HomeMy WebLinkAboutScope of ServicesEXHIBIT J
SCOPE OF SERVICES
Building Construction, Department of Management Services, State of Florida, hereinafter referred to as "BC",
proposes to provide the following program management services for the projects identified on the face of this
Agreement:
1. A/E's Design Development Phase Services
BC WILL;
Accept Assignment Of A/E's Contract With The City Of Maimi, Public Works Department
Provide Direction/Consultation To The A/E As Required Regarding Scope, Additional
Services, Procedures , etc.
Provide Information To The A/E Regarding Permitting Agencies and Codes to Use
Provide Budgetary Direction To The A/E
Participate In Value Engineering Analysis To Provide The Best Project Within Budget
Review Plans For Architectural, Mechanical, Electrical And Civil And Provide
Comments To The A/E
Reviews A/E Responses And/Or Revisions Due To DBC (And Other Reviewing Agencies) Comments
Monitor The Schedule For Submittals And Establish Dates For Reviews
Reviews A/E Requests For Additional Services For Scope, Completeness, Fairness
Issue A/E Additional Services Authorizations Agreed Upon
Receive, Review And Approve A/E Invoices For Services Rendered Versus Contract
Conditions
Process A/E Invoices To Proper Accounting Office For Vouchering
Review And Analyze Cost Estimates
Review Specifications
Assure Meetings Are Documented And Minutes Distributed To All Parties
Assure ALl Decisions Required For That Particular Design Phase Are Made
Issue Approval To A/E To Proceed Into Next Phase
THE FOLLOWING WILL BE PROVIDED BY THE A/E UNDER CONTRACT TO BC
Conferences With Client & Others
Site - Informational Data
Master Plan
Environmental Considerations
Grading & Site Development
Site Construction
Roads, Walks, Paths & Parking
Utility Services
Fencing
Landscaping
Lateral & Transverse Site Sections
Special Site Considerations
Buildings - Architectural:
Floor Plans
Area Recap
Elevations
Building Sections
Typical Wall Sections
Finish & Equipment Schedules
Color Pallet & Schedule
Code Classifications
Complex Area Plans
List Of Safety Equipment
Design Concept Sketch
4
Materials List
Other Information
Buildings - Structural:
Describe Foundation Conditions
Describe Structure Selected
Preliminary Framing Plan
Describe Roof Structure
Structural Building Sections
Identify Building Loads
Design Calculations & Criteria
Special Conditions
Buildings - HVAC:
Single Line Layout With Equipment
Sections Showing Equipment
Fleet Forms
Describe Auto Management System
Describe Criteria For Heating System
Describe Ventilation System
Describe AC Criteria & System
Describe Evaporative Cooling System
Buildings - Refrigeration:
Areas To Be Refrigerated
Outside Design Temperatures
Type Refrigeration Equipment
Type/Thickness Insulation
Buildings - Electrical:
Describe Electrical Service Entrance
Describe Electrical Characteristics
Identify Panel Locations
Describe Wiring Systems
Describe Conductors
Locate Lights, Outlets & Switches
Describe Standards Of Design
Describe Short -Circuit Duty
Describe Emergency Electrical Systems
Coordinate Building & Site Electrical
Other
Buildings - Communication:
Describe Systems
Describe Materials
Describe Locations
Describe Radio Paths
Describe Antenna Requirements
Describe Antenna Transmission
Describe Bonding & Grounding
Describe Cable/Radio Links
Describe Test Equipment
Describe Equipment Arrangement
Describe Wiring/Cable Requirements
Describe Lighting/Power Requirements
Describe AC Requirements
Describe Interference/Clearance
Buildings - Plumbing:
Preliminary Layout Of Lines
Preliminary Plan Locations
Preliminary Section With Risers
Identify Number Of Fixtures
5
f•
Identify Water Pressure
Identify Hot Water System
Other
Buildings - Fire Protection:
Identify Hydrant
• Identify Riser/Hose Cabinets
Identify Sprinkler Criteria
Insurance Design Criteria
Sprinkler Head Layout
Buildings - Special Equipment:
Kitchen Equipment
Auditorium Seating
Stage Curtain And Equipment
Gym Layout And Equipment
Window Coverings
Hospital Equipment
Lawn Sprinkler Equipment
Vacuum Cleaning Systems
Material Handling Equipment
Telephone Systems •
Other Systems
Checklist
Bid Packages/Sequences;Ease Bid & Alternates
Probable Construction cost
Area Analysis
Telephone Site Plan
Distribution Of Review Packages
BC Review
A/E's Response To Review Comments
2 A/E's Construction Documents Phase Services
BC WILL;
Provide Direction/Consultation To The A/E As Required Regarding Scope, Additional
Services, Procedures , etc.
Provide Information To The A/E Regarding Permitting Agencies and Codes to Use
Provide Budgetary Direction To The A/E
Participate In Value Engineering Analysis To Provide The Best Project Within Budget
Review Plans For Architectural, Mechanical, Electrical And Civil And Provide Comments To ,—
The A/E
Reviews AIE Responses And/Or Revisions Due To BC (And Other Reviewing Agencies) Comments
Monitor The Schedule For Submittals And Establish Dates For Reviews
Reviews A/E Requests For Additional Services For Scope, Completeness, Fairness
Issue A/E Additional Services Authorizations Agreed Upon
Receive, Review And Approve A/E Invoices For Services Rendered Versus Contract Conditions
Process A/E Invoices To Proper Accounting Office For Vouchering
Review And Analyze Cost Estimates
Review Specifications
Assure Meetings Are Documented And Minutes Distributed To All Parties
Assure Ail Decisions Required For That Particular Design Phase Are Made
Issue Approval To A/E To Proceed Into Next Phase
THE FOLLOWING WILL BE PROVIDED BY THE A/E UNDER CONTRACT TO BC
Conferences \Vith CLIENT
50% Documents Review
Non -Technical Specifications
Fleet/Solar Energy
Codes Certification
Check List
Cost Estimates
Area Analysis
Color Schedules
Handicapped Check List
Drawings - -
Technical Specifications
Bid Packages
Alternates
Mechanical Test And Balance
100% Documents Review
• 100% Review Response
3. A/E's Bidding Phase Services (If Applicable)
BC WILL;
Prepare Sample Advertisement For A/E To Use In Newspapers
Issue State MBE Directory To The A/E To Be Made Available To Contractors (As Required
To Meet Project Goals)
Monitor Addenda For Scope And Clarity
Participate In Bid Openings
Review Contracts Financial Qualifications And Experience
Make Recommendations For Bid Award
THE FOLLOWING WILL BE PROVIDED BY THE A/E UNDER CONTRACT TO BC
Prepare Camera Ready Copy Of Documents For Each Bid
Package
Prepare & Issue Addenda
Attend Bid Openings
Award Recommendations
4. A/E's Construction Phase Services
BC WILL;
Prepare And Issue The Notice To Proceed
Participate With The ATE And Contractor In The Initial Construction Conference
Review The Contractor's Schedule For The Project
Participate In All Monthly (Or Bi-Weekly) Team Meetings
Assure All Team Meetings Are Documented And Minutes Sent To All Parties
Review Contractors List Of Subcontractors
Review Monthly RFI, ASI, Submittal, Shop Drawings And Other Logs For Timeliness
Review Contractor's Progress Against The Schedule On A Monthly (Or Bi-Weekly) Basis
Analyze Change Order Proposals For Scope, Need, Completeness, Fairness
Recommend Change Orders As Required
Review Contractor's Pay Requests
Process Pay Requests To The Appropriate Accounting Office For Voucherine
Participate In Monthly Inspections With The A/E
Participate In Substantial Completion Inspections
Participate In Final Completion Inspections
Review And Sign Affidavits Of Completion
THE FOLLOWING WILL BE PROVIDED BY THE ATE UNDER CONTRACT TO BC
Initial Construction Conferences
Project Sinn Design
Monthly Construction Conferences
Review Contractor's Progress Schedule
Review Contractor's List Of Subcontractors
Review Contractor's Shop Drawings
Transmit Payroll Records Required By Federal Grants
7
Review As -Built Drawings
Clarification Documents
Monthly Status Report
Site Visits And Reports
Monthly Contractor Payment Reviews
Review Testing Invoices
Change Orders
Claim Reviews And Correspondence
Substantial Completion Inspection
Final Completion Punchlist
Final Inspection
- Review Contractor's Affidavits Of Completion
Review Contractor's Guarantees And Operating Manuals
Review Contractor's As -Built Drawings
5. Contractor Selection
BC WILL;
Establish Contractor Selection Team Consisting Of BC, A E &
CLIENT Personnel
Advertise For'Qualified Contractors
Prepare Project Scope Information For Contractors
Answer Contractor's Questions
Verify Contractor Prequalification Criteria
County & State Licensure/Certification/Corporation
Analyze Previous Experience On Similar Projects
Analyze Management Staff & Experience
Analyze Site Management Capability
Analyze Present Workload
Schedule/Arrange Contractor Selection Meetings
Conduct Preliminary Selections, Reducing Applicants To 5
Contractors
Publish Shortlist Results Of Contractor Selections
Debrief Unsuccessful Contractors
Brief Successful Contractors
Conduct Interviews With Remaining 5 Contractors
Finalize Selection, Reducing To 3 Contractors In Order Of
Preference
Debrief Ranked Contractors
6. Contractor Fee Negotiations
BC WILL;
Establish Contractor Negotiation Team Consisting Of BC,
A/E & CLIENT Personnel
Prepare & Publish Detailed Scope For Contractors
Notify Number 1 Contractor Of Negotiation & Proposal
Requirements
Answer Number 1 Contractor's Questions
Receive & Analyze Proposal From Number 1 Contractor
Conduct Pre -Negotiation Conference With Negotiation Team
Conduct Negotiations of Contractor's Fee With Number 1 Contractor
Establish On -Site Design Personnel Requirements
Establish Off -Site Design Personnel Requirements
Establish On -Site Construction Personnel Requirements
Establish Off -Site Construction Personnel Requirements
Establish General Conditions Requirements
Establish Design & Construction Phase Fee
Establish Overhead & Profit Fee
Establish Preliminary Schedule Requirements
Establish Construction Team, Consisting Of BC, CLIENT,
A/E & Contractor Personnel
Coordinate With CLIENT
Distribute Results Of Negotiation
Obtain CLIENT Approval
7. Contractor Contract Preparation/Execution
BC WILL;
Prepare Contract On BC's Form For Contractor & BC
'• Execution
Prepare Performance Bond On BC's Form In Budget Amount
Prepare Labor & Material Payment Bond On BC's Form In
Budget Amount
Prepare Certificate Of Insurance On BC's Form
Prepare Assignment Of Contractor's Antitrust Rights To CLIENT
On BC's Form
Process Contract Documents To Contractor For Execution
Receive Executed Documents Back From Contractor &
Thoroughly Check For Proper Execution
Execute Documents On Behalf Of CLIENT
Give Contractor Notice -To -Proceed With Design Phase Services
S. Contractor's Design Phase Services
BC WILL;
Participate With The A/E And Contractor/CM In Plan Reviews At Each Submittal Phase
Participate With The A/E And Contractor/CM In Value Engineering Alternative
Design/Construction Approaches
Review All Contractor/CM Estimates
Review Contractor/CM GMP With The Team And Recommend For Contracting
Explore Tax Savings And Implement Procedures As Necessary
THE FOLLOWING WILL BE PROVIDED BY THE CONTRACTOR/CM UNDER CONTRACT TO
BC (WITHOUT ASSUMING DESIGN RESPONSIBILITIES)
Distribute Document Package
Schedule Familiarization Meeting.
Conduct Familiarization Meeting
Manage Requests For Information
Pricing & Value Engineering (VE)
Review & VE Site Civil
Review & VE Mechanical -Electrical Systems
Review & VE Structural Systems
Review & VE Roof & Exterior
Review & VE ADA Compliance
Review & VE Detail Coordination
Evaluate Construction Phasing
Evaluate Constructability
Propose Guaranteed Maximum Price (GMP)
Negotiate Final GMP & Conditions
Document Final GMP & Conditions
Review Final GRIP & Conditions With CLIENT Team
Obtain CLIENT Team Approval Of Final GMP & Conditions
Amend Contractor's Contract To Reflect Final GMP/Conditions
Prepare GMP Amendment To Construction Contract
Process GMP Amendment To Contractor For Execution
Receive Executed Amendment Back From Contractor &
Thoroughly Check For Proper Execution
9
Execute GMP Amendment On Behalf Of CLIENT
Process Executed GMP Amendment To Contractor
9. Contractor's Construction Phase Services
BC WILL;
• Prepare And Issue The Notice -To -Proceed
Participate With The A/E And Contractor In The Initial Construction Conference
Review The Contractor's Schedule For The Project
Participate In All Monthly (Or Bi-Weekly) Team Meetings .
Assure All Team Meetings Are Documented And Minutes Sent To All Parties
Review Contractor's List Of Subcontractors
• Review Monthly RFI, ASI, Submittal, Shop Drawings And Other Logs For Timeliness
Review Contractor's Progress Against The Schedule On A Monthly (Or Bi-Weekly) Basis
Analyze Change Order Proposals For Scope, Need, Completeness, Fairness
Recommend Change Orders As Required
Review Contractor's Pay Requests
Process Pay Requests To The Appropriate Accounting Office For Vouchering
Participate In Monthly Inspections With The A/E
Participate In Substantial Completion Inspections
Participate In Final Completion Inspections
Review And Sign Affidavits Of Completion
THE FOLLOWING WILL BE PROVIDED BY THE CONTRACTOR/CM UNDER CONTRACT TO
• BC (WITHOUT ASSUMING DESIGN RESPONSIBILITIES)
Coordinate Contractor's Project Promotion & Advertisement
Contact Qualified Sub -Contractors
Promote Through Associations & Exchanges
Promote MBE participation To Make Good Faith Effort
Toward Meeting District Board Of Trustees Requirements
Use BC & CLIENT Databases Of Interested Contractors
BC & CLIENT To Participate In Pre -Bid Meetings & Bid
Openings
Coordinate Contractor's Review Of 100% Construction
Documents
Give Contractor Notice -To -Proceed With Construction
Coordinate Contractor's Project Information Management
Key Personnel Contacts
Budget & Financial Data
Project Construction Scheduling
Construction Progress Conference Scheduling
Interface With Construction Management Systems
Initial Team Construction Conference
Maintain Constructive Agenda
Document Potential Areas Of Concern
Develop Subcontractor Coordination Plan
Review Construction Critical Path
Confirm Communications Network Weekly Team Meetings
Monthly Team Meetings
Prepare For Meetings
Attend Meetings
Prepare Monthly Report
Review Submittal Schedule
Identify Lona-Lead Submittals
Coordinate Review Periods With Construction Schedule
Review Budget Status
Review Value Analysis Reports
10
1
Perform Quality Control Observations
Review Construction Schedule
Review Change Proposals. Reviews And Implementation Are
To Be By The Construction Team On Changes To The GMP
That Are Less Than $100,000. Those Changes Equal To
Or Greater Than $100,000 Will Require CLIENT Approval.
Review MBE Participation Reports
Review Testing Reports
Review Building Code Inspection Reports
Review Requests For Payment & Transmit To CLIENT For Review
"•& Payment
• Establish Transition Team
Monitor As•Built Development
Substantial Completion Inspection
Review A/E Certifications
Expedite & Verify Punchlist Corrections
Review Warranties & Submittals
Final Inspection & DOE Certification
10. Occupancy Services (Additional Service to Owner)
BC WILL,
Assure Staff Training Occurs For Equipment
THE FOLLOWING WILL BE PROVIDED BY THE CONTRACTORlCM LENDER CONTRACT TO BC
.(WITHOUT ASSUMING DESIGN RESPONSIBILITIES)
Review Occupancy Requirements
Coordinate Maintenance & Operational Training
Review Systems Testing & Certifications
ll