HomeMy WebLinkAboutProject Analysis FormsFINAL PROJECT ANALYSIS FORM Department of Capital improvements City of Miami Date Prepared: 11/5/2004 Revised Date: Revised Date: Revised Date: PROJECT NAME: FLAGAMIIWEST END STORM SEWER PUMP STATIONS NOS.1, 2, 3, & 4 ADDRESS / LOCATION: REFER TO PROJECT SCOPE BELOW PROJECT No.: B-50696 NET OFFICE: Flagami DISTRICT: D1 414 CLIENT DEPT: EST. PROJECT COST: $5,235,149 CLIENT CONTACT: TEL.: ALLOCATED FUNDS: $0 PROJECT MANAGER: JOSE L. LAGO, P.E. TEL.: 305-416.1252 PROCUREMENT: Formal Bid CONSTR. MANAGER: TEL.: PROJECT TEAM: INSPECTOR / CEO: TEL.: EST. DESIGN START: 5/30/2002 EST. DESIGN END: 3/15/2005 EST. BID ADV.: 3/24/2005 EST. AWARD DATE: 7/28/2005 EST. CONSTRUCTION START: 9/1/2005 EST. CONSTRUCTION END: 3/1/2007 PRODUCTION PHASE A. Design Svcs. - Outside Consultant 1 Basic Fees: 2 Additional Services: B. Design Svcs. - CIP 1 In-house Basic Design Fee: 2 In-house Additional Design Services: Prime Come/hint TYLIN JNT'L / NJ ROSS C Production Management Services 1 Prod. Mgmt. of Outside Consultant by CIP: 2 Prod. Mgmt. of Outside Consultant by Industry Partner: 0.0% $0 SUB -TOTAL: $0 Peroentege 0.0% 0.0% SUS -TOTAL: $0 $0 $0 0.0% $0 0.0% $0 SUB -TOTAL: $0 D Miscellaneous Services 1 Survey; 2 Re -plat: Vendor: Vendor: 0.0% $0 3 Geotechnlcel Testing: Vendor: 4 Utility Locations (Soft Digs): vendor: 5 Asbestos Survey: Vendor: 8 Energy / HVAC Calculations: Vendor: 7 Phase I Environmental: Vendor: 8 Phase II Environmental: Vendor: 9 Structural Testing: Vendor: 10 Archeological Survey: Vendor: 11 Other: Vendor: SUB -TOTAL: E Special Fees / Assessments: 1 DERM (Plane review, environmental permits, etc.): 2 Miami -Dade County Water and Sewer Department (Plan review) Fee Waiver r 3 Florida Department of Environmental Protection (Permits): 4 FOOT (Plane review, Inspections, etc.): 5 South Florida Water Management District (Permits); 8 U.S. Army Corps of Engineers (Plane review, permits): 7 HRS (Plane review, inspections, etc.): 8 Other: SUS -TOTAL: $0 PRODUCTION PHASE TOTAL: $p CONSTRUCTION PHASE F Construction: 1 Construction Estimate: 2 Contingency Allowance: Contractor: Sauthnaetorn Engineering Contractors, Inc. $4,632,875 0.0% $0 3 Data & Telecommunication Systems (IT Dept.): 4 Fixtures, Furniture and Equipment: 5 WASA System Betterment: 6 FPL Contribution -In Aid -of Construction. 7 Other; SUB -TOTAL: $4,832,875 Page 1 of 2 FLAGAM1IWEST END STORM SEWER PUMP STATIONS NOS. 1, 2, 3, & 4 FINAL B-50696 1_ PROJECT COST ESTIMATE G . City and other Gov't Agencies Permit Fees 1 Clty of Miami Permits: Bldg. Dept. E Public Works I✓ 2 Miami -Dade County Impact Fees: 3 Miami -Dade County Archeological Monitoring: 4 Other: SUB -TOTAL: $O CONSTRUCTION PHASE TOTAL: . $4,032,875 CONSTRUCTION ADMINISTRATION H Construction Inspection Services - CIP: 0.0% $0 I Construction Mgmt - Industry Partner: 0.0% $0 J Construction Engineering Observer (CEO) - Industry Partner 10.0% $463,288 K JOC Administration 0.0% $0 CONSTRUCTION ADMINISTRATION TOTAL: $463,288 ADMINISTRATIVE EXPENSES L CIP Dept.(Mgmt.JBudgetIProcurement/Comm.). 2,0% $92,858 M industry Partner Program Mgmt. Support 1.0% $48,320 ADMINISTRATIVE EXPENSES TOTAL: $138,988 LAND ACQUISITION EXPENSES N Land Cost: 0 Transaction Costs: 0.0% $0 LAND ACQUISITION TOTAL: $0 GRAND TOTAL - ESTIMATED PROJECT COST: $5,235,149 PROJECT SCOPE THE PROJECT INCLUDES CONSTRUCTION OF STORM SEWER IMPROVEMENTS CONSISTING OF FOUR (4) PUMP STATIONS, CONNECTING FORCEMAINS, AND WATER QUALITY UNITS INCLUDING SURFACE RESTORATION. ENGINEERING CONSULTANT POST DESIGN SERVICES SHALL ALSO BE PART OF THIS WORK. THE PUMP STATIONS SHALL BE CONSTRUCTED AT THE FOLLOWING LOCATIONS WITHIN THE R-0-W: 1) SW 63 COURT AND SW 6 STREET 2) SW 83 COURT AND SW 2 STREET 3) NW 64 COURT AND NW 3 STREET 4) NW 62 COURT AND NW 5 STREET FOR QUESTIONS OR MORE DETAILS REGARDING THE PROJECT, PLEASE CONTACT JOSE L. LAGO, P.E , PROJECT MANAGER, AT 305-416-1252. ur ti q 2 NOTE: THIS IS A FEMA FUNDED HAZARD MITIGATION PROJECT. THE DESIGN PHASE OF THIS PROJECT WAS COMPLETED UNDER PROJECT NUMBERS B-5673-131, B-5673-B2, B-5673-C1 AND B-5673-C2. FUND SOURCES Fund: CIP # Flacal Year Avelleble Amount: Fund: CIP # Amount: Fund: CIP # Amount: Fund: CIP # Amount: Fund: CIP # Amount: Fund: CIP # Amount: TOTAL. ALLOCATED AMOUNT: $U. O VALIDAT Project Manager: Sr. Project Manager: Reviewed by: Accepted by: JOSE L. LAGO, P.E. CESAR GONZALEZ CIP Budget Administrator Sign Sign Data: 7/1 /2005 Date: Date: Date: Director of the Client Depadment Sign Copies To' CLIENT DEPARTMENT, ALL CIP SECTION CHIEFS, CIP SENIOR ACCOUNTANT, HDR PROGRAM MANAGER Page 2 of 2 FINAL PROJECT ANALYSIS FORM ' Department of Capital Improvements City of Miami Data Prepared: 11 /5/2004 Revised Dale: Revised Date: Revised Dale: PROJECT NAME: FAIRLAWN STORM WATER PUMP STATION PROJECT, PHASE IlA ADDRESS / LOCATION: REFER TO PROJECT SCOPE BELOW PROJECT No.: B-50702 NET OFFICE: Flagaml DISTRICT: D1 CLIENT DEPT: EST. PROJECT COST: $2,352,069 CLIENT CONTACT: TEL.: ALLOCATED FUNDS: $0 PROJECT MANAGER: JOSE L. LAGO, P.E. TEL.: 305-416-1252 PROCUREMENT: Formal Bid CONSTR. MANAGER: TEL.: PROJECT TEAM: INSPECTOR / CEO: TEL.: EST. DESIGN START: 5/30/2002 EST. DESIGN END: 3/15/2005 EST. BIDADV.: 3/24/2005 EST, AWARD DATE: 7/28/2005 EST. CONSTRUCTION START: 9/1/2005 EST. CONSTRUCTION END: 9/1/2006 PROJECT COST ESTIMATE PRODUCTION PHASE Percentage A. Design Svcs. • Outside Consultant Prime Coneultent: TYLIN INT'L / HJ ROSS $0 1 Beek Fees: 0.4% 2 Additional Services: 0.0% $0 B. Design Svcs. - CIP 1 In-house Basic Design Fee: SUB -TOTAL: 0.0% $0 $0 2 In-house Additional Design Services: 0.0% $0 C Production Management Services 1 Prod. Mgmt. of Outside Consultant by CIP: 2 Prod. Mgmt. of Outside Consultant by Industry Partner: SUB -TOTAL: a.R% $0 $0 0.0% $0 D Miscellaneous Services 1 Survey: Vendor: SUB -TOTAL: $0 2 Re -plat: vendor: 3 Geotechnicat Testing: vendor: 4 Utility Locations (Soft Digs): vendor: 5 Asbestos Survey: Vendor: 6 Energy / HVAC Calculations: vendor: 7 Phase I Environmental Vendor: 8 Phase II Environmental: Vendor 9 Structural Testing: Vendor: 10 Archeological Survey: Vendor _ 11 Other: Vendor: $0 E Special Fees / Assessments: 1 DERM (Plans review, environmental permits, etc.): SUB -TOTAL: Fee Waiver t- 2 Miami -Dade County Water and Sewer Department (Plan review) 3 Florida Department of Environmental Protection (Permits): 4 FDOT (Plans review, inspections, etc.): 5 South Florida Water Management District (Permits): 6 U.S. Army Corps of Engineers (Plane review, permits): 7 HRS (Plans review, inspections, etc.): 8 Other: SUB-TOTAL: $0 PRODUCTION PHASE TOTAL: $0 CONSTRUCTION PHASE F Construction. Contractor: Southeastern Engineering ConIredors, Inc. $2,081,477.40 1 Construction Estimate: 2 Contingency Allowance: 0.0% $0 3 Data & Telecommunication Systems (IT Dept): 4 Fixtures, Furniture and Equipment: 5 WASA System Betterment: 6 FPL Contribution -in -Aid -of Construction: 7 Other: SUBTOTAL: $2,081,477 Page 1 of 2 FAIitLAWN STORM WATER PUMP STATION PROJECT, PHASE IIA FINAL B-50702 PROJECT COST ESTIMATE G' City and other Gov't Agencies Permit Fees 1 City of Miami Permits: Bldg. Dept. r Public Wortta IV 2 Miami -Dade County Impact Fees: 3 Mleml-Dade County Archeological Monitoring: 4 Other: SUBTOTAL: $0 CONSTRUCTION PHASE TOTAL: $2,081,477 CONSTRUCTION ADMINISTRATION H Construction Inspection Services - CIP: 0.0% $0 Construction Mgmt. - Industry Partner: 0.0% $0 J Construction Engineering Observer (CEO) - Industry Partner 10.0% $208,148 K JOC Administration 0.0% $0 CONSTRUCTION ADMINISTRATION TOTAL: 8208,148 ADMINISTRATIVE EXPENSES L CIP Dept.(Mgmt./Budget/Procurement/Comm.): 2.0% $41,630 M Industry Partner Program Mgmt. Support: 1.096 $20,815 ADMINISTRATIVE EXPENSES TOTAL: $62,444: LAND ACQUISITION EXPENSES N Land Cost: 0 Transaction Costs: 0.0% $0 LAND ACQUISI`FION;TOTAL, $0 GRAND TOTAL - ESTIMATED PROJECT COST: $2,352,0B9 PROJECT SCOPE THE PROPOSED PROJECT INVOLVES THE CONSTRUCTION OF A NEW GRAVITY CONVEYANCE SYSTEM CONNECTED TO A NEW PUMP STATION 8, FORCE MAIN OUTFALLING TO THE C-4 CANAL (VIA A NEW GUTFALL). THIS PROJECT INCLUDES MILLING AND RESURFACING OF THE AFFECTED ROADWAYS BY THE CONSTRUCTION. THE PROJECT AREA IS BOUNDED BY NW 4 TERRACE, NW 47 AVENUE, NW 7 STREET, NW 51 AVENUE, AND THE SW PORTION OF ANTONIO MACEO PARK. CONSULTANT ENGINEERING POST DESIGN SERVICES SHALL BE PART OF THIS WORK. FOR QUESTIONS OR MORE DETAILS REGARDING THE PROJECT, PLEASE CONTACT JOSE L. LAGO, P.E., PROJECT MANAGER, AT 305-416-1252. 11 NOTES 1 NOTE: THIS PROJECT WAS DESIGNED BY TYLIN INTERNATIONAL/HJ ROSS AT NO EXPENSE TO THE CITY OF MIAMI. L_ FUND SOURCES Fund: CIP # Fiscal Year Ayalleble Amount: Fund: CIP # Amount: Fund: CIP # Amount: Fund: CIP # Amount: Fund: CIP # Amount: Fund: CIP # Amount: TOTAL ALLOCATED AMOUNT:. $0 VALIDATION Protect Manager: Sr, Protect Manager: Reviewed by: Accepted by: JOSE L. LAGO, P.E Date: 7/1/2005 CESAR GONZALEZ Sign Data: Sign Date: CIP Budget Administrator Sign Date: Director of the Client Department Sign Copies To: CLIENT DEPARTMENT, ALL CIP SECTION CHIEFS, CIP SENIOR ACCOUNTANT, HOR PROGRAM MANAGER Page 2 of 2