HomeMy WebLinkAboutMUSP Analysis•
•
•
Analysis for Major Use Special Permit for the
Hurricane Cove Project
located at approximately
1818 NW North River Drive and 1884 NW North River Drive
CASE NO. 2004-027
Pursuant to Ordinance 11000, as amended, the Zoning Ordinance of the City of Miami,
Florida, the subject proposal for the Hurricane Cove Project has been reviewed to allow a
Major Use Special Permit per Articles 5, 9, 13 and 17, to be of comprised of three
buildings containing 1,073 multifamily residential units with recreational amenities,
2,500 square feet of restaurant, 2,500 square feet of marine retail, a 130-slip commercial
marina, and approximately 1,737 total parking spaces.
This Permit also includes the following requests:
MUSP, as per Article 17 for development of 1,073 residential units;
MUSP, as per Article 5, Section 502, PUD districts; to increase the floor area by
twenty percent, 155,900 square feet;
MUSP, as per Article 9, Section 914, a development bonus to permit a mixed use
of 176,550.39 square feet of floor area will be paid to the Affordable Housing
Trust Fund at the applicable rate at time of permitting;
MUSP, as per Article 17 for parking structures of approximately 1,737 parking
spaces;
SPECIAL EXCEPTION, as per Article 9, Section 917.1.2, to allow restaurant
parking facilities maintained with valet parking up to fifty percent of required off
street parking spaces;
CLASS II, as per Article 9, Section 927, to allow temporary off -site parking
during construction;
CLASS II, as per Article 9, Section 922.1 and 923.2, a request to waive and
modify backup and dimensions of standard from 23 feet to 21 feet;
CLASS I, as per Article 9, Section 925.3.8, to allow
development/construction/rental signage;
CLASS I, as per Article 9, Section 918.2, for parking and staging during
construction;
CLASS I, as per Article 9, Section 918.2, for parking and staging of offsite
parking for construction crews;
CLASS I, as per Article 9, Section 906.6, for active recreational facilities
(including swimming pools);
CLASS I, as per Section 915.2 for FAA clearance letter;
CLASS I, as per Article 9, Section 917.1.2 to allow valet parking for commercial
and residential use;
CLASS I, as per Article 9, Section 920.1, to allow a construction trailer and
watchman's quarters;
Page 1 of 4
•
•
CLASS I. as per Article 9, Section 920.1, to allow a trailer for construction and
other temporary office uses such as leasing and sales;
CLASS 1, as per Article 9, Section 906.9 to allow for a special event namely a
ground breaking ceremony;
Note: Designation as a phased development pursuant to Section 2502 of
Ordinance No. 11000.
REQUEST that the following MUSP conditions be required at the time of Temporary
Certificate of Occupancy or Final Certificate of Occupancy instead of at the issuance of
foundation petniit:
a. the requirement to record in the Public Records a Declaration of Covenants and
Restrictions providing that the ownership, operation and maintenance of all
common areas and facilities will be by the property owner or a mandatory
property owner association; and
b. the requirement to record in the Public Records a unity of title or covenant in lieu
of unity of title.
Pursuant to Articles 5, 9, 13 and 17 of Zoning Ordinance 11000, approval of the
requested Major Use Special Permit shall be considered sufficient for the subordinate
permits requested and referenced above as well as any other special approvals required by
the City which may be required to carry out the requested plans.
In determining the appropriateness of the proposed project, the Planning and
Zoning Department has referred this project to the Large Scale Development
Committee (LSDC) and the Planning & Zoning's Internal Design Review
Committee for additional input and recommendations; the following findings have
been made:
• It is found that the proposed development project will benefit the area by creating new
residential opportunities in the Allapattah NET District, located along NW North
River Drive between NW 17th Avenue and NW 22'd Avenue.
• It is found that the subject property is located in the SD-4 (Waterfront Industrial
District) of the Riversedge, Pirates Cove, Riverfront and Valentine Plats within the
Curtis Park region of the City. The applicant has submitted an application to change
the current zoning to C-1 (Restricted Commercial District).
• It is found that the project has convenient access to the Metrorail system, located
approximately 3/4-mile (Civic Center Station) east of the subject property, for efficient
use of existing mass transit systems.
Page 2 of 4
•
•
• It is found that the Traffic Impact Analysis still has yet to be approved in final form
by the City Transportation Department or the City's consultant, URS Corp, as stated
in the URS correspondence dated February 23, 2004.
• It is found that the proposed project is located within an Archeological Conservation
area and is therefore subject to a Certificate of Appropriateness for any ground
disturbing activity within the designated area.
• It is found that the project was reviewed by the Large Scale Development Committee
on July 23, 2003 to address the expressed technical concerns raised at said Large
Scale Development Committee meeting.
• It is found that the proposed project was reviewed for design appropriateness by the
Urban Development Review Board on December 17, 2003, which recommended
approval with the following condition; Single pale tint color for the glass. The
Planning and Zoning Department's review resulted in design modifications that were
then recommended for approval to the Planning and Zoning Director.
• It is found that with respect to all additional criteria as specified in Section 1305 of
Zoning Ordinance 11000, the proposal has been reviewed and found to be adequate.
Based on these findings, the Planning and Zoning Department is recommending
approval of the requested Development Project with the following conditions:
1 Meet all applicable building codes, land development regulations, ordinances and
other laws and pay all applicable fees due prior to the issuance of a building
permit.
2. Allow the Miami Police Department to conduct a security survey, at the option of
the Department, and to make recommendations concerning security measures and
systems; further submit a report to the Department of Planning and Zoning, prior
to commencement of construction, demonstrating how the Police Department
recommendations, if any, have been incorporated into the PROJECT security and
construction plans, or demonstrate to the Director of the Department of Planning
and Zoning why such recommendations are impractical.
3. Obtain approval from, or provide a letter from the Department of Fire -Rescue
indicating APPLICANT'S coordination with members of the Fire Plan Review
Section at the Department of Fire -Rescue in the review of the scope of the
PROJECT, owner responsibility, building development process and review
procedures, as well as specific requirements for fire protection and life safety
systems, exiting, vehicular access and water supply.
4. Obtain approval from, or provide a letter of assurance from the Department of
Solid Waste that the PROJECT has addressed all concerns of the said Department
prior to the obtainment of a shell permit.
Page 3 of 4
•
•
•
5. Comply with the Minority Participation and Employment Plan (including a
Contractor/Subcontractor Participation Plan) submitted to the City as part of the
Application for Development Approval, with the understanding that the
APPLICANT must use its best efforts to follow the provisions of the City's
Minority/Women Business Affairs and Procurement Program as a guide.
6. Prior to the issuance of a shell permit, provide the City with a recorded copy of
the MUSP permit resolution and development order, and further, an executed,
recordable unity of title or covenant in lieu of unity of title agreement for the
subject property; said agreement shall be subject to the review and approval of the
City Attorney's Office.
7. Provide the Department of Planning and Zoning with a temporary construction
plan that includes the following: a temporary construction parking plan, with an
enforcement policy; a construction noise management plan with an enforcement
policy; and a maintenance plan for the temporary construction site; said plan shall
be subject to the review and approval by the Department of Planning and Zoning
prior to the issuance of any building permits and shall be enforced during
construction activity. All construction activity shall remain in full compliance
with the provisions of the submitted construction plan; failure to comply may lead
to a suspension or revocation of this Major Use Special Permit.
8. In so far as this Major Use Special Permit includes the subordinate approval of a
series of Class I Special Peiinits for which specific details have not yet been de-
veloped or provided, the applicant shall provide the Department of Planning and
Zoning with all subordinate Class I Special Permit plans and detailed require-
ments for final review and approval of each one prior to the issuance of any of the
subordinate approvals required in order to carry out any of the requested activities
and/or improvements listed in this development order or captioned in the plans
approved by it.
9. If the project is to be developed in phases, the Applicant shall submit an interim
plan, including a landscape plan, which addresses design details for the land oc-
cupying future phases of this Project in the event that the future phases are not de-
veloped, said plan shall include a proposed timetable and shall be subject to re-
view and approval by the Director of Planning and Zoning.
10. Prior to application for Public Hearing of the City Commission, the applicant shall
continue to work with the City's Transportation Department regarding the resolv-
ing of all the traffic issues related to this project.
11. Pursuant to the UDRB's and Planning and Zoning Department's review, the ap-
plicant shall meet the following condition: Single pale tint color for the glass.
12. The Applicant shall follow the Archeological Management Plan approved on Oc-
tober 21, 2003 (Resolution # 2003-63) by the Historic and Environmental Preser-
vation Board during the development process.
Page 4 of 4