File Number: 05-00096 Final Action Date: 2/24/2005
A RESOLUTION OF THE MIAMI CITY COMMISSION, WITH ATTACHMENT(S), BYA
FOUR -FIFTH (4/STHS) AFFIRMATIVE VOTE, AFTER AN ADVERTISED PUBLIC
HEARING, RATIFYING, APPROVING AND CONFIRMING THE CITY MANAGER'S
FINDING OF AN EMERGENCY AND WAIVING COMPETITIVE BIDDING
PROCEDURES IN THE AWARD OF ADDITIONAL WORK TO PROFESSIONAL
GENERAL CONTRACTORS, INC., THE CONTRACTOR CURRENTLY
PERFORMING STRUCTURAL WORK FOR THE PROJECT ENTITLED "ORANGE
BOWL STADIUM STRUCTURAL REPAIRS, B-30297" (FORMERLY B-3297);
PURSUANT TO CONTRACT DATED SEPTEMBER 2, 2003, AS AMENDED,
AUTHORIZED BY RESOLUTIONS NO. 03-829, 04-0179, AND 04-0428
("CONTRACT"), APPROVING AN AMENDMENT TO THE CONTRACT TO INCLUDE
THE ADDITIONAL WORK AND INCREASE THE COMPENSATION TO THE
CONTRACTOR BY $3,717,005 FROM $2,849,031 TO $6,566,036; AMENDING
RESOLUTION NO. 04-0428, TO REFLECT SAID INCREASE; AUTHORIZING THE
CITY MANAGER TO EXECUTE THE THIRD AMENDMENT TO THE CONTRACT, IN
SUBSTANTIALLY THE ATTACHED FORM; ALLOCATING FUNDS FOR SAID
CONTRACT INCREASE FROM CAPITAL IMPROVEMENTS PROJECT NO. 324002.
WHEREAS, pursuant to Resolution No. 03-829, adopted July 17, 2003, the City of Miami ("City")
entered into a contract ("Contract") with Professional General Contractors, Inc. ("Contractor"), for the
project entitled "Orange Bowl Stadium Structural Repairs, B-30297 (formerly B-3297)" ("Project"); and
WHEREAS, the contract sum, under the Contract, was $1,949,039, subject to additions and
deductions and based on sum and unit prices; and
WHEREAS, Resolution No. 04-0179, adopted March 25, 2004, authorized the City Manager to
increase the contract sum by an amount not to exceed $500,000, thereby increasing the contract sum
from $1,949,039 to $2,449,031, to pay for the repair of 15 additional supports of the upper trusses of
the north side of the Orange Bowl Stadium ("Stadium"), and to replace four (4) access ramps that
were severely damaged; and
WHEREAS, Resolution No. 04-0428, adopted June 24, 2004, authorized the City Manager to
further increase the contract sum by an amount not to exceed $400,000, thereby increasing the
contract sum from $2,449,031 to $2,849,031, to pay for repairs to severely overstressed structures in
the concourse at + 36' - 0" Elevation, at the north side of the Stadium, where the 4" concrete slab that
conforms the concourse was showing cracks and deflections that represented structural failures in
nature, indicating that the structural integrity of the slab was lost; and
WHEREAS, during the course of the approved work, generalized severe deterioration has been
observed in the concourse at + 36' - 0" Elevation at the north and south side of the Stadium, where
the 3" concrete slab and the supporting structural framing are showing the same cracks and
deflection that were present in the limited repair done under the Second Amendment to the contract;
City of Miami
Page 1 of 3 File Id: 05-00096 (Version: 2) Printed On: 10/28/2016
File Number: 05-00096 Enactment Number: R-05-0132
and
WHEREAS, the following additional elements in the lower bowl require extensive repair because
of the deterioration caused by corrosion and concrete distress related to corrosion: the tread and riser
plates at the expansion joints and the end of support of the stands; the raker beam and the
connection to the columns; the toe and head of the vomitory ramps, as well as the lateral bracing of
the main structural framing ("Additional Repairs"); and
WHEREAS, in addition to the Additional Repairs, it is necessary to replace the concrete slabs
at the 9'-6" concourse at the north and south of the Stadium; repair and replace the tie beams along
grid line M; life -safety improvements along the stem wall at the upper section of the lower bowl at the
West End Zone, and perform all other related structural work ("Additional Anticipated Work"), but
construction drawings for such Additional Anticipated Work have not yet been completed; and
WHEREAS, the consultants retained by the City to oversee the structural repairs of the Orange
Bowl Stadium recommend that the Additional Repairs and the Additional Anticipated Work be
completed prior to the 2005 University of Miami football season and failure to complete the repairs by
August 2005 will further delay the planned redevelopment of the Orange Bowl Stadium; and
WHEREAS, the Contractor is fully familiar with the Orange Bowl Stadium, is qualified and willing
to perform the Additional Repairs and Anticipated Additional Work by August 2005, under the terms of
the Contract, and Florida Statute 255.20 exempts repair and maintenance of existing public facilities
from formal competitive bid requirements; and
WHEREAS, the Contractor has estimated the cost of the Additional Repairs, including labor and
materials, not to exceed $2,954,256 and the estimated cost of the Additional Anticipated Work,
including labor and materials, not to exceed $762,749; and
WHEREAS, it is in the best interest of the City to amend the Contract to authorize the Contractor
to perform the Additional Repairs and to give the City Manager the authority to request the
performance of the Additional Anticipated Work, and increase the Contract Sum accordingly,; and
WHEREAS, funds in the amount of $3,717,005 for the Additional Repairs and the Anticipated
Additional Work are available from Project No. 324002 entitled "Orange Bowl Stadium Structural
Repairs, B-30297"; and
WHEREAS, Florida Statute 255.20 (c )(5) exempts projects undertaken as repair or maintenance
of an existing public facility from competitive bidding; and
WHEREAS it is the finding of the City Commission, based on the representations of the Capital
Improvements and Transportation Department and the City Administration that this Project qualifies
for that exemption; and,
WHEREAS, §18-89 of the Code of the City of Miami, Florida, as amended ("City Code") provides
that the findings contained herein be made at a properly advertised public hearing by the City of
Miami City Commission;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI,
City of Miami Page 2 of 3 File Id: 05-00096 (Version: 2) Printed On: 10/28/2016
File Number: 05-00096 Enactment Number: R-05-0132
FLORIDA:
Section 1. The recitals and findings contained in the Preamble to this Resolution are adopted by
reference and incorporated as if fully set forth in this Section.
Section 2. By a four -fifth (4/5ths) affirmative vote, after an advertised hearing, the City Manager's
finding of an emergency, waiving competitive bidding procedures in the award of additional work to
Professional General Contractors, Inc., the contractor currently performing structural work for the
Project "Orange Bowl Stadium Structural Repairs, B-30297" (formerly B-3297); pursuant to Contract
dated September 2, 2003, as amended, authorized by Resolutions No. 03-829, 04-0179, and 04-
0428 (the "Contract") is ratified, approved and confirmed.
Section 3. The City Manager is authorized {1} to execute the Third Amendment to the Contract, in
substantially the attached form, to include the Additional Repairs and, at the City Manager's
discretion, the Anticipated Additional Work, and to increase the compensation to the contractor by
$3,717,005 from $2,849,031 to $6,566,036, with funds allocated for said contract increase from
Capital Improvements Project No. 324002.
Section 4. Resolution No. 04-0428 is amended to reflect said increase.
Section 5. This Resolution shall become effective immediately upon its adoption and signature of
the Mayor.{2}
Footnotes:
{1} The herein authorization is further subject to compliance with all requirements that may be
imposed by the City Attorney, including but not limited to those prescribed by applicable City Charter
and Code provisions.
{2} If the Mayor does not sign this Resolution, it shall become effective at the end of ten calendar
days from the date it was passed and adopted. If the Mayor vetoes this Resolution, it shall become
effective immediately upon override of the veto by the City Commission.