Contract Change Order
Project Name: Bicentenial Park Shoreline Stabilization
Project No.: B-30293
Contractor: Shoreline Foundation, Inc.
2781 SW 56th Avenue
Pembroke Park, Florida 33023
Change Order No.: 2
Contract Award Date: March 26, 2003
Completion Date: February 26, 2005
Revised Completion Date (prior to this change): April 28,
2006
Extension(s) of Time Previously Approved:
426 days
Revised Completion Date (including this change):
The Contractor and the City hereby agree to modify the Contract as follows: (Attach additional pages as necessary)
Item No.
Description of Change
Contract Price
Contract Tme
Increase
Decrease
Increase
Decrease
1
Construction of Phase II of the Projects
$5,330,461.15
365
2
Correct the date of the contract from March
N/A
NIA
N/A
N/A
2
26, 2004 to Mach 26, 2004
Difference (Net)
5,330,461.15
SUMMARY OF CONTRACT AMOUNT
Reason for Change
Regulatory Change
Original Contract Amount (without contingency)
$6,069,646.46
City Requested
X
Cost of Construction Changes Previously Ordered
$3,118,071.00
Design Error
Adjusted Contract Amount Prior to this Change Order
$9,187,717.46
Unforeseen/Unforeseeable
Cost of Construction Changes in this Change Order
5,330,461.15
Adjusted Contract Amount Including this Chan a
$14,518,178.61
Percentage Increase this Change Order
58.02%
Total Percent Increase to Date
139.19%
Contingency Funds Used Yes
Contingency $791,746.00 Contingency Balance $456,884.27
Extension of Time Allowed by this Change - '365 days
D
This change order is hereby incorporated into and becomes a part of the Contract ocuments.
Accepted By Contractor: Date:
Accepted By CIP Director Date: