HomeMy WebLinkAboutexhibit 3-project fact sheetProject Name:
City of Miami
Department of Capital Improvements
PROJECT FACT SHEET
Data: February 5, 2004
Emergency:
BICENTENNIAL PARK SHORELINE STABILIZATION- PHASE I
Project Location: 1075 Biscayne Blvd. Miami, Florida Commissioner District: 2
Protect Number: 8-3293 initiating Dept.: Planning Department
Project Manager/Ext. No.. Sandra Vela, Ext-1243 Project Budget: 57,530,475.36
Homeland Defense 0 Account Number: 331415 Amount: $5,000,000.00
I45PedestrlanOverpass
1.95 P.O. - interest
Other: FIND
uJ
y
Account Number:
Account Number:
Account Number:
Amount: $168,400.00
Amount:
Amount:
$20,438.00
$700, 000.00
The project consists of the furnishing of all labor, materials and equipment for the shoreline stabilization
of approximately 2,508 L.F. of failing seawall at Bicentennial Park. The project includes site preparation,
demolition, backfill, riprap placement, filler aggregate limerock fill, steel sheet piling, relocation of trees,
manatee protection and coral transplantation.
NE Firm: Edwards and Kelcey
Addtese;: • 7300 North Kendall Drive Suite 400
pity, stets, Zip: Miami, Florida 33158
•Cvnt.ot Person: Egon Y. Tokay
Tslephon .MaU:
Type of Work: New seawall/shoreline stabilization
Comments: •
. EK Telephone 305-279-2298
• EK Fax 305279-6812
NE firm Fees:
Additions! Design Services:
In-HOUIs Design Cost
MitiodllaNecus tllervloas:
CIP Design'Adminletratian:
nsiain Plisse Total:
PROJECT COSTS
(A). - Actual
(a) East
$421 R407.00 (A)
NIA (A)
N/A (A)
571,826.26 (A)
$40,048.00 (A)
$133,11e0:*6
Contractor Shoreline Foundation, Ina
Address: 2781 SW 58th Avenue
City, State, Zip: Pembroke Park, Florida 33023
Contact Person: Mr. James Royo
Telephone/E-mail: 954.985-0480
Class:
(J ■ Joint P = Prima S u Sub)
Minority Status: NIA
(B ■ Black F • !: emala M ■ Hispania N ■ None)
Established: 7 years
License Number CGC 058114
Sub -Contractors:
Homestead Concrete
Allied Trucking
Sunshine Guardrails
Vila & Sons
Construction Contract Amount:
CIP Construction Adminlstratlon:
Misc. Construction Costs:
Construction Phase Total
Tots' Project Cost
Oapiss es CIP Senior Aaocwrtsnt, CIP A nlnistrstor, • FNs, . InlUsting Dapar4nrrt
$6,957,195.10 (pia)
$40,000,00 (E)
$100,000.00 (E)
$7,097,195.10
$7630
0.35