within the boundaries of the
area proposed for Major Use Special Permit are provided in Article I.
(2) The nature of the unified interest or control.
The nature of unified interest or control is indicated in Article I.
(3) Survey of the proposed area showing property lines and ownership.
A copy of the Surveys are included under Tab 5 of the Supporting
Documents.
(4) Map of existing features, including streets, alleys, easements, utilities
lines, existing land use, general topography, and physical features.
The existing site features and utility lines are shown on the Boundary Survey
of the property located under Tab 5. The site features and the utilities are
also described in the Site Utility Study, located under Tab 3 of the
Supporting Documents.
(5) Materials to demonstrate the relationship of the elements listed in (4)
preceding to surrounding area characteristics.
•
•
•
The drawings submitted with this Application are located under Tab 6 of the
Supporting Documents.
(6) Existing zoning and adopted comprehensive plan designations for the
area on and around the lands proposed for Major Use Special Permit.
The existing zoning designation for the property pursuant to City of Miami
Ordinance No. 11000 as amended. The existing zoning designation for the
property is C-1, SD-20/SD-20.1 Overlay. The Comprehensive Plan Future
Land Use designation for the property is Restricted Commercial. The zoning
and the comprehensive plan designations are consistent with one another.
3. Section 1702.2.2 Major Use Special Permit Concept Plan.
a. Relationships of the concept plan to surrounding existing and
proposed future uses, activities, systems, and facilities (transportation,
recreation, view corridors, pedestrian systems, service systems and
similar uses.
Article II contains a written narrative of this project outlining proposed uses,
activities and architectural character. This narrative also contains
descriptions of the project's relationship to traffic, pedestrian movements,
and transportation access. Building elevations, sections and perspectives
showing the proposed materials, vertical profile and height, and orientation
to streets are included in the drawings submitted with this Application. The
list of drawings submitted is found under Tab 6 of the Supporting
Documents.
b. Existing zoning and adopted comprehensive plan principles and
designations.
The project conforms with the C-1, SD-20/SD-20.1 Overlay zoning district
designation for the property. The comprehensive plan future land use
designation conforms with the land use designation currently in effect for the
property.
4. Section 1702.2.3 Developmental Impact Study.
(a) A traffic analysis shall be submitted for an area within approximately
1/4 mile of the site, or an area including the major intersections to be
impacted by the site, whichever is larger.
The Traffic Impact Analysis is included under Tab 2 of the Supporting
Documents.
(b) Economic impact data shall be provided, including estimates for
construction costs, construction employment, and permanent
employment and shall demonstrate that the proposed development is
favorable to the economy, public services, environment and housing
supply of the City.
•
•
•
The Economic Impact Study is included under Tab 4 of the Supporting
Documents.
(c) A housing impact assessment.
Over the last several years prices of urban housing have increased
dramatically; despite the recent &ow down in the economy. Subsequently, a
substantial amount of people within metropolitan areas have begun to return
to the city to live. This has created a shortage of multi -family housing along
with an upward surge of housing prices. Contrarily, the cost of construction
has not kept pace with these increases, which has made it economically
affordable to construct new buildings for sale. This pattern remains the
same in South Florida where there continues to be an increased demand for
housing, and offices.
(d) A description of proposed energy conservation measures shall be
provided, including only those measures that are proposed in addition
to the minimum requirements in State Energy Code.
Architecturally, the building envelope will be comprised of insulated walls
and roof. Tinted glass will be used throughout the building. Energy saving
lamps, ballasts, and fixtures are being considered at cores and public
spaces.
(e).
(0.
Historic Buildings
There are no historic structures located on the property.
Environmental Zone
The property is not located within an environmental preservation district.