HomeMy WebLinkAboutsecond amendmentqtCOND AMENDMENT TO CONTRA
"ORANGE BOWL STADIUM STRUCTURAL REPAIRS 2003, B-30297"
This second Amendment to the Contract for the project entitled "ORANGE BOWL STADIUM
STRUCTURAL REPAIRS 2003, B-30297" between the Contractor and the City, awarded to the
Contractor by informal solicitation, authorized by the City Commission Resolution No. 03-829, on
September 2, 2002, which is d emed as being incorporated by reference as if set for in full herein, is
entered into this day of S F' , 2004, by and between the City of Miami, a municipal
corporation of the State of Florida (t e "City"), and "Professional General Contractors, Inc.", a Florida
corporation ("Contractor") for the purpose of amending that certain Contract dated July 17, 2003 between
the City and the Contractor (the "Contract") as set forth herein.
RECITALS:
WHEREAS, pursuant Resolution No. 03-829, adopted by the City Commission on July 17, 2003,
the City and the Contractor entered into the Contract for all labor, materials and equipment and perform
all the work in the form and manner provided by the Contract Documents for the project entitled
"ORANGE BOWL STADIUM STRUCTURAL REPAIRS 2003, B-30297"; and
WHEREAS, the City shall pay to the Contractor, (as provided in the attachment "A" and other
Contract Documents for this project), the sum of ($1,949,03I.00), One Million Nine Hundred Forty Nine
Thousand Thirty One Dollars; and
WHEREAS, the City Commission, by Resolution No. 04-0179, adopted on March 25, 2004, has
authorized an increase in the amount of the Contract in ($500,000) Five Hundred Thousand to pay. for the
First Amendment to the contract to increase the scope of work to repair 15 additional supports of the upper
trusses at the North Side of the Stadium that were found severely corroded, and to replace four access ramps
that were severely damaged; and
WHEREAS, severe structural overstress has been observed in the concourse at + 36' - 0" Elev., at
the North Side of the Stadium, where the 4" concrete slab that conform the concourse is showing cracks and
deflections that represent structural failures in nature, indicating that the structural integrity of the slab is
lost; and
WHEREAS, the City had received additional request from the Consultants to do remedial repair
work in several bent beam that are severely corroded and need to be replaced; and
WHEREAS, the Consultants, Bliss & Nyitray, Inc, who are under contract to the City to oversee
the structural repairs, are recommending that the deficiencies must be repaired to restore the structural
integrity of the stadium in a timely manner prior to the 2004 UM football season.
WHEREAS, the additional work, and materials are required to complete the proposed work in an
estimated amount of ($400,000) Four Hundred Thousand; and
WHEREAS, the City Commission, by Resolution No. 04-0428 adopted on June 24, 2004,has
authorized an increase in the amount of the contract in ($400,000) Four Hundred Thousand; and
0
NOW THEREFORE, in consideration of the foregoing and of the mutual agreements and
B B !�'
covenants of the parties as set forth in the Contract, the City and the Contractor agree as follows:
Compensation: Article 2 of the Contract is hereby amended to increase the amount of compensation from
$2,449,031.00 to $2,849,031.00; the additional amount to be used exclusively for the payment of the
additional work due to restore the structural integrity of the stadium in a timely manner prior to the 2004
UM football season.
CITY OFMIAA¢I
AUG •4 2004
ate
J • - Arriola
Cis Manager
Attest:
Priscilla Thompso
City Clerk
APPROVED AS TO LEGAL FORM
AND CORRECTNESS:
Date Th fA A7
Maria4Y. Chtaro,
Interim City Attorney
APPROVED AS TO ENGINEERING:
e C. Cano, P.E., Deputy Director
CIP De artment titgG
Ver
CONTRACTOR
Date
arm / / /) '
R. Ramos, President;f / ,/
Professional General Contractors Inc...
Attest:
Date
orporate Secretary
(AFFIX CORPORATE SEAL)
INSURANCE REQUIREMENT
APPROVED:
T. :a/2a Date 7/I �-!o
Dania F. Carrillo,
Risk Management Administrator