HomeMy WebLinkAboutAnalysis•
Analysis for Major Use Special Permit for the
Villaggio Project
located at approximately 2745, 2749, 2755, 2765, 2803, 2823, and 2833
Coconut Avenue and 2740-2744, and 2754 Southwest 28th Avenue
CASE NO. 2003-0049
Pursuant to Ordinance 11000, as amended, the Zoning Ordinance of the City of Miami,
Florida, the subject proposal for the Villaggio Project has been reviewed to allow a Major
Use Special Permit per Article 17, for a residential building with up to 86 residential
units, recreational amenities, and approximately 118 parking spaces
This Permit also includes the following requests:
MUSP, as per Article 9, Section 914, a development bonus to permit a residential
use of 15,537 square feet of floor area $6.67 = $103,631, by contribution to the
Affordable Housing Trust Fund.
MUSP, as per Article 5, Section 502, PUD districts; to increase the floor area by
twenty percent.
CLASS II SPECIAL PERMIT as per Article 9, Section 908.2, for access from a
public street roadway width greater then 25 feet.
CLASS II SPECIAL PERMIT as per Article 15, Section 1512, to request a waiver
of City of Miami Parking Guides and Standards for reduction of required backup
space for parking.
CLASS II SPECIAL PERMIT as per Article 15, Section 1512, to request a waiver
of City of Miami Parking Guides and Standards for reduction of required width
for a two way drive.
CLASS II SPECIAL PERMIT as per Article 9, Section 922.1 and 923.2, a request
to waive and modify backup and dimensions of loading,
CLASS II SPECIAL PERMIT for approval of signage.
CLASS II SPECIAL PERMIT as per Article 6, Section 603, for new construction.
CLASS I SPECIAL PERMIT as per Article Section 925.3.8, to allow
development/construction/rental signage.
CLASS I SPECIAL PERMIT as per Article 9, Section 918.2, for parking and
staging of construction during construction.
CLASS I SPECIAL PERMIT as per Article 9, Section 920.1, to allow a trailer for
construction and other temporary office uses such as leasing and sales.
CLASS I SPECIAL PERMIT as per Article 9, Section 906.6, for pool/outdoor
recreation area.
•
REQUEST that the following MUSP conditions be required at the time of shell
permit instead of at issuance of foundation permit:
a. The requirement to record in the Public Records a Declaration of
Covenants and Restrictions providing that the ownership, operation
and maintenance of all common areas and facilities will be by the
property owner or a mandatory property owner association .
Pursuant to Articles 5, 9, 13, and 17 of Zoning Ordinance 11000, approval of the
requested Major Use Special Permit shall be considered sufficient for the subordinate
permits requested and referenced above as well as any other special approvals required by
the City which may be required to carry out the requested plans.
In determining the appropriateness of the proposed project, the Planning and
Zoning Department has referred this project to the Large Scale Development
Committee (LSDC) and the Urban Development Review Board (UDRB) for
additional input and recommendations; the following findings have been made:
• It is found that the proposed development project will benefit the area by creating new
housing opportunities in the North/East Coconut Grove Area.
• It is found that the subject property is located southeast from Highway US-1 abutting
both Coconut Avenue and Southwest 28th Terrace in the Palm Terrace Subdivision.
• It is found that the project has convenient access to the Metro Rail system for efficient
use of existing mass transit systems.
• It is found that the project was reviewed by the Large Scale Development Committee
and has been modified to address the expressed technical concerns raised at said
Large Scale Development Committee meeting;
• It is found that the proposed project was reviewed for design appropriateness by the
Urban Development Review Board, which recommended denial due to the following
reasons; ingress and egress should be reduce to allow for one access on Coconut
Avenue, landscaping needs to be maximized, and the lack of connectivity between
buildings with regards to their designs. Notwithstanding the findings from the Urban
Development Review Board, the Planning and Zoning Department recommends
approval with the condition that the applicant increases the amount of landscaping
being proposed, therefore, the staff review resulted in design modifications which
were then recommended for approval to the Planning and Zoning Director.
• It is found that with respect to all additional criteria as specified in Section 1305 of
Zoning Ordinance 11000, the proposal has been reviewed and found to be adequate.
•
•
•
Based on these findings, the Planning and Zoning Department is recommending
approval of the requested Development Project with the following conditions:
1. Meet all applicable building codes, land development regulations, ordinances and
other laws and pay all applicable fees due prior to the issuance of a building
permit.
2. Allow the Miami Police Department to conduct a security survey, at the option of
the Department, and to make recommendations concerning security measures and
systems; further submit a report to the Dept t lent of Planning and Zoning, prior
to commencement of construction, demonstrating how the Police Department
recommendations, if any, have been incorporated into the PROJECT security and
construction plans, or demonstrate to the Director of the Department of Planning
and Zoning why such recommendations are impractical.
3. Obtain approval from, or provide a letter from the Department of Fire -Rescue
indicating APPLICANT'S coordination with members of the Fire Plan Review
Section at the Department of Fire -Rescue in the review of the scope of the
PROJECT, owner responsibility, building development process and review
procedures, as well as specific requirements for fire protection and life safety
systems, exiting, vehicular access and water supply.
4. Obtain approval from, or provide a letter of assurance from the Department of
Solid Waste that the PROJECT has addressed all concerns of the said Department
prior to the obtainment of a shell permit.
5. Comply with the Minority Participation and Employment Plan (including a
Contractor/Subcontractor Participation Plan) submitted to the City as part of the
Application for Development Approval, with the understanding that the
APPLICANT must use its best efforts to follow the provisions of the City's
Minority/Women Business Affairs and Procurement Program as a guide.
6. Prior to the issuance of a shell permit, provide the City with an executed,
recordable unity of title agreement for the subject property; said agreement shall
be subject to the review and approval of the City Attorney's Office.
7. Provide the Department of Planning and Zoning with a temporary construction
plan that includes the following: a temporary construction parking plan, with an
enforcement policy; a construction noise management plan with an enforcement
policy; and a maintenance plan for the temporary construction site; said plan shall
be subject to the review and approval by the Department of Planning and Zoning
prior to the issuance of any building permits and shall be enforced during
construction activity. All construction activity shall remain in full compliance
with the provisions of the submitted construction plan; failure to comply may lead
to a suspension or revocation of this Major Use Special Permit.
•
o
•
8. Pursuant to the UDRB and Planning and Zoning Department review, the applicant
shall modify the proposed landscape plans to indicate the increase in the amount
of landscaping as requested.