INTER -OFFICE MEMORANDUM
Joe Arriola
Chief Administrator/City Manager
August 5, 2003
Watson Island Boat Ramp
Parking Lot Lighting
L�..r Project
yam,
Keith A. ') Department of E4tevelopment
The Watson Island Boat Ramp Parking Lot project is nearing completion. Gancedo Technologies, Inc., the
electrical contractor, has submitted notification of change order letters for unforeseen additional work. The
requests have been verified by City staff and are as follows:
1. Transportation costs of moving concrete light poles from storage site at a cost of $850.00.
2. FPL Primary Feeder — installation of primary conduits from FPL manhole to main entrance
service at a cost of $2,100.00.
3. Replacement of one damaged light pole at a cost of $1,600.00 which was damaged by an
unknown trespasser.
4. Cost to unload new light pole with crane and to auger new hole at a cost of $700.00.
Gancedo Technologies, Inc. is under contract in the amount of $68,972.00. This original contract did not
include a customary ten percent contingency line item for unforeseeable conditions such as the ones
previously described.
At this time, we are requesting your approval of an emergency to increase the existing Purchase Order
number 231785 in the amount not to exceed $10,000.00 (ten thousand dollars) as a cash allowance item for
this contract. Funds are available from Project No. 333126 669301.6.860 for the $10,000.00 cash allowance
item. It should be noted that this project was funded 50% by the Florida Inland Navigation District which
the City has received its reimbursement. The approval will be followed by a ratification item for the City
Commission meeting on October 9, 2003.
If you have any questions, please call Enrique Nunez, Project Manager at extension 1419.
LH/KAC/LB/EN/cm
Soh.
Approved by
Capital l m o vements
r e C. Cana, Dir
epartm nt of C
i
Joe to a, Chief Administrator/City Manager