HomeMy WebLinkAboutExhibit 3CITY OF MIAMI
ATTACHMENT B
DEPARTMENT OF CAPITAL IMPROVEMENTS
444 NW 2ND AVENUE
MIAMI, FLORIDA 33130
SUBSTANTIAL COMPLETION INSPECTION
Date of Inspection: Re -Inspection No.:
Project Information
Project No.:
Project Location:
Representation
City of Miami
User Agency:
Project Name:
Contractor's Name:
Contractor:
Inspection
Based on the request of the Contractor a substantial completion inspection was conducted, which
resulted in the following:
❑ No punch list created. By signing below the City acknowledges that the work has been performed in
accordance with the contract and specification requirements. This form shall serve as the Notice of
Final Completion. Project Close Out and final payment is subject to the submittal of all required
documentation.
❑ The punch list items as stated on the punch list form are of a nature that will allow beneficial
occupancy on the premises and the punch list is issued as a final punch list, subject to re -inspection
by the City. By signing below the City acknowledges that the work has been performed in
accordance with the contract and specification requirements. This form shall serve as a partial
acceptance and notification of substantial completion. Final Acceptance shall be issued subsequent
Miami Watersports Complex Page 26
to completion and re -inspection of the punch list items. Project Close Out and final payment is
subject to the punch list re -inspection and the submittal of all required documentation.
❑ The punch list items listed are of a nature that precludes beneficial occupancy of the premises.
Substantial completion is denied at this time. Items on the punch list must be completed and the
Contractor must request another Substantial Completion Inspection,
The failure or refusal of the Contractor to sign the Project Substantial Completion Inspection Form or
Punch List shall relieve the Contractor from complying with the findings of the Project Substantial
Completion Inspection and completing the Project to the satisfaction of the City
All punch list items must be completed on or before the mutually agreed upon date of
Contractor City of Miami Consultant
Accepted By: Approved By: Approved By:
Name
Signature
Name Name
Signature Signature
Miami Watersports Complex Page 27