This AGREEMENT, made and entered into this_ day of _ A.D., 2004, by
and between the City of Miami, Florida, a municipal corporation of the State of Florida, party
of the first part, (hereinafter sometimes called the "City"), and MQRLIC ENGINEERING
CORP.
Party of the second part (hereinafter sometimes called the "Contractor")
WITNESSETH: That the parties hereto, for the considerations hereinafter set
forth, mutually agree as follows:
ARTICLE 1. SCOPE OF THE WORK: The Contractor shall furnish all labor,
materials and equipment and perform all the work in the manner and form provided by
the Contract Documents, for the project entitled:
"ALLAPATTAI3 pRODUCE NARSE3 IMPRO -4674" (2nd BIDDING)
ARTICLE 2. THE CONTRACT SUM: The City shall pay to the Contractor, for the
faithful performance of the Contract, in lawful money of the United States, and subject
to additions and deductions and based on unit prices (where applicable), all as provided
in the Proposal and other Contract Documents, the sum of (1407,860.00), Four Hundred
and Seven Thousand and Ebt Hundred Sixty Dollars and ELCents
ARTICLE 3. PARTIAL. AND FINAL PAYMENTS: In accordance with the
provisions fully set forth in the "General Conditions" of the "Specifications," and
subject to additions and deductions as provided, the City shall pay the Contractor as
follows:
(a) On or before the 10th day of each calendar month, the City shall make
partial payments to the Contractor on the basis of a duly certified and
approved estimate of work, performed during the preceding calendar month
by the Contractor, less ten (10%) percent of the amount of such estimate,
which is to be retained by the City until all work has been performed strictly
in accordance with this Agreement and until such work has been accepted
by the City.
(b) Upon submission by the Contractor of evidence satisfactory to the City that
all payrolls, material bills and other costs incurred by the Contractor in
connection with the construction of the work have been paid in full, and
also, after all guarantees that may be required in the Specifications or by the
Contractor have been furnished and are found acceptable by the City, final
payment on account of this Agreement shall be made within sixty (60) days
after completion by the Contractor of all work covered by this Agreement
and acceptance of such work by the City.