HomeMy WebLinkAboutattachment E4aATTACHMENT E-4A
WATERWAYS ASSISTANCE PROGRAM
APPLICATION EVALUATION AND RATING FORM
DEVELOPMENT & CONSTRUCTION PROJECTS
THIS ATTACHMENT IS TO BE COMPLETED IF YOUR PROJECT IS A DEVELOPMENT OR
CONSTRUCTION PROJECT BUT IS NOT AN INLET MANAGEMENT OF BEACH '
RENOURISHMENT PROJECT.
CATEGORY RATING
& RATING POINTS
POINTS
AVAILABLE
EVALUATION CRITERIA
PERMITTING
(For revluwer only)
(1.2 points)
(1..2 points)
List all of the necessary permits that are required for the proJac.t,
the date of application, and the anticipated date of receipt of the
required permits, If permits are NOT required, explain why not,
The following environmental permits are required:
Agency Date awned fQr holed
FDEP 1/05 TBD
ACM 1/05 TBD
DERM 1/0S TBD
(12) Havo all permits been applied for? Is timing time
sufficient to meet application deadline? (If the project is a
Phase 1 project a minimum score of 2 points will be awarded)
(13) Has the project received all of the required parmil:s?
(If the project is a Phase I project a minimum score of 2
points will be awarded)
PROJECT DESIGN
if
(For reviewer only)
', (1.2 points)
Dist the status of the design of this project. Describe any unique
design aspects of this project that enhance public usage or ae00631
decrease environmental impacts, improve water quality or reduce
coats.
The final design has been completed and the construction 4ocuu111e4t
will be completed within three months after the execution of the grant
contract. The proposed improvements include: water quality
improvements through the stabilization of the unconsolidated
shorelines utilizing red mangroves, removal of exotic vegetation,
restoration of native upland vegetation, creation of an interpretliva
nature trail and picnic sites, and the installation of are
education/tour boat docking facility,
(14) Has the design work been completed? (A Phase I project
should be evaluated based upon the design work completed to
date). Are there unique beneficial aspects to the proposed design?
M--M.-
CONSTRUCTION TECHNIQUES Briefly explain the construction techniques to be utilized for this
project.
Miami -Dade County (PERM) has agreed to assist with the propaseci,
enhancement project. DERM has been involved in restoring and,
enhancing Miami -Dade County for over 25 years, and has developed
cost-effective, environmentally sound, habitat restoration and
enhancement techniques. A shallow draft barge will deliver all
equipment and materials to the islands. Turbidity control measures
will be installed prior to the initiation of the boat docking facility and
will remain in place for the duration of' construction. School groups
will be involved in the planting and success monitoring of till
completed project.
(For reviewer only)
(1.3 points) (15) Are the construction techniques appropriate for the
project site?
CONSTRUCTION MATERIALS List the materials to be utilized for this project. 'What is the design
life of the proposed materials? Describe any recyclable material tit
be utilized.
The shoreline stabilization will be accomplished utilizing
native red mangroves. The exotic vegetation will be
selectively cleared, followed by the planting of salt/drought
tolerant native vegetation. The docking facilities will be
constructed of long lasting materials.
(1-3 paints) (16) Are the construction materials of lasting quality? Are
recyclables utilized?
RATING POINT
TOTAL
(Note: The total maximum score possible is 50 points and the minimum score possible is 16 ;points. A
score of 35 points or mare is required to be considered for funding.)
Form No, 91-25A
(Effective Date: 3-21-01)