CERTIFICATE OF SUBSTANTIAL COMPLETION
EXHIBIT G
CERTIFICATE OF SUBSTANTIAL COMPLETION:
PROJECT: Little Haiti Park ARCHITECT:
B1D/CONTRACT NUMBER:
TO: City of Miami
CONTRACT FOR:
NOTICE TO PROCEED DATE:
FIRM: Recreational Design & Construction Inc.
DATE OF ISSUANCE:
PROJECT OR DESIGNATED PORTION SHALL INCLUDE:
The Work performed under this Contract has been reviewed and found to be substantially
complete and all documents required to be submitted by FIRM under the Contract
Documents have been received and accepted. The Date of Substantial Completion of the
Project or portion thereof designated above is hereby established as
which is also the date of commencement of applicable warranties required by the Contract
Documents, except as stated below.
DEFINITION OF DATE OF SUBSTANTIAL COMPLETION
The Date of Substantial Completion of the Work or portion thereof
designated by COM is the date certified by ARCHITECT when all
conditions and requirements of permits and regulatory agencies
have been satisfied and the Work, is sufficiently complete in
accordance with the Contract Documents, so the Project is
available for beneficial occupancy by COM. A temporary
Certificate of Occupancy must be issued for Substantial
.tabzweL issuaricluf a
EXHIBIT G (cont.)
temporary Certificate of Occupancy or the date thereof are not to be
determinative of the achievement or date of Substantial Completion.
A list of items to be completed or corrected, prepared by ARCHITECT, is attached hereto.
The failure to include any items on such list does not alter the responsibility of FIRM to
complete all work in accordance with the Contract Documents. The date of commencement
of warranties for items on the attached list will be the date of final payment unless otherwise
agreed in writing.
ARCHITECT
BY DATE
In accordance with Section 37 of the Contract, FIRM will complete or correct the work on the
list of items attached hereto within thirty (30) days from the above Date of Substantial
Completion.
FIRM
BY DATE
COM, through the Contract Administrator, accepts the Work or portion thereof designated by
COUNTY as substantially complete and will assume full possession thereof at
(time) on (date).
City of Miami
By Contract Administrator DATE
The responsibilities of COM and FIRM for security, maintenance, heat, utilities, damage to
the work and insurance shall be as follows: