HomeMy WebLinkAboutSchool Board Review CommentsR r 20 2005 9 : 09RM SITE PL RNN I NG
305995475Q p.2
**REVISED"*
SCHOOL IMPACT REVIEW ANALYSIS
April 19, 2005
FOR INFORMATIONAL PURPOSES ONLY; THE REQUIREMENTS UNDER THE
INTERLOCAL AGREEMENT FOR SCHOOL FACILITY PLANNING ARE NOT
TRIGGERED SINCE THE APPLICANT IS NOT REQUESTING ADDITIONAL
RESIDENTIAL DENSITY OVER WHAT IS CURRENTLY ALLOWED IN THE
PROPERTY'S ZONING CLASSIFICATION.
APPICATION: Bayview Market
REQUEST: Major Use Special Permit (PAB April 20, 2005)
ACRES: 6.98 net acres and 8.715 gross acres
ZONING: C-2 Liberal Commercial — allows 150 DUlacre
LOCATION: Approximately at NE 2"d Avenue and 17t' Street, Miami
MSA: 4.7 = 0.22 Multifamily
NUMBER OF
UNITS:
24 loft units (6.98 net acres x 150 DU/acre = 157 Max.
residential units allowed)
ESTIMATED STUDENT
POPULATION: 5 students*
ELEMENTARY: 2
MIDDLE: 1
SENIOR: 2
SCHOOLS SERVING AREA OF APPLICATION:
ELEMENTARY: Phillis Wheatley Elementary— 1801 N.W. First PI.
MIDDLE: Jose de Diego Middle — 3100 N.W. 5 Avenue
SENIOR HIGH: Booker T. Washington Sr. — 1200 N.W. 6 Avenue
*Based on Census 2000 information provided by the Miami -Dade County Department of
Planning and Zoning.
fipr 20 2005 5:09AM SITE PLANNING 3059954750
P.3
The following population and facility capacity data are as
Information Technology, as of October 2004.
STUDENT
POPULATON
Phillis Wheatley 373/
Elementary 375*
Jose De Diego 1,170/
Middle 1,171'
Booker T. 1,502/
Washington 1,504*
FISH DESIGN
CAPACITY
PERMANENT
637
1,036
% UTILIZATION
FISH DESIGN
CAPACITY
PERMANTENT
P
59%/
59%*
113%/
113%*
reported by the Office of
NUMBER
OF
PORTABLE
STUDENT
STATIONS
0
0
% UTILIZATION
FISH DESING
CAPACITY
PERMANENT
AND
RELOCATABLE
59%I
59%*
113%/
113%*
57%/ 57%/
2,624 57%* 0 57%*
* increased student population as a result of the proposed development
Note:
1) The cumulative effect of other approved or proposed developments in the vicinity is
not included as part of this analysis.
2) Figures above reflect the impact of the class size amendment.
3) Pursuant to the Interlocal Agreement, none of the schools meet the review
threshold.
PLANNED RELIEF SCHOOLS IN THE AREA
(Information included in proposed 5-Year Capital Plan, 2005-2009, dated January 2005)
Projects In Planning, Design or Construction
School Status Occupancy Date
N/A
Proposed Relief Schools
School Funding Year
New Middle School FY 06-07
State School "GG-1"
(Jose De Diego Middle relief)
(1,241 student stations)
OPERATING COSTS: According to Financial Affairs, the average cost for K-12 grade
students amounts to $6,549 per student. The total annual operating cost for additional
students residing in this development, if approved, would total $32,745.
'Apr 20 2005 9: 09faM SITE PLANNING
3059954760
P.4
CAPITAL COSTS: Based on the States April 2005 student station cost factors*, capital
costs for the estimated additional students to be generated by the proposed
development are:
ELEMENTARY
MIDDLE
SENIOR
Total Potential Capital Cost
$ 13,531 = $27,062
$ 15,513 = $15,513
$ 20,529 - $41,058
$83,633
*Based on Information provided by the Florida Department of Education, Office of
Educational Facilities Budgeting. Cost per student station does not include land cost.