HomeMy WebLinkAboutConstruction Engineering & InspectionMARLI
ENGINEERING
City of Miami
Construction Engineering and Inspection
NW 14 Street Improvement Project
Purpose:
This scope of work describes the services which are required for construction engineering and
inspection, materials sampling and testing, and contract administration for the construction
project listed below.
Exhibit Al: Scope of Service
Exhibit B 1: Length of Service
Exhibit Cl : Fee Estimate
Exhibit Al: Scope of Service
Scope:
The Consultant will act as support service to the City of Miami Project Engineer and staff.
The Consultant will utilize effective control procedures which will assure that the
construction of the project is performed in conformity with the plans, specifications, and
contract provisions.
The project for which the services are required is:
Project limits: NW 14 St. from NW 22 Ave. to NW 34 Ave.
County: Miami Dade
This project involves the Milling and Resurfacing of NW 14 St. with the addition of sidewalk,
ped-ramps and turf block as well as miscellaneous upgrades at NW 34 Ave underneath SR
836 which include drainage improvements as well as improvements to sidewalk as specified
in plan.
Items to be furnished by the City of Miami:
The City on an as needed basis will furnish the following items.
1-set of Construction Plans
1-set of Specifications and Special Provisions
1-copy of executed contract
The Consultant shall submit a request in writing for these above mentioned items from the
City's Project Engineer.
T33nsfaortation I -? arming Traffic Eiacyinccring Pic r)cvclolpna(:r)t F-liclItwaty C)os1gra
Mrr nicih/\VIatiQII Ir aan5it (7x3rIsti tictiMan: concli t 13ri<Igc in 3)(( tIOI!
2191 NW 97 Avenue Miami, Florida 33172-2313 Tel. (305) 477-7575 Fax (305) 477-7590
Field Office:
Engineers field office:
Marlin Engineering, Inc.
2191 NW 97 Ave
Miami Fl, 33172
Requirements:
It shall be the responsibility of the Consultant to provide required services in order for the City's
Project Engineer to administer the Contract to assure that the project is constructed in reasonable
conformity with the plans, and specifications.
The consultant shall observe the Contractor during various operations to ensure the materials and
methods used by the contractor conform to the specifications of the contract.
The Consultant shall notify the City of any omissions, substitutions, defects, and deficiencies
noted in the work of the Contractor and the corrective action taken. Work provided by the
Consultant shall not relieve the contractor of responsibility for the satisfactory performance of
the construction.
On -site Inspections:
The Consultant and City inspection personnel shall monitor the Contractors onsite construction
operations and inspect materials entering into the work as required to assure that the projects are
completed in reasonable conformity with the plans, and specifications. The Consultant shall
keep detailed accurate records of the Contractors daily operations and of significant events that
affect the work.
Testing:
The Consultant and City's Project Engineer shall perform sampling and testing of all component
materials and completed work items to the extent that will assure that the materials and
workmanship incorporated in each task are in reasonable conformity with the plans and
specifications.
Documentation reports on sampling and testing shall be submitted to responsible parties the
same week that the construction work is done or as otherwise directed by the City's Project
Engineer.
Personnel:
The Consultant shall provided qualified personnel necessary to efficiently and effectively carry
out its responsibilities under this Agreement. As per the approved estimate the Consultant shall
provide:
Project Manager 1
Construction Manager Sup. 1
Const. Inspector 1
Clerical 1
Exhibit B1: Length of Services:
Length of Services:
The consultant services for the contract will begin upon written notification to proceed by the
City of Miami.
For estimating purposes the consultant will be allowed an accumulation of twenty-one (21)
working days to assist the City Project Engineer prior to the Contractors first contract day and
thirty (30) calendar days subsequent final acceptance of the contract to be completed.
Construction Contract Estimate
Letting Date Start Date Duration
Mo/Day/Yr Mo/Day/Yr 6 month
Exhibit Cl Fee Estimate:
For Fee estimate for the services as outlined in this scope please see attached Staff Hour
Estimate.