HomeMy WebLinkAboutLetter-DesimoneDESIMONE
MEMORANDUM
Date: January 26, 2005
Re: River Front West
NEW YORK
SLBMITTEDsitiZTHE
PUBLIC RECORD FOR
ITEM ez.a ON Oc
Proposed Tunnel Alignment
Expert Analysis Based Upon City of Miami Requirement as Presented by City
of Miami Assistant City Manager Alicia Cuervo Schreiber
This letter follows up on our meeting yesterday at the Miami City Hall with Alicia
Cuervo Schreiber, Assistant City Manager. In this meeting, we discussed various
issues related to a proposed tunnel that may cross under the Miami River and
through the River Front West parcel. We were informed that the City of Miami has
engaged consultants to study tunnel alignment and construction methods. This
study is to be concluded after a six-month period, which began approximately 2
weeks ago.
Ms. Cuervo Schreiber informed us that an initial feasible location for the tunnel
would be directly under the River Front West parcel running in a north -south
direction. We were informed that one feasible tunnel alignment would be
somewhere within 150 feet of the west property line. We were further informed
that the two-lane tunnel (one each direction) would require a right-of-way [ROW]
of approximately 50 feet.
We are scheduled to deliver permit drawings to the City of Miami Building
Department next week for Phase I of the project. Foundations for the project are
designed in accordance with a geotechnical report prepared by KACO dated
November 30, 2004. The currently designed Phase I tower foundation consists of
24-inch diameter auger -cast piles supporting the 46-story tower and individual
shallow spread footings supporting the low-rise podium. The piles extend to a
depth of -90.0 NGVD. There are three major pile cap groups that support the
shear walls providing lateral stability to the building. A shallow mat foundation is
not possible for the proposed towers due to the soil conditions on the site.
The piles are generally placed 6 feet apart across the footprint of the tower
creating a "forest" of piles 90 feet into the ground. Therefore, it would be
impossible for a tunnel alignment to pass below the building with the present
foundation system. This building design effort to date has required over 1,000 man
hours. Much of this work will be of no use if the tunnel alignment passes below the
building.
DESIMONE CONSULTING ENGINEERS, PLLC 2600 DOUGLAS ROAD SLATE 900 CORAL GABLES, FLORIDA 33134 P. 305.441.0755 F. 305,447.9023
River Front West
Proposed Tunnel Alignment
January 26, 2005
Page 2 of 3
DES
ONE
A possible technical solution being proposed by the City of Miami for the River
Front West parcel is to provide a foundation system that "bridges" over the tunnel
ROW. Essentially, a very deep and very wide beam would span a minimum of 50
feet across the ROW and support the 46-story tower above. We have not had an
opportunity to fully evaluate the technical merits of this proposed solution.
However, if possible, the depth of this beam could be 30 feet deep or more. With
a top of pile cap elevation of +6.5 NGVD, this places the bottom of beam at
approximately elevation -23.5 NGVD.
The proposed tunnel alignment below the proposed towers will need to pass
below elevation -23.5 NGVD. Assuming a minimum clearance of six feet between
the bottom of building foundations and top of tunnel, the top of tunnel elevation
would be approximately -29.5 NGVD. Therefore, the solution proposed by the City
of Miami would require the top of the tunnel to remain very deep throughout the
River Front West parcel to clear the tower foundations. With this in mind, it does not
appear possible to link the tunnel roadway with S.W. 3rd Street as proposed in the
City of Miami Downtown Transportation Master Plan, Section 7.2.15. Assuming a
roadway elevation 20 feet below the tunnel roof at elevation -49.5 NGVD, it would
require approximately one -quarter of a mile to bring the roadway up to ground
level assuming a design standard 5-percent incline. The closest street meeting the
one -quarter mile criteria is north of N.E. 1st Street. See Exhibit A for a representative
section.
There will be other impacts to the proposed towers. The tunnel will require
ventilation shafts and emergency exit shafts. It is probable that these will extend
up from the tunnel within the River Front West parcel disrupting or prohibiting
above ground uses.
Ms. Cuervo Schreiber suggested that we design and submit for permit review an
alternate foundation system that would be coordinated with the proposed tunnel
alignment. She added that the city proposed foundation solution would cost 30 to
50 percent more than what is presently designed. In this manner, a foundation
system that could accommodate a tunnel could be reviewed concurrently with
the present foundation system and thus minimize project delays. We believe,
however, that this alternate foundation system will exceed a 50-percent cost
increase as compared to the current foundation design, further a new foundation
design cannot be developed until the specifics of the tunnel are determined by
the city.
River Front West
Proposed Tunnel Alignment
January 26, 2005
Page 3 of 3
DESIMONE,
Further foundation redesign will likely be required for the 9-story podium. The
shallow foundations will likely be replaced with a smaller version of the tower
"bridge". Other issues to consider are the effects of tunnel construction upon the
building foundations. Deep piles or caissons obtain load capacity through direct
bearing on the tip and through skin friction along the length of the pie. Disruption
of soil near a pile or caisson could cause a loss of capacity.
Currently, we are submitting plans for permit at the end of this month and plan to
commence construction in June 2005. Due to the new city recuirement to
accommodate a possible tunnel alignment, the general information of which was
given to us on January 25, 2005, and the tunnel alignment which will take a
minimum of 6 months to determine although could extend from that date, a
foundation cannot be designed until the completion of the study. Please note
that the exact horizontal and vertical alignment, width, and depth must be
determined before a foundation system can be designed. It would then take
another 2 to 3 months to finalize a design and produce construction documents
for the alternate foundation system. Permit reviews in the City of Miami can then
take another 3 to 6 months. This amounts to a 12 to 15 month project delay.
Based upon the foregoing, it is clear that the proposed River Front West parcel use
is not compatible with the proposed tunnel alignment through the site.
Submitted by,
William R. O'Donnell, P.E.
Managing Partner
WOD/dhm
Attachment: Exhibit A: Representative Section
A
PHASE II
luNNI I I XII IN
NI 1ST I
DESIMON I
MIAMI RIVER
RIVER FRONT WEST
EXHIBIT A
REPRESENTATIVE
SECTION
S-1