HomeMy WebLinkAboutRevised School Impact Analysis**REVISED**
SCHOOL. IMPACT REVIEW ANALYSIS
April 4, 2006
FOR INFORMATIONAL PURPOSES ONLY; THE REQUIREMENTS UNDER THE
INTERLOCAL AGREEMENT FOR SCHOOL FACILITY PLANNING ARE NOT TRIGGERED
SINCE THE APPLICANT IS NOT REQUESTING ADDITIONAL RESIDENTIAL DENSITY
OVER WHAT IS CURRENTLY ALLOWED IN THE PROPERTY'S ZONING CLASSIFICATION.
APPLICATION: West Brickell Centre
(PAB Mtg. April 5, 2006)
REQUEST: Major Use Special Permit
ZONING: R-4 "Multifamily High Density Residential" (150 DU/acre)
ACRES: +1.367 net acres
LOCATION: Approximately 240-270 and 290 SW 10 Street; 251-253, 255 and
267 SW 11 Street, Miami
MSA/
MULTIP LIER:
NUMBER OF
UNITS:
5.2 / 0.18 Multifamily
192 dwelling units
(Existing zoning allows 205 units)
ESTIMATED STUDENT
POPULATION: 35
ELEMENTARY:
MIDDLE:
SENIOR HIGH:
16
9
10
SCHOOLS SERVING AREA OF APPLICATION
ELEMENTARY: Southside Elementary — 45 SW 13 Street
MIDDLE: Shenandoah Middle — 1950 SW 19 Street
SENIOR HIGH: Booker T. Washington Senior High — 1200 NW 6 Avenue
All schools are located in Regional Center IV.
*Based on Census 2000 information provided by Miami -Dade County Department of Planning
and Zoning.
The following population and facility capacity data are as reported by the Office of
Information Technology, as of October 2005:
Southside
Elementary
Shenandoah
Middle
Booker T.
Washington Sr.
UTILIZATION
FISH DESIGN FISH DESIGN
STUDENT CAPACITY CAPACITY
POPULATION PERMANENT PERMANENT
230
164%
171
104%
1,204
..............
1,256 104%
1,543 68%2 270
1,553 68%
NUMBER OF
PORTABLE
STUDENT
STATIONS
0
0
0
% UTILIZATION FISH
DESIGN CAPACITY
PERMANENT AND CUMULATIVE
RELCOATABLE STUDENTS"
164%
104%
68%
68%
2078
2,295
4,330
*Student population i ncrease as a result of the proposed developm ent
**Estimated # of students (cumulative) based on zoning/land use log (2001- present) and
assuming all approved developments are built; also assumes none of the prior cumulative
students are figured in current population.
Notes:
1) Figures above reflect the impact of the class size amendment.
2) Pursuant to the Interlocal Agreement, only Southside Elementary School meets the
review threshold.
PLANNED RELIEF SCHOOLS IN THE AREA
(Information included in proposed 5-Year Capital Plan, 2005-2009, dated April 2005)
Projects in Planning, Design or Construction
School Status
State School "K-1" Planning
at Southside Elementary
(Coral Way/Southside/Silver Bluff
Elementary relief schools)
(1,221 student stations)
Proposed Relief Schools
School
N/A
Projected Occupancy Date
School Opening 2009
Funding year
OPERATING COSTS: Accounting to Financial Affairs, the average cost for K-12 grade students
amounts to $6,549 per student. The total annual operating cost for additional students residing
in this development, if approved, would total $229,215.
CAPITAL COSTS: Based on the State's April 2006 student station cost factors*, capital costs
for the estimated additional students to be generated by the proposed development are:
ELEMENTARY 16 x 14,364 = $229,824
MIDDLE 9 x 16,468 = $148,212
SENIOR HIGH 10 x 21,793 = $217,930
Total Potential Capital Cost $595,966
*Based on Information provided by the Florida Department of Education, Office of Educational
Facilities Budgeting. Cost per student station does not include land cost.