HomeMy WebLinkAboutExhibit 2CO of t.iami Contract Change Order Project Name: Bicentenial Park Shoreline Stabilization Project No.: B-30293 Contractor: Shoreline Foundation, Inc. 2781 SW 56th Avenue Pembroke Park, Florida 33023 Change Order No.: 2 Contract Award Date: March 26, 2003 Completion Date: February 26, 2005 Revised Completion Date (prior to this change): April 28, 2006 Extension(s) of Time Previously Approved: 426 days Revised Completion Date (including this change): The Contractor and the City hereby agree to modify the Contract as follows: (Attach additional pages as necessary) Item No. Description of Change Contract Price Contract Tme Increase Decrease Increase Decrease 1 Construction of Phase II of the Projects $5,330,461.15 365 2 Correct the date of the contract from March N/A NIA N/A N/A 2 26, 2004 to Mach 26, 2004 Difference (Net) 5,330,461.15 SUMMARY OF CONTRACT AMOUNT Reason for Change Regulatory Change Original Contract Amount (without contingency) $6,069,646.46 City Requested X Cost of Construction Changes Previously Ordered $3,118,071.00 Design Error Adjusted Contract Amount Prior to this Change Order $9,187,717.46 Unforeseen/Unforeseeable Cost of Construction Changes in this Change Order 5,330,461.15 Adjusted Contract Amount Including this Chan a $14,518,178.61 Percentage Increase this Change Order 58.02% Total Percent Increase to Date 139.19% Contingency Funds Used Yes Contingency $791,746.00 Contingency Balance $456,884.27 Extension of Time Allowed by this Change - '365 days D This change order is hereby incorporated into and becomes a part of the Contract ocuments. Accepted By Contractor: Date: Accepted By CIP Director Date: Distribution: CUP Form 101 Contractor LI. A/E Li Finance [J Capital Improvements & Transportation 444 SW 2nd Ave, 8rn Floor Project File U Page 1 of 2