HomeMy WebLinkAboutExhibit 4Agenda -3-
ATTACHMENT E-4
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING WORKSHEET
The applicant is to complete this worksheet by entering the project title, applicant name
and answers to the applicable questions. **Do not answer with more than three
sentences.**
All applicants must answer a total of ten questions. All applicants will complete
Attachment E-4 of the worksheet, which includes questions 1 through 6.
Each applicant will then complete one and only one sub -Attachment (E-4 A, B, C, D or
E, questions 7-10) according to the applicant's project type in reference to Attachment B.
The applicant should determine their project type (if the project incorporates more than
one project type) by determining which project type is dominant in terms of project cost.
All other sub -attachments that are not applicable to an applicant's project should not
be included in the submitted application.
APPLICATION TITLE:
APPLICANT:
CATEGORY RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
1) PRIORITY LIST:
a) List the priority list category of this project from Attachment C in the application. (The
application may only be of one type based upon the predominant cost of the project elements.)
b) Explain how the project fits this priority category.
(For reviewer only)
Max. Available Score
Range of Score
(0 to 8 points)
Agenda -4-
2) WATERWAY RELATIONSHIP:
a) Explain how the project directly relates to the 1CW and the mission of the Navigation
District.
b) How does the project benefit public navigation or access to the 1CW or adjoining waterways?
(For reviewer only)
(0-6 points)
3) PUBLIC USAGE & BENEFITS:
a) How is the public usage of this project clearly identified and quantified?
b) Discuss the regional local public benefits and access to be provided by the project.
c) Estimate the amount of total public use.
d) Can residents from other counties of the District reasonably use the project? Explain.
(For reviewer only)
(0-8 points)
2
Agenda -5-
4) TIMELINESS
a) Describe current status of the project and present a reasonable and effective timeline for the
completion of the project consistent with Attachment E-8.
b) Briefly explain any unique aspects of this project that could influence the project timeline.
(For reviewer only)
(0-3 points)
5) COSTS & EFFICIENCY:
a) List any additional funding sources and the status and amount of the corresponding funding
that will be utilized to complete this project.
b) identify and describe any project costs that may be increased because of the materials
utilized or specific site conditions.
c) Describe any methods to be utilized to increase the cost efficiency of this project.
(For reviewer only)
(0-6 points)
3
Agenda -6-
6) PROJECT VIABILITY:
a) Does the project fill a specific need in the community?
b) Clearly demonstrate how the project will continue to be maintained after District funding is
completed.
c) Will the program result in significant and lasting benefits?
(For reviewer only)
(0-7points)
SUB -TOTAL
FIND FORM NO. 91-25
(Effective Date: 3-21-01, Revised _-j
4
Agenda -7-
ATTACHMENT E-4A
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING.WORKSHEET
DEVELOPMENT & CONSTRUCTION PROJECTS
THIS ATTACHMENT IS TO BE COMPLETED IF YOUR PROJECT IS A
DEVELOPMENT OR CONSTRUCTION PROJECT BUT IS NOT AN INLET
MANAGEMENT OR BEACH RENOURISHMENT PROJECT.
CATEGORY RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
7) PERMITTING:
a) Have all required environmental permits been applied for? if permits are NOT required,
explain why not.
b) If the project is a Phase I project, list the tasks scheduled to obtain the necessary permits and
engineering work.
c) Detail any significant impediments that may have been identified that would potentially delay
the timely issuance of the required permits.
(For reviewer only)
(0-4 points)
5
Agenda -8-
8) PROJECT DESIGN:
a) Has the design work been completed? If this is a Phase I project, has a preliminary design
been developed?
b) Are there unique beneficial aspects to the proposed design that enhance public usage or
access, decrease environmental impacts, improve water quality or reduce costs?
(For reviewer only)
(0-2 points)
9) CONSTRUCTION TECHNIQUES:
a) Briefly explain the construction techniques to be utilized for this project.
b) How are the construction techniques utilized appropriate for the project site?
c) Identify any unusual construction techniques that may increase or decrease the costs of the
project.
(For reviewer only)
(0-3 points)
Agenda -9-
10) CONSTRUCTION MATERIALS:
a) List the materials to be utilized for this project. What is the design life of the proposed
materials?
b) Describe any recyclable material to be utilized. How does the recyclable material (if any)
compare to other available material?
c) Identify any unique construction materials that may significantly alter the project costs.
(For reviewer only)
(0-3 points)
RATING POINT
TOTAL
(Note: The total maximum score possible is dependent upon the project priority category but cannot exceed
50 points unless the project qualifies as an emergency -related project. The minimum score possible is 0
points. A score of 35 points or more is required to be considered for funding.)
Form No. 91-25A
(Effective Date: 3-21-01, revised _-_ )
7
Agenda -7-
ATTACHMENT E-4B
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING WORKSHEET
ENVIRONMENTAL EDUCATION PROJECTS
THIS ATTACHMENT IS TO BE COMPLETED IF YOUR PROJECT IS AN
ENVIRONMENTAL EDUCATION PROJECT
CATEGORY — RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
7) THOROUGHNESS:
a) Who is the primary target audience or user group for the project and how were they
identified?
b) How have the needs of the target audience been evaluated and met?
c) How many people will the program serve on an annual basis? What will be the measurable
results?
(For reviewer only)
(0-5 points)
8
Agenda -8-
8) DELIVERABLES:
a) Describe the materials and project deliverables to be produced by this project.
b) Is there a clear and effective plan of dissemination of the materials produced through the
project?
(For reviewer only)
(0-2 points)
9) EXPERIENCE & QUALIFICATIONS:
a) Please briefly describe the qualifications of the program administrator(s), including prior
experience, and areas of expertise.
b) How is the program manager sufficiently capable and qualified to conduct the proposed
project successfully?
c) What previous projects of this nature have been completed by the program manager?
(For reviewer only)
(0-3 points)
9
Agenda -9-
10) PROJECT GOALS:
a) What are the long -terms goals of This project as it relates to the ICW?
(For reviewer only)
(0-2 points)
RATING POINT
TOTAL
(Note: The total maximum score possible is dependent upon the project priority category but cannot exceed
50 points unless the project qualifies as an emergency -related project. The minimum score possible is 0
points. A score of 35 points or more is required to be considered for funding.)
Form No. 91-258
(Effective Date: 3-21-01, Revised = _-06)
10
Agenda -7-
ATTACHMENT E-4C
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING WOKSHEET
LAW ENFORCEMENT & BOATING SAFETY PROJECTS
THIS ATTACHMENT IS TO BE COMPLETED IF YOUR PROJECT IS A LAW
ENFORCEMENT OR BOATING SAFETY PROJECT
CATEGORY RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
7) VIABILITY:
a) Describe how project will address particular public health, safety, or welfare issues of the
Navigation District's Waterways.
b) Does the project provide significant benefits or enhancements to the District's Waterways?
(For reviewer only)
(0-3 points)
11
Agenda -S-
8) EXPERIENCE & QUALIFICATIONS:
a) List the personnel tasked with the implementation of this project, their qualifications,
previous training and experience.
b) Have the personnel participated in or received state marine law enforcement training?
(For reviewer only)
(0-4 points)
9) DELIVERABLES:
a) Describe the anticipated, long-term measurable results of implementing this project?
b) How will the project continue to be funded?
c) Does the project demonstrate a Tong -term, measurable result that fulfills a particular
community need?
For reviewer only)
(0-2 points)
12
Agenda -9-
10) EDUCATION:
a) What are the educational benefits (if any) of this proposed project?
b) How does the project or program provide effective public boating education?
(For reviewer only)
(0-3 points)
RAT-JNG-P-QINT
TOTAL
(Note: The total maximum score possible is dependent upon the project priority category but cannot exceed
50 points unless the project qualifies as an emergency -related project. The minimum score possible is 0
points. A score of 35 points or more is required to be considered for funding.)
Form No. 91-2SC
(Effective Date: 3-21-01, revised _-_)
13
Agenda -7-
ATTACHMENT E-4D
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING WORKSHEET
INLET MANAGEMENT and PUBLIC NAVIGATION PROJECTS
THIS ATTACHMENT IS TO BE COMPLETED IF YOUR PROJECT IS AN INLET
MANAGEMENT or PUBLIC NAVIGATION PROJECT
CATEGORY RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
7) WATERWAY RELATIONSHIP:
a) How does the project directly benefit the Atlantic Intracoastal Waterway (AICW)?
b) Briefly discuss any methods or activities that will address long-term sedimentation problems,
c) Will the project inhibit sediment inflow into, or reduce the dredging frequency of the AICW?
(For reviewer only)
(0-5 points)
14
Agenda -8-
8) PUBLIC ACCESS:
a) Will the project enhance public access to the waterways? Describe in brief detail.
(For reviewer only)
(0-3 points)
9) PROJECT DESIGN':
a) Are there additional benefits to be realized by implementing this project?
b) Briefly spell out any water quality, environmental or habitat benefits to be realized by this
project.
(For reviewer only)
(0-2 points)
15
Agenda -9-
10) PROJECT FUNDING:
a) List the additional funding sources for this project. What is the status of these funding
sources?
b) Explain the funding mechanism for the long-term maintenance of the project.
(For reviewer only)
(0-2 points)
RATING POINT
TOTAL
(Note: The total maximum score possible is dependent upon the project priority category but cannot exceed
50 points unless the project qualifies as an emergency -related project. The minimum score possible is 0
points. A score of 35 points or more is required to be considered for funding.)
Form No. 91-25D
(Effective Date; 3-21-01, Revised _-_)
16
Agenda -7-
ATTACHMENT E-4E
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING WORKSHEET
BEACH RENOURISHMENT PROJECTS
THIS ATTACHMENT IS TO BE COMPLETED IF YOUR PROJECT IS A BEACH
RENOURISHMENT PROJECT
CATEGORY RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
7) WATERWAY RELATIONSHIP:
a) Describe how the District and other navigation interests will benefit from the implementation
of this project.
(For reviewer only)
(0-4 points)
17
Agenda -8-
8) VIABILITY:
a) Is the project site defined as critically eroded by a statewide beach management plan?
b) Cite the quantifiable rate of erosion in this area.
c) Is the project an important component of an overall beach management effort?
(For reviewer only)
(0-4 points)
9) PUBLIC BENEFITS:
a) Are there quantifiable public benefits demonstrated by the project?
b) Is there adequate public access to the project area?
(For reviewer only)
(0-1 palms)
18
Agenda -9-
10) PROJECT FUNDING:
a) Describe any assistance funding from other sources.
b) Clarify the availability of long-term funding for this project.
(For reviewer only)
(0-2 points)
RATING POINT
TOTAL
(Note: The total maximum score possible is dependent upon the project priority category but cannot exceed
50 points unless the project qualifies as an emergency -related project. The minimum score possible is 0
points. A score of 35 points or more is required to be considered for funding.)
Form No. 91-25E
(Effective Date: 3-21-01)
19
Agenda -X-
ATTACHMENT E-4F
EMERGENCY RE -CONSTRUCTION
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING WORKSHEET
RECONSTRUCTION AND RESTORATION OF A WATERWAY PROJECT
THIS ATTACHMENT IS TO BE COMPLETED IF YOUR PROJECT IS A
WATERWAY PROJECT THAT WAS DAMAGED BY A NATURAL DISASTER AS
DECLARED BY A STATE OF EMERGENCY UNDER CHAPTER 252, FLORIDA
STATUTES, DO NOT UTILIZE THIS FORM UNLESS YOUR PROJECT MEETS
THIS SPECIFIC CRITERION.
CATEGORY RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
11 (extra) STORM DAMAGE EVALUATION:
a) is this project a previously funded FIND grant project?
b) Detail the other funding mechanisms and financial assistance that will be applied to defray
the reconstruction costs or damage repair.
(For reviewer only)
(0-3 points)
Form No. 91-25F
(Effective Date: -05, Revised -_j
20
ATTACHMENT E-5
FLORIDA INLAND NAVIGATION DISTRICT
WATERWAYS ASSISTANCE PROGRAM
PROJECT COST ESTIMATE
(See Rule Section 66B-2.005 & 2.008 for eti2ibility and funding ratios)
PROJECT TITLE:
APPLICANT:
Project Elements
Quantity Estimated
Applicant's Cost
FIND Cost
(Please list the MAJOR project elements and
provide a general cost break out for each one.
Cost
(Number and/or Footage)
For Phase I Projects, please list the major
elements and products expected)
** TOTALS =
Form No. 90-25 (New 10/14/92, Revised -_j
Agenda - 10 -
ATTACHMENT E-6
RESOLUTION FOR ASSISTANCE
UNDER THE FLORIDA INLAND NAVIGATION DISTRICT
WATERWAYS ASSISTANCE PROGRAM
WHEREAS, THE is interested in carrying out the
(Name of Agency)
following described project for the enjoyment of the citizenry of
and the State of Florida:
Project Title
Total Estimated Cost $
Brief Description of Project:
AND, Florida inland Navigation District financial assistance is required for the program
mentioned above,
NOW THEREFORE, be it resolved by the
(Name of Agency)
that the project described above be authorized,
AND, be it further resolved that said
(Name of Agency)
make application to the Florida Inland Navigation District in the amount of % of the
actual cost of the project in behalf of said
(Name of Agency)
AND, be it further resolved by the
(Name of Agency)
that it certifies to the following:
I. That it will accept the terms and conditions set forth in FIND Rule 66B-2
F.A.C. and which will be a part of the Project Agreement for any assistance awarded under
the attached proposal.
2. That it is in complete accord with the attached proposal and that it will carry out
the Program in the manner described in the proposal and any plans and specifications attached
thereto unless prior approval for any change has been received from the District.
Form No. 90-21 (Effective date 12-17-90, Rev. 10-14-92)
(I)
3. That it has the ability and intention to finance its share of the cost of the project
and that the project will be operated and maintained at the expense of said
for public use.
(Name of Agency)
4. That it will not discriminate against any person on the basis of race, color or ,
national origin in the use of any property or facility acquired or developed pursuant to this
proposal, and shall comply with the terms and intent of the Title VI of the Civil Rights Act of
1964, P. L. 88-352 (1964) and design and construct all facilities to comply fully with statutes
relating to accessibility by handicapped persons as well as other federal, state and local
laws, rules and requirements.
5. That it will maintain adequate financial records on the proposed project to
substantiate claims for reimbursement.
6. That it will make available to FIND if requested, a post -audit of expenses
incurred on the project prior to, or in conjunction with, request for the final 10% of the
funding agreed to by FIND.
This is to certify that the foregoing is a true and correct copy of a resolution duly and
legally adopted by the at a legal meeting
held on this day of 20�
Attest Signature
Title Title
Form No. 90-21 (Effective date 12-17-90, Rev. 10-14-92) (2)
ATTACHMENT E-7
ATTORNEYS CERTIFICATION OF TITLE
(See Rule 66B-2.006(4) & 2.008(2) FAC)
OFFICE OF THE (City or County) ATTORNEY
(Address)
,20
TO WHOM IT MAY CONCERN:
I, , am the Attorney for the (City or County), Florida. I
hereby state that I have examined a copy of a (deed, lease, management
agreement,_ etc.) from to the (City or County) dated
conveying (type of interest, ie.
Fee simple, easement, 25 year lease, etc.) in the following described property:
(Legal Description of Property)
I have also examined a document showing that this property is listed on the tax
rolls as belonging -to the- (City or County). Finally,_ I have. also examined such
documents and records as necessary for this certification,
This property is what is now called "(Name of Property as Referenced in the WAP
application)".
I certify that the (City or Coun y1 does in fact (own,
lease, etc.) this property for years.
Very truly yours,
(Name)
(City or County) Attorney
FIND Form No. 94-26 (effective date 5-25-00)
ATTACHMENT E-8
WATERWAYS ASSISTANCE PROGRAM
PROJECT TIMELINE
The applicant is to present a detailed timeline on the accomplishment of the
components of the proposed project including completion dates, as applicable, for;
permitting, design, bidding, applicant approvals, initiation of construction and
completion of construction.
FIND Form 96-10