HomeMy WebLinkAboutExhibit 300600 CONTRACT
THIS IS A CONTRACT, dated as of the day of
2005, by and between the City of Miami, a political subdivision of the. State of Florida,
hereinafter referred to as City, and WILLIAMS PAVING CO., INC., hereinafter referred
to as Contractor.
RECITAL
WHEREAS, the City Commission, or the City Manager, as applicable, has
awarded the Contract to the Contractor for the Project entitled:
Project Name(s): Avalon Storm Sewers Project, Phase I & II
Project/Bid Numbers: Projects B-50685, Bid No. 04-05-129
(hereinafter referred to as "Project")
W 1 T N E S S ET H, that Contractor and City, for the considerations hereinafter
named, agree as follows:
ARTICLE 1
SCOPE OF WORK
Contractor hereby agrees to furnish all hehe labor, work descnbedam,theuipment services and
Cont act Documents
incidentals necessary to perform ail of
and related thereto for the Project(s).
ARTICLE 2
CONTRACT TIME
2.1 Contractor shall be issued a Notice of Award by the Contract Administrator.
Contractor shall commence scheduling activities, permit applications and other
preconstruction work within five (5) calendar days after receipt of the Notice of
Award. The Notice to Proceed and Purchase Order will not be issued until
Contractor's submission to City of ail required documents (including but not
limited to: Payment and Performance Bonds, and Insurance Certificate) and after
execution of the Contract by both parties.
2.1.1. The receipt of all necessary permits by Contractor and acceptance of the
full progress schedule in accordance with technical specifications
section, submittal schedule and schedule of values is a condition
precedent to the issuance of the Notice to Proceed to mobilize on the
Project site and commence with physical construction of the Work. The
Contractor shall submit all necessary documents required by this
provision within fifteen (15) calendar days of the issuance of the Notice
of Award.
2.2 Time is of the essence throughout this Contract. Project Work shall be
performed concurrently for both Projects. The Work and Project Closeout shall
be completed within three hundred sixty five (365) calendar days from the
issuance of the Notice to Proceed, and ready for final payment in accordance
with Article 7. Where the City only awards one of the two Packages the time for
completion shall be 365 calendar days from issuance of the Notice to Proceed.
ARTICLE 3
LIQUIDATED DAMAGES
3.1 Upon failure of Contractor to complete the Contract within the specified period of
time, plus approved time extensions (if applicable), Contractor shall pay to City
the sum of One thousand dollars($1,000.00) for each calendar day after the
time specified in Section 2.2 above, plus any approved time extensions (if
applicable), for Final Completion. These amounts are not penalties but are
liquidated damages to City for its inability to obtain full beneficial occupancy
and/or use of the Project. Liquidated damages are hereby fixed and agreed
upon between the parties, recognizing the impossibility of precisely ascertaining
the amount of damages that will be sustained by City as a consequence of such
delay, and both parties desiring to obviate any question of dispute concerning the
amount of said damages and the cost and effect of the failure of Contractor to
complete the Contract on time.
The above -stated liquidated damages shall apply separately to each portion of
the Project for which a time for completion, is given.
3.2 City is authorized to deduct liquidated damages from monies due to Contractor
for the Work under this Contract or as much thereof as City may, in its sole
discretion, deem just and reasonable_
3.3 Contractor shall be responsible for reimbursing City, in addition to liquidated
damages, for all costs incurred by Consultant in administering the construction of
the Project beyond the completion date plus approved time extensions.
Consultant construction administration costs shall be pursuant to the contract
between City and Consultant, a copy of which is available upon request from the
Contract Administrator. All such costs shall be deducted from the monies due
Contractor for performance of Work under this Contract by means of unilateral
credit change orders issued by City as costs are incurred by Consultant and
agreed to by City.
ARTICLE 4
NO DAMAGES FOR DELAY
In the event of any delays to the project, the Contractor's sole remedy shall be to seek
an extension of time in accordance with the terms of the Contract, The City shall not be
liable for any delay damages or damages attributable to performing work out of
sequence, acceleration claims or other similar type claims, incurred by Contractor
arising out of or in any way associated with the performance of this Agreement.
ARTICLE 5
THE CONTRACT SUM
5.1 This is a Fixed Price, not to Exceed Contract with payments based on Tine item
pricing.
The total amount shall not exceed $3,094,286,00.
5.2 Payment shall be paid based on the line item prices stated in the Contract for
Work actually performed. Payments shall be full compensation for all costs,
including overhead and profit, associated with completion of all the Work in full
conformity with the requirements as Weak not covered by a ted or shown, ordeli Hite Con#th, in the Cracttline
Documents. The cost of any item
item price should be included in the line item price to which the item is most
applicable.
ARTICLE 6
PROGRESS PAYMENTS
6.1 Contractor may make Application for Payment for Work completed duri
the
Project at intervals of not more than once a month. Separate Applications Payment must be submitted for each Package. Contractor's Application for
payment shall show a complete breakdown of the Project components, the
quantities completed and the amount due, together with such supporting
evidence as may be required by Consultant shall include, but is not limited to, an
updated progress schedule acceptable to Consultant as required by the Contract
Documents and a partial release of liens or consent of Surety relative to the
Work, which is the subject of the Application and any other information required
by the Consultant. Each Application for Payment shall be submitted in triplicate
to Consultant for approval. City shall make payment to Contractor within twenty-
five (25) days after approval by Consultant of Contractor's Application for
Payment and submission of an acceptable updated progress schedule.
6.2 Ten percent (10%) of all monies earned by Contractor shall be retained by City
until Final Completion and acceptance by City in accordance with Article 7
hereof, except that after ninety percent (90%) of the Work has been completed,
the Contract Administrator may reduce the retainage to five percent (5%) of all
monies previously earned and all monies earned thereafter, Any reduction in
retainage shall be in the sole discretion Cont actoe halltract have Administrator,
lementshall
toba
recommended by Consultant and
reduction. Any interest earned on retainage shall accrue to the benefit of City.
All requests for retainage reduction shall be in writing in a separate stand alone
document.
6.3 City may withhold, in whole or in part, payment to such extent as may be
necessary to protect itself from loss on account of:
6.3.1 Defective work not remedied.
6.3.2 Claims filed or reasonable evidence indicating probable filing of claims
by other parties against Contractor or City because of Contractor's
performance.
6.3.3 Failure of Contractor to make payments properly to Subcontractors or for
material or labor.
6.3.4 Damage to another contractor not remedied.
6.3.5 Liquidated damages and costs incurred by Consultant for extended
construction administration.
6.3.6 Failure of Contractor to provide any and all documents required by the
Contract Documents.
When the above grounds are removed or resolved satisfactory to the Contract
Administrator, payment shall be made in whole or in part.
2.4 Contractor shall submit separate Applications for Payment for each Project.
2,5 Detailed information concerning the submittal of Applications for Payment is
contained in the Supplemental Conditions of the Contract Documents.
ARTICLE 7
ACCEPTANCE AND FINAL PAYMENT
7.1 Upon receipt of written notice from Contractor that the Work is ready for final
inspection and acceptance, Consultant shall, within ten (10) calendar days, make
an inspection thereof. If Consultant and Project Manager find the Work
acceptable, the requisite documents have been submitted and the requirements
of the Contract Documents fully satisfied, and all conditions of the permits and
regulatory agencies have been met, a Final Certificate for Payment (Form 00926)
shall be issued by Consultant, over its signature, stating that the requirements of
the Contract Documents have been performed and the Work is ready for
acceptance under the terms and conditions thereof.
7.2 Before issuance of the Final Certificate for Payment, Contractor shall deliver to
Consultant a complete release of all liens arising out of this Contract, receipts in
full in lieu thereof; an affidavit certifying that all suppliers and subcontractors have
been paid in full and that all other indebtedness connected with the Work has
been paid, and a consent of the surety to final payment; the final corrected as -
built drawings; and the final bill of materials, if required, and invoice. Contractor
shall deliver the written Contractor's and all Manufacturer's warranties prior to
issuance of the Final Certificate for Payment.
7,3 lf, after the Work has been substantially completed, full completion thereof is
materially delayed through no fault of Contractor, and Consultant so certifies,
City
shall, upon certificate of Consultant, and without terminating the Contract, make
payment of the balance due for that portion
�� ands a the°r� fully and pleted and
cond bons
accepted.. Such payment shall
governing final payment, except that it shall not constitute a waiver of claims.
7.4 Final payment shall be made only after the City Manager or his designee has
reviewed a written evaluation of the performance of Contractor prepared by the
Contract Administrator, and approved the final payment. The acceptance of final
payment shall constitute a waiver of all claims by Contractor, except those
previously made in strict accordance with the provisions of the General
Conditions and identified by Contractor as unsettled at the time of the application
for final payment.
ARTICLE 8
CONTRACT HIERARCHY
8.1 This Contract is part of, and incorporated thero document the Contract incorporated Documents
by the Contract
herein. Accordingly, all
Documents shall govern this Project.
8.2 Where there is a conflict between any provision set forth within the Contract
Documents and a more stringent state or federal provision which is applicable to
this Project, the more stringent state or federal provision shall prevail. The order
of hierarchy within the Contract Documents shall be the technical specifications,
the drawings, Supplemental Conditions, General Conditions, and last shall be the
Instructions to Bidders.
ARTICLE 9
PUBLIC ENTITY CRIMES
In accordance with the Public Crimes Act, Section 287.133, Florida Statutes, a person
or affiliate who is a contractor, Consultant or other provider, who has been placed on
the convicted vendor list following a conviction for a public entity crime may not submit a
bid on a contract to provide any goods or services to the City, may not submit a bid on a
contract with the City for the construction or repair of a public building or public work,
may not submit bids on leases of real property to the City, may not be awarded or
perform work as a contractor, supplier, subcontractor, or Consultant under a contract
with the City, and may not transact any business with the City in excess of the threshold
amount provided in Section 287.017, Florida Statutes, for category two purchases for a
period of 36 months from the date of being placed on the convicted vendor list.
Violation of this section by Contractor shall result in cancellation of the City purchase
order and may result in Contractor debarment.
ARTICLE 10
INDEPENDENT CONTRACTOR
Contractor is an independent coshallrbender sub'ectis to the supery supervisionact. Services
Contraprovided
r. by
Contractor pursuant to this ContractJ
providing such services, neitherContractor
Contract shallnots agents ormake the parties shall
act as officers,
employees, or agents of the City.T
a partnership or joint venture.
ARTICLE 11
THIRD PARTY BENEFICIARIES
Neither Contractor nor City intends to directly or substantially benefit a third party by this
Contract. Therefore, the parties agree that there are no third party beneficiaries to this
Contract and that no third party shall be entitled to assert a claim against either of them
based upon this Contract. The parties expressly acknowledge that it is not their intent
to create any rights or obligations in any third person or entity under this Contract.
ARTICLE 12
NOTICES
Whenever either party desires to give notice to the other, such notice must be in writing,
sent by certified United States Mail, postage prepaid, return receipt requested, or by
hand -delivery with a request for a written receipt of acknowledgment of delivery,
addressed to the party for whom it is intended at the place last specified. The place for
giving notice shall remain the same as set forth herein until changed in writing in the
manner provided in this section. For the present, the parties designate the following:
For City:
Mary H. Conway, P.E.
Director -Capital Improvements and Transportation Department
Office of the City Manager
444 SW 2nd Avenue
10th Floor
Miami, FL 33130
With copies to:
Department of Capital Improvements and Transportation
City of Miami
444 SW 2"d Ave., 8th Floor
Miami, Florida 33130
For Contractor:
Mr. Jose Rodriquez -President
Williams Paving Co., Inc.
11300 N.W. South River Drive
Medley, Florida 33178
ARTICLE 13
ASSIGNMENT AND PERFORMANCE
13.1 Neither this Contract nor any interest herein shall be assigned, transferred, or
encumbered by either party without the prior written consent of the other party..
In addition, Contractor shall not subcontract any portion of the work required by
this Contract except as authorized by Section 26 of the General Conditions.
Contractor represents that all persons delivering the services required by this
Contract have the knowledge and skills, either by training, experience, education,
or a combination thereof, to adequately and competently perform the duties,
obligations, and services set forth in the Scope of Work and to provide and
perform such services to City's satisfaction for the agreed compensation.
13.2 Contractor shall perform its duties, obligations, and services under this Contract
in a skillful and respectable manner. The quality of Contractor's performance and
all interim and final product(s) provided to or on behalf of City shall be
comparable to the best local and national standards.
ARTICLE 14
MATERIALITY AND WAIVER OF BREACH
14.1 City and Contractor agree that each requirement, duty, and obligation set forth in
these Contract Documents is substantial and important to the formation of this
Contract and, therefore, is a material term hereof.
14.2 City's failure to enforce any provision of this Contract shall not be deemed a
waiver of such provision or modification of this Contract. A waiver of any breach
of a provision of this Contract shall not be deemed a waiver of any subsequent
breach and shall not be construed to be a modification of the terms of this
Contract.
ARTICLE 15
SEVERANCE
In the event a portion of this Contract is found by a court of competent jurisdiction
to be invalid, the remaining provisions shall continue to be effective unless City or
Contractor elects to terminate this Contract. An election to terminate this
Contract based upon this provision shall be made within seven (7) days after the
finding by the court becomes final.
ARTICLE 16
APPLICABLE LAW AND VENUE
This Contract shall be enforceable in Miami -Dade County, Florida, and if legal
action is necessary by either party with respect to the enforcement of any or all of
the terms or conditions herein exclusive venue for the enforcement of same shall
lie in Miami -Dade County, Florida. By entering into this Contract, Contractor and
City hereby expressly waive any rights either party may have to a trial by jury or
to file permissive counterclaims in any civil litigation related to, or arising out of
the Project. Contractor shall specifically bind all subcontractors to the provisions
of this Contract. Each party shall bear their own attorney's fees.
ARTICLE 17
AMENDMENTS
No modification, amendment, or alteration in the terms or conditions contained
herein shall be effective unless this Contract and execuntained in a writtented by the City Managerocument prepared t
the same or similar formality as
and Contractor.
ARTICLE 18
PRIOR AGREEMENTS
This document incorporates and includes all prior negotiations, correspondence,
conversations, agreements, and understandings applicable to the matters
contained herein and the parties agree that there are no commitments,
agreements or understandings concerning the subject matter of this Contract that
are not contained in this document. Accordingly, the parties agree that prior
deviation from the terms hereof shall be predicated upon any
representations or agreements, whether oral or written. It is further agreed that
no modification, amendment or alteration in the terms or conditions contained
herein shall be effective unless set forth in writing in accordance with Article 17
above.
IN WITNESS WHEREOF, the parties have set their hands and seals on the day and
year here written , 2005 (effective date).
"City"
City Of Miami, a municipal
ATTEST: corporation
By:
Priscilla A. Thompson, City Clerk Joe Arriola, City Manager
"Contractor"
ATTEST:
a corporation
By:
Print Name: Print Name:
Title: Title:
APPROVED AS TO FORM AND APPROVED AS TO INSURANCE
CORRECTNESS: REQUIREMENTS:
Jorge L. Fernandez Risk Management Administrator
City Attorney Dania Carrillo
THE CITY REQUIRES FOUR (4) FULLY -EXECUTED CONTRACTS, FOR
DISTRIBUTION.