HomeMy WebLinkAboutSummary FormDate: 6/28/2005
AGENDA ITEM SUMMARY FORM
FILE ID: 05-o 66
Requesting Department: Public Works
Commission Meeting Date: 7/28/2005 District Impacted: All
Type: ® Resolution 0 Ordinance ❑ Emergency Ordinance ❑ Discussion Item
❑ Other
Subject: Resolution awarding a contract to Envirowaste Services Group, Inc in the amount of $479,270
for "Citywide Storm Sewer Cleaning Project - North Zone, B-50711"
Purpose of Item:
Award a contract to Envirowaste Services Group, Inc., a company located at 5931 SW 88 Street,
Miami, whose Principal is Mr. Rafael Barba, President, for the project entitled "Citywide Storm
Sewer Cleaning Project - North Zone, B-50711" in the amount of $479,270 Total Bid (2 years). This
contract is for a two year period and the City reserves the right to renew for two additional one year
periods.
Background Information:
On June 16, 2005, the Public Works Department received formal bids to clean the storm sewer
system. Eight (8) prospective bidders picked up specifications and two (2) contractors submitted bids.
Envirowaste Services Group, Inc. submitted the lowest responsible and responsive bid in the amount
of $479,270 (2 years). Funds are allocated from PW General Account No. 001000.311003,6340, in
the amount of $479,270 to cover contract costs.
Budget Impact Analysis
NO Is this item related to revenue?
YES Is this item an expenditure? If so, please identify funding source below.
General Account No: 001000.311003.6.340 a -..al 001000, its o0 3 6. 27 a
Special Revenue Account No: +� � Iae3• 1 I r; +r
CIP Project No:
NO Is this item funded by Homeland Defense/Neighborhood Improvement Bonds?
Start Up Capital Cost:
Maintenance Cost:
Total Fiscal Impact: $479,270.00
CIP
Final Approvals
(SIGN AND DATE}
Budget
If using or receiving capital funds
Grants
Purch sin
Chief
Risk Managem
Dept. Director
City Manager
Page 1 of 1