Loading...
HomeMy WebLinkAboutfirst amendmentFIRST AMENDMENT TO CONTRACT "ORANGE BOWL STADIUM STRUCTURAL REPAIRS 2003, B-3297" This first Amendment to the Contract for the project entitled "ORANGE BOWL STADIUM STRUCTURAL REPAIRS 2003, B-3297" between the Contractor and the City, awarded to the Contractor by informal solicitation, authorized by the City Commission Resolution No. 03-829, on September 2, 2002, which is deemed as being incorporated by reference as if set for in full herein, is entered into this 29 day of March . 2004, by and between the City of Miami, a municipal corporation of the State of Florida (the "City"), and "Professional General Contractors, Inc.", a Florida corporation ("Contractor") for the purpose of amending that certain Contract dated July 17, 2003 between. the City and the Contractor (the "Contract") as set forth herein. RECITALS: WHEREAS, pursuant Resolution No. 03-829, adopted by the City Commission on July 17, 2003, the City and the Contractor entered into the Contract for all labor, materials and equipment and perform all the work in the form and manner provided by the Contract Documents for the project entitled "ORANGE BOWL STADIUM STRUCTURAL REPAIRS 2003, B-03297"; and WHEREAS, the City shall pay to the Contractor, (as provided in the attachment "A" and other Contract Documents for this project), the sum of ($1,949,031..00), One Million Nine Hundred Forty Nine Thousand Thirty One Dollars; and WHEREAS, while conducting the structural repairs under the contract "Orange Bowl Stadium Structural Repairs 2003, Job No. B-3297", and after the cleaning of the base connection of the upper bowl trusses was completed, it was found that 15 of the 40 supports at the North side of the stadium show a different degree of deterioration and are in need of repair. Also, the four ramps that Lead from the ground toward the concession concourse at `9-6"elevation present severe damage and deterioration and needs to be replaced; and WHEREAS, the Consultants, Bliss & Nyitray, Inc, who are under contract to the City to oversee the structural repairs, are recommending that the deficiencies must be repaired to restore the structural integrity of the stadium in a timely manner prior to the 2004 UM football season. WHEREAS, the additional work, and materials are required to complete the proposed work in an estimated amount of ($500,000) Five Hundred Thousand; and WHEREAS, the City Commission, by Resolution No. 04-0179, adopted on March 25, 2004, has authorized an increase in the amount of the Contract in ($500,000) Five Hundred Thousand; and NOW THEREFORE, in consideration of the foregoing and of the mutual agreements and covenants of the parties as set forth in the Contract, the City and the Contractor agree as follows: Compensation: Article 2 of the Contract is hereby amended to increase the amount of compensation from $1,949,031.00 to $2,449,031.00; the additional amount to be used exclusively for the payment of the additional work due to restore the structural integrity of the stadium in a timely manner prior to the 2004 UM football season. , CITY OF MIAMI Joe Arriola City Manager Attest: Priscilla Thompson City Clerk APPRO AND ate di 1°cX, TO LEGAL FORM TNESS: Date 5 ndro Vilarello y Attorney 1 1? APPROVED AS TO ENGINEERING: ano, P.E., Deputy Director Department CONTRACTOR )ale z ;.1/. s R. Ramos, Pent Prof siona! General Contractors Inc... Attest: Greta ry (AFFIX CORPORATE SEAL) INSURANCE REQUIREMENT APPROVED: 0-4(..-rrti4Date00/1)1r Dania F. Carrillo, Risk Management Administrator 'A 3 0/ fl