HomeMy WebLinkAboutestimated construction costS.W. 16 TERRACE ROAD RECONSTRUCTION PROJECT B-4698
ESTIMATED CONSTRUCTION COST
ITEM DESCRIPTION CITY UNIT VALUE
TREE REMOVAL 10 $100.00
NEW TREES 20 $400.00
LIMEROCK BASE COURSE, 8" THICK 7,000 $15.00
ASPHALTIC CONCRETE PAVEMENT SURFACE COURSE (1 1f2") 7,000 $10.00
DRAINAGE STRUCTURES 20 $2,000.00
DRAIN PIPES SYSTEM 1,500 $90.00
EXISTING UTILITY STRUCTURES TO BE ADJUSTED 10 $1,000.00
SIDEWALK CONCRETE (4" THICK) 6,000 $8.00
SIDEWALK CONCRETE (6" THICK) 7,000 $10.00
STANDARD OR DEPRESED CONCRETE CURB & GUTTER 4,068 $17.00
SODDING 8,000 $2.00
PREPARED BY MARIA E. LOPEZ, P.E.
UNIT TOTAL VALUE
EA.
EA.
PER SY
PER SY
EA.
PER LF.
EA.
PER SF.
PER SF.
PER LF.
PER SF.
SUBTOTAL:
$572,456.00
MOBILIZATION (10%)
SPECIAL PROVIS.(10%)
TOTAL:
ssree.76