HomeMy WebLinkAboutExhibit 1AMENDMENT TO INLET RETROFIT FOR THE (H 3 WAGNER CREEK BASIN
PROJECT
This AGREEMENT ("Agreement"), is made and entered into this - day of
, 2005, by and between the City of Miami, Florida, a municipal
corporation of the State of Florida, whose principal address is 444 S.W. 2"d Avenue, 10th'
Floor, Miami, Florida 33130 (the "City") and Environmental Performance
W South River �s, I,Inc.
a Florida corporation, whose principal address is 12650
Medley, Florida 33018 (the "Contractor").
WITNESSETH:
WHEREAS, pursuant to Resolution No. 05-0222, adopted by the Miami City
Commission on April 14, 2005, the City Commission accepted the bid of the Contractor
to provide for the installation of baskets and traps along the Wagner Creek Basin area and
entered into an agreement for said services for a period of one (1) year (the "Contract");
and
WHEREAS, the City has determined that it is in its best interest to have
retrofitting devices installed in storm sewer systems in other areas within the City, such
as Overtown and Allapattah Market Place (the "Additional Services"); and
WHEREAS, Contractor is performing similar services in other areas or the City
under the Contract and is willing to perform the Additional Services for the additional
sum -of $50,000,which-amount isacceptable to the City; and
WHEREAS, the parties wish to amend the Contract to include the Additional
Services and increase the amount of compensation accordingly.
NOW, THEREFORE, in considerationContract foregoing,
as follows:
promisesand
covenants contained herein the parties y amend the
1. Recitals: The Recitals are true and correct and are hereby incorporated into
and made a part of this Agreement.
2, Scope of Work: Article 1 of the Contract is amended to include the
Additional Services, which are specifically described in Exhibit "A," attached hereto and
made a part of this Agreement.
3, The Contract Sum: Article 2 of the Contract is amended to increase the
Contract Sum by an amount not toFifty
Cents
Four Hundaed and
) for a
total Contract Sum not to exceed wo Hundred Forty SiThousand,
Eighty and No Cents ($246,480).
ors:DDocument 1433
4. Time Of Completion: Article 4 of the Contract is amended to increase the
number of days in which Contractor shall complete the work, including the
Additional Services, by forty (40) working days. Accordingly, Article 7 of the
contract is amended to extend the contract Term by forty (40) working days
beginning ten days after a Second Notice to Proceed is issued by the Departments
Director, for a total contract term of one hundred sixty (160) working days.
5. Additional Bond: Article 5 of the Contract is amended to o requirent uthethe
Contractor
Performancen
to provide an additional Performance Bond, or to increase
Bond, to cover the performance of the Additional Services.
6. No Implied Modifications: Except as provided herein, the terms of the Contract
are unchanged and shall remain in effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement on the
day and date first above written.
Attest:
CONTRACTOR:
Environmental Performance
Systems, Inc., a Florida Corporation
BY: BY:
Corporate Secretary
(SEAL)
Attest:
THE CITY OF MIAMI, a municipal
corporation of the State of Florida
By:
Priscilla A. Thompson, City Clerk Joe Arriola, City Manager
APPROVED AS TO FORM AND APPROVED AS TO INSURANCE
CORRECTNESS REQURIEMENTS
Jorge L. Fernandez Dania Carrillo, Administrator
City Attorney Risk Management
or®Document 1433