Loading...
HomeMy WebLinkAboutexhibit2Act ID Description Early - Early Start Finish 2004 - - - 2005 - 2006. - • . - 2007 S O NO J F M A ►F J J A s O ri D. J F. M A M J .J A S 0. A D J F to .A 1001 Execute Change Order 06DEC04 1010 Place Steel Sheet Pile Order 08DEC04 1020 Fabricate & Deliver Steel Sheet Pile 08DECO4 01 FEB05 1030 Install Steel Sheet Pile & Concrete Cap 02FEB05 31AUGO5 1040 Project Completion 31AUGO5 Start date 24AUG04 Finish date 31AUGO5 Data date 24AUG04 Run date 01 NOVO4 Page number 1A Completion of Phase I ►® Execute Change Order Place Steel Sheet Pile Order PINIUgil Fabricate & Deliver Steel Sheet Pile r t c 9 install Steel Sheet Pile & Concrete Cap ►Ea Project Completion Proposed Draft Schedule Bicentennial Park - Phase 11 Early bar ® Progress bar CZ Critical bar Summary bar l� Start miln=+nnc pint Finish milestone p in+ 0 Primavera Systems, Inc