HomeMy WebLinkAboutExhibit 300600
CONTRACT
THIS IS A CONTRACT, effective the day of , 2005 by
and between the City of Miami, a Florida municipal corporation, hereinafter referred to
as CITY, and SHORELINE FOUNDATION, hereinafter referred to as CONTRACTOR.
RECITAL
WHEREAS, the City Commission, or the City Manager, as applicable, has
awarded the Contract to the Contractor for the Project entitled:
Project Name(s): Dinner Key Marina Fuel Dock
Project/Bid Numbers: Project B-60465/Bid No. 04-05-026
(hereinafter referred to as "Project")
W I T N E S S E T H, that CONTRACTOR and CITY, for the considerations
hereinafter named, agree as follows:
ARTICLE 1
SCOPE OF WORK AND CONTRACT DOCUMENTS
CONTRACTOR hereby agrees to furnish all of the labor, materials, equipment
services and incidentals necessary to perform all of the work described in the Contract
Documents and related thereto for the Project. The Contract Documents consist of the
Invitation for Bids (Bid No. 04-05-026) and all addenda thereto, which by this reference
is incorporated into a made apart of this Contract.
ARTICLE 2
CONTRACT TIME
2.1 CONTRACTOR shall be issued a Notice of Award by the Contract Administrator.
CONTRACTOR shall commence scheduling activities, permit applications and
other preconstruction work within five (5) calendar days after receipt of the Notice
of Award. The Notice to Proceed and Purchase Order will not be issued until
CONTRACTOR's submission to CITY of all required documents (including but
limited to: Payment and Performance Bonds, and Insurance Certificate) and after
execution of the Contract by both parties.
2.1.1. The receipt of all necessary permits by CONTRACTOR and acceptance
of the full progress schedule in accordance with technical specifications
section, submittal schedule and schedule of values is a condition
Ott 5 ity fit oso/a-o 3
precedent to the issuance of the Notice to Proceed to mobilize on the
Project site and commence with physical construction of the work. The
CONTRACTOR shall submit all necessary documents required by this
provision within fifteen (15) calendar days of the issuance of the Notice
of Award.
2.2 Time is of the essence throughout this Contract. The Work shall be substantially
completed within two hundred twenty nine (229) calendar days from the
issuance of the Notice to Proceed, and completed and ready for final payment in
accordance with Article 5 within forty five (45) calendar days from the date
certified by CONSULTANT as the date of Substantial Completion.
2.3 Upon failure of CONTRACTOR to substantially complete the Contract within the
specified period of time, plus approved time extensions (if applicable),
CONTRACTOR shall pay to CITY the sum of four hundred seventy five
dollars ($475.00) for each calendar day after the time specified in Section 2.2
above, plus any approved time extensions (if applicable), for Substantial
Completion. After Substantial Completion should CONTRACTOR fail to
complete the remaining work within the time specified in Section 2.2, plus
approved time extensions thereof, for completion and readiness for final
payment, CONTRACTOR shall pay to CITY the sum of two hundred fifty
dollars ($250.00) for each calendar day after the time specified in Section 2.2
above, plus any approved extensions, for completion and readiness for final
payment. These amounts are not penalties but are liquidated damages to CITY
for its inability to obtain full beneficial occupancy and/or use of the Project.
Liquidated damages are hereby fixed and agreed upon between the parties,
recognizing the impossibility of precisely ascertaining the amount of damages
that will be sustained by CITY as a consequence of such delay, and both parties
desiring to obviate any question of dispute concerning the amount of said
damages and the cost and effect of the failure of CONTRACTOR to complete the
Contract on time.
The above -stated liquidated damages shall apply separately to each portion of
the Project for which a time for completion is given.
2.4 CITY is authorized to deduct liquidated damages from monies due to
CONTRACTOR for the Work under this Contract or as much thereof as CITY
may, in its sole discretion, deem just and reasonable.
2.5 CONTRACTOR shall be responsible for reimbursing CITY, in addition to
liquidated damages, for all costs incurred by CONSULTANT in administering the
construction of the Project beyond the completion date plus approved time
extensions. CONSULTANT construction administration costs shall be pursuant
to the contract between CITY and CONSULTANT, a copy of which is available
upon request of the Contract Administrator. All such costs shall be deducted
from the monies due CONTRACTOR for performance of Work under this
Contract by means of unilateral credit change orders issued by CITY as costs are
incurred by CONSULTANT and agreed to by CITY. The CONSULTANT and the
Contract Administrator are identified in the Contract Documents.
2.6 NO DAMAGES FOR DELAY. In the event of any delays to the project, the
Contractor's sole remedy shall be to seek an extension of time in accordance
with the terms of the Contract. The City shall not be liable for any delay damages
or damages attributable to performing work out of sequence, acceleration claims
or other similar type claims, incurred by subcontractor arising out of or in any way
associated with the performance of this Agreement.
ARTICLE 3
THE CONTRACT SUM
This is a Lump Sum Contract:*
3.1 CITY shall pay to CONTRACTOR for the performance of the Work described in
the Contract Documents, the total price stated as awarded.
3.2 Payment shall be at the lump sum price stated in the Contract. This price shall
be full compensation for all costs, including overhead and profit, associated with
completion of all the work in full conformity with the requirements as stated or
shown, or both, in the Contract Documents. The cost of any item of work not
covered by a definite Contract lump sum should be included in the lump sum
price to which the item is most applicable.
*Note: Some Projects include both unit prices and lump sums in which case both
sections shall apply to the Work identified for each type of Contract.
ARTICLE 4
PROGRESS PAYMENTS
4.1 CONTRACTOR may make Application for Payment for Work completed during
the Project at intervals of not more than once a month. CONTRACTOR's
application shall show a complete breakdown of the Project components, the
quantities completed and the amount due, together with such supporting
evidence as may be required by CONSULTANT may require the amount due,
together with such supporting evidence as CONTRACTOR shall include, but not
limited to, with each Application for Payment, an updated progress schedule
acceptable to CONSULTANT as required by the Contract Documents and a
partial release of liens or consent of surety relative to the work, which is the
subject of the Application. Each Application for Payment shall be submitted in
triplicate to CONSULTANT for approval. CITY shall make payment to
CONTRACTOR within twenty-five (25) days after approval by CONSULTANT of
CONTRACTOR's Application for Payment and submission of an acceptable
updated progress schedule.
4.2 Ten percent (10%) of all monies earned by CONTRACTOR shall be retained by
CITY until Final Completion and acceptance by CITY in accordance with Article 5
hereof, except that after ninety percent (90%) of the Work has been completed,
the Contract Administrator may reduce the retainage to five percent (5%) of all
monies previously earned and all monies earned thereafter. Any reduction in
retainage shall be in the sole discretion of the Contract Administrator, shall be
recommended by CONSULTANT and CONTRACTOR shall have no entitlement
to a reduction. Any interest earned on retainage shall accrue to the benefit of
CITY. All requests for retainage reduction shall be in writing in a separate stand
alone document.
4.3 CITY may withhold, in whole or in part, payment to such extent as may be
necessary to protect itself from loss on account of:
4.3.1 Defective work not remedied.
4.3.2 Claims filed or reasonable evidence indicating probable filing of claims
by other parties against CONTRACTOR or CITY because of
CONTRACTOR's performance.
4.3.3 Failure of CONTRACTOR to make payments properly to Subcontractors
or for material or labor.
4.3.4 Damage to another contractor not remedied.
4.3.5 Liquidated damages and costs incurred by CONSULTANT for extended
construction administration.
4.3.6 Failure of CONTRACTOR to provide any and all documents required by
the Contract Documents.
When the above grounds are removed or resolved satisfactory to the Contract
Administrator, payment shall be made in whole or in part.
ARTICLE 5
ACCEPTANCE AND FINAL PAYMENT
5.1 Upon receipt of written notice from CONTRACTOR that the Work is ready for
final inspection and acceptance, CONSULTANT shall, within ten (10) calendar
days, make an inspection thereof. If CONSULTANT and PROJECT MANAGER
find the Work acceptable, the requisite documents have been submitted and the
requirements of the Contract Documents fully satisfied, and all conditions of the
permits and regulatory agencies have been met, a Final Certificate for Payment
(Form 00926) shall be issued by CONSULTANT, over its signature, stating that
the requirements of the Contract Documents have been performed and the Work
is ready for acceptance under the terms and conditions thereof.
5.2 Before issuance of the Final Certificate for Payment, CONTRACTOR shall
deliver to CONSULTANT a complete release of all liens arising out of this
Contract, receipts in full in lieu thereof; an affidavit certifying that all suppliers and
subcontractors have been paid in full and that all other indebtedness connected
with the Work has been paid, and a consent of the surety to final payment; the
final corrected as -built drawings; and the final bill of materials, if required, and
invoice.
5.3 If, after the Work has been substantially completed, full completion thereof is
materially delayed through no fault of CONTRACTOR, and CONSULTANT so
certifies, CITY shall, upon certificate of CONSULTANT, and without terminating
the Contract, make payment of the balance due for that portion of the Work fully
completed and accepted. Such payment shall be made under the terms and
conditions governing final payment, except that it shall not constitute a waiver of
claims.
5.4 Final payment shall be made only after the City Manager or his designee has
reviewed a written evaluation of the performance of CONTRACTOR prepared by
the Contract Administrator, and approved the final payment. The acceptance of
final payment shall constitute a waiver of all claims by CONTRACTOR, except
those previously made in strict accordance with the provisions of the General
Conditions and identified by CONTRACTOR as unsettled at the time of the
application for final payment.
ARTICLE 6
MISCELLANEOUS
6.1 This Contract is part of, and incorporated in, the Contract Documents as defined
in Article 1. Accordingly, all of the documents incorporated by the Contract
Documents shall govern this Project.
6.2 Where there is a conflict between any provision set forth within the Contract
Documents and a more stringent state or federal provision which is applicable to
this Project, the more stringent state or federal provision shall prevail.
6.3 Public Entity Crimes
In accordance with the Public Crimes Act, Section 287.133, Florida Statutes, a
person or affiliate who is a contractor, CONSULTANT or other provider, who has
been placed on the convicted vendor list following a conviction for a public entity
crime may not submit a bid on a contract to provide any goods or services to the
CITY, may not submit a bid on a contract with the CITY for the construction or
repair of a public building or public work, may not submit bids on leases of real
property to the CITY, may not be awarded or perform work as a contractor,
supplier, subcontractor, or CONSULTANT under a contract with the CITY, and
may not transact any business with the CITY in excess of the threshold amount
provided in Section 287.017, Florida Statutes, for category two purchases for a
period of 36 months from the date of being placed on the convicted vendor list.
Violation of this section by Contractor shall result in cancellation of the CITY
purchase and may result in Contractor debarment.
6.4 Independent Contractor
CONTRACTOR is an independent contractor under this Contract. Services
provided by CONTRACTOR pursuant to this Contract shall be subject to the
supervision of CONTRACTOR. In providing such services, neither
CONTRACTOR nor its agents shall act as officers, employees, or agents of the
CITY. This Contract shall not constitute or make the parties a partnership or joint
venture.
6.5 Third Party Beneficiaries
Neither CONTRACTOR nor CITY intends to directly or substantially benefit a
third party by this Contract. Therefore, the parties agree that there are no third
party beneficiaries to this Contract and that no third party shall be entitled to
assert a claim against either of them based upon this Contract. The parties
expressly acknowledge that it is not their intent to create any rights or obligations
in any third person or entity under this Contract.
6.6 Notices
Whenever either party desires to give notice to the other, such notice must be in
writing, sent by certified United States Mail, postage prepaid, return receipt
requested, or by hand -delivery with a request for a written receipt of
acknowledgment of delivery, addressed to the party for whom it is intended at the
place last specified. The place for giving notice shall remain the same as set
forth herein until changed in writing in the manner provided in this section. For
the present, the parties designate the following:
For CITY:
Mary Conway
Director -Capital improvement Program/Transportation
Office of the City Manager
444 SW 2nd Avenue
10th Floor
Miami, FL 33130
With copies to:
Department of Capital Improvements and Transportation
City of Miami
444 SW 2nd Ave., 8th Floor
Miami, Florida 33130
For Contractor:
6.7 Assignment and Performance
Neither this Contract nor any interest herein shall be assigned, transferred, or
encumbered by either party. In addition, CONTRACTOR shall not subcontract
any portion of the work required by this Contract except as authorized by Section
27 of the General Conditions. CONTRACTOR represents that all persons
delivering the services required by this Contract have the knowledge and skills,
either by training, experience, education, or a combination thereof, to adequately
and competently perform the duties, obligations, and services set forth in the
Scope of Work and to provide and perform such services to CITY's satisfaction
for the agreed compensation.
CONTRACTOR shall perform its duties, obligations, and services under this
Contract in a skillful and respectable manner. The quality of CONTRACTOR's
performance and all interim and final product(s) provided to or on behalf of CITY
shall be comparable to the best local and national standards.
6.8 Materiality and Waiver of Breach
CITY and CONTRACTOR agree that each requirement, duty, and obligation set
forth in these Contract Documents is substantial and important to the formation of
this Contract and, therefore, is a material term hereof.
CITY's failure to enforce any provision of this Contract shall not be deemed a
waiver of such provision or modification of this Contract. A waiver of any breach
of a provision of this Contract shall not be deemed a waiver of any subsequent
breach and shall not be construed to be a modification of the terms of this
Contract.
6.9 Severance
In the event a portion of this Contract is found by a court of competent jurisdiction
to be invalid, the remaining provisions shall continue to be effective unless CITY
or CONTRACTOR elects to terminate this Contract. An election to terminate this
Contract based upon this provision shall be made within seven (7) days after the
finding by the court becomes final.
6.10 Applicable Law and Venue
This Contract shall be enforceable in Miami -Dade County, Florida, and if legal
action is necessary by either party with respect to the enforcement of any or all of
the terms or conditions herein exclusive venue for the enforcement of same shall
lie in Miami -Dade County, Florida. By entering into this Contract, CONTRACTOR
and CITY hereby expressly waive any rights either party may have to a trial by
jury or to file permissive counterclaims in of any civil litigation related to, or
arising out of the Project. CONTRACTOR shall specifically bind all
subcontractors to the provisions of this Contract. Each party shall bear their own
attorney's fees.
6.11 Amendments
No modification, amendment, or alteration in the terms or conditions contained
herein shall be effective unless contained in a written document prepared with
the same or similar formality as this Contract and executed by the City Manager
and CONTRACTOR.
6.12 Prior Agreements
This document incorporates and includes all prior negotiations, correspondence,
conversations, agreements, and understandings applicable to the matters
contained herein and the parties agree that there are no commitments,
agreements or understandings concerning the subject matter of this Contract that
are not contained in this document. Accordingly, the parties agree that no
deviation from the terms hereof shall be predicated upon any prior
representations or agreements, whether oral or written. It is further agreed that
no modification, amendment or alteration in the terms or conditions contained
herein shall be effective unless set forth in writing in accordance with Section
6.11 above.
IN WITNESS WHEREOF, the parties have set their hands and seals parties
have set their hands and seal on the day and year first above written.
"City"
CITY OF MIAMI, a municipal
ATTEST: corporation
By:
Priscilla A. Thompson, City Clerk Joe Arriola, City Manager
ATTEST:
"Contractor"
a corporation
By:
Print Name: Print Name:
Title: Corporate Secretary Title: President
APPROVED AS TO FORM AND APPROVED AS TO INSURANCE
CORRECTNESS: REQUIREMENTS:
Jorge L. Fernandez Risk Management Administrator
City Attorney Dania Carrillo
THE CITY REQUIRES FOUR (4) FULLY -EXECUTED CONTRACTS, FOR
DISTRIBUTION.