NE 71st STREET STORM SEWERS PROJECT, B-5690
C.I.P. Project No: 352216
"Exhibit C"
Project Design & Permitting Schedule(*)
ID #
Task Name and/or Activity Description
Duration
(WEEKS)
Start
Date
Finish
Date
01
TASK 1: SURVEY.
6
8/15/03
10/01/03
02
TASK 2: GEOTECHNICAL TESTING.
4
8/15/03
9/15/03
03
PHASE 01: SCHEMATIC DESIGN.
N/A
N/A
N/A
04
CITY SCHEMATIC REVIEW.
N/A
N/A
N/A
05
PHASE 02: DESIGN DEVELOPMENT.
9
8/15/03
10/21/03
06
CITY'S DESIGN DEVELOPMENT REVIEW.
2
10/21/03
11/07/03
07
PHASE 03: 50% CONSTRUCTION DOCUMENTS.
4
11/07/03
12/07/03
08
CITY'S 50% CONSTRUCTION DOCUMENT REVIEW.
2
12/07/03
12/21/03
09
PREPARE & SUBMIT 90% CONSTRUCTION
DOCUMENTS TO THE CITY
3
12/21/03
1/15/04
10
CITY'S 90% CONSTRUCTION DOCUMENT REVIEW
2
1/15/04
1/31/04
11
PREPARE & SUBMIT 100% CONSTRUCTION
DOCUMENTS TO THE CITY
2
2/01/04
2/15/04
12
CITY'S 100% CONSTRUCTION DOCUMENT REVIEW
1
2/15/04
2/21/04
13
REVISE PER CITY COMMENTS AND SUBMIT
PERMITTING PACKAGE TO DERM.
1
2/21//04
2/30/04
14
DERM'S REVIEW AND APPROVAL PERIOD.
5
3/01/04
4/07/04
15
SUBMIT FINAL CONSTRUCTION DOCUMENTS TO
THE CITY.
1
4/07/04
4/15/04
(*) The above schedule assumes that a written Notice to Proceed will be received from the
City by AUGUST 15, 2003 and review period by the City and the regulatory agencies will
not exceed the duration allocated in this schedule.