Breakdown of work effort by Edwards and Kelcey is based on estimated hours worked
by individuals in the following categories to accomplish the tasks included in the Scope
of Work:
Principal in Charge 48 hours @ $160.00 p/h $ 7,680.00
Principal Engineer 98 hours @ $142.00 p/h $13,916.00
Project Manager 238 hours @ $113.00 p/h $26,894.00
Professional Eng, 710 hours @ $ 91.00 p/h $64,610.00
Engineer 373 hours @ $ 76.00 p/h $28,348.00
Engineering Tech. 420 hours @ $ 62.00 p/h $26,040.00
CADD Operator 520 hours @ $ 53.00 p/h $27,560.00
Construction Eng. 592 hours @ $ 76.00 p/h $44,992.00
Sub -Total $240,040.00 V
Expenses $ 4,000.00
Edwards and Kelcey Total (Phases l-VI) $244,040.00
SUB -CONSULTANTS /
• Dalton, Olmsted & Fuglevand, Inc. $29,000.00 !/
(Phase I, II, Ill and IV)
• High Surveying and Mapping (Phase I, II, 111) $ 4,400,00 /
Sub -Consultants Total $33,400.00
TOTAL $277,440.00 7
Additional Services as required and
Authorized by the City
TOTAL AMOUNT THIS SERVICE ORDER:
Edwards
_aoKe/Cey
$ 15,000.00
TOTAL $292,440.00 V