HomeMy WebLinkAboutEmergency Waiver MemoCITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
TO: Carlos A. Migoya DATE: March 31, 2010 FILE:
City Manager
SUBJECT: Procurement Waivers- Emergency
Findings & Separate Bid Waiver as
being in the best interests of the
City
GLENN MARCOS, CPO, CPLD, etc., et. al.
Director of Purchasing Waiver of Competitive Bidding
Procedures:
Approval of Change Orders to
Pirtle Construction Co., Inc.
FROM: Ola O. Aluko REFERENCES: Police College and Law
Enforcement High School Project, B-72910
Director
Department of Capital Improvements ENCLOSURES:
RECOMMENDATION
In the interest of maintaining continuity of work, it was determined that utilizing another Contractor to
install Furniture Fixtures and Equipment ("FF&E") and its electrical infrastructure for the Police
College and Law Enforcement High School Project, B-72910, would substantially delay the project
and ultimately cost the City undue additional expenditures, and potentially delay the opening of the
school. One of the conditions placed on the contractor, Pirtle Construction Co., Inc., was that they
would obtain competitive pricing on the FF&E. In an effort to avoid disruption of the essential
governmental services provided by the facility, it was determined that it was most practicable and
advantageous to the City for Pirtle Construction Co., Inc., to perform the additional FF&E work, in the
amount of $1,255,038.
We recommend that the City Commission concur to waive the formal requirements set forth in the
Code of the City of Miami, as amended, in Section 18-85, and under Florida Statutes Section
255.0525 and 255.20, pursuant to City Code Section 18-90 and ratify, approve and confirm these
emergency findings for the previously delivered and installed Furniture Fixtures and Equipment
("FF&E") and its electrical infrastructure for the Police College and Law Enforcement High School
Project, B-72910 in the amount of $1,255,038. We recommend the City Commission to waive the
formal requirements set forth in the Procurement Code of the City of Miami, as amended, per
Section 18-90, as an emergency procurement, and under Florida Statutes Section 255.0525 and
255.20, and affirm and adopt these findings by a 4/5tt' affirmative vote.
Furthermore, in the interest of maintaining continuity of work and to avoid undue additional
expenditures, it has similarly been determined that it be most practicable and advantageous to the
City for Pirtle Construction Company, Inc., to perform forthcoming City requested additional work,
including an IT switchgear upgrade, technology boards, memorial signs, and tactical training mats, in
an amount not to exceed $104,383.
We recommend that the City Commission concur to waive the formal requirements set forth in the
Procurement Code of the City of Miami, as amended, in Section 18-85, and under Florida Statutes
Section 255.0525 and 255.20, and affirm and adopt these findings, by a 4!5"' affirmative vote.
BACKGROUND
The City of Miami ("City"), the Miami -Dade County Board of Commissioners, the Miami -Dade County
School Board ("School Board") and numerous other municipalities within Miami -Dade County
("County") have previously entered into an Interlocal Agreement for Public School Facility Planning
in the County. On June 9, 2005, the City Commission adopted Resolution No. 05-0373, to reaffirm
its commitments to the voters and citizens of the City regarding smart growth principles, projects and
initiatives for master planning, capital improvement projects and working with the County, the School
Board and other municipalities to deliver regional solutions to basic service requirements such as
utilities, transit, air and sea ports, schools and other needs. On September 7, 2005, the School
Board authorized joining forces with the City to create first-rate educational programs and services
throughout the City through the formation of an Education Compact to focus on improving academic
programs, meeting capital and infrastructure needs and providing community involvement.
The City's Capital Improvement Program and Multi -Year Plan includes the design and construction
of a Police College, and the School Board's Capital Improvement Program and Multi -Year Plan
includes the construction and operation of a Law Enforcement Officers Memorial High School for law
studies, homeland security, and forensic sciences.
The School Board, the City Manager, the Department of Capital Improvements and the Miami Police
Department began negotiating agreements regarding the design, construction, funding, operation,
maintenance, and co -location of the Police College and Law Enforcement Officers Memorial High
School as a single capital improvement project (the "Project") at the City owned properties located at
405 Northwest 3`d Avenue, the Miami Police Headquarters, and at 401 Northwest Td Avenue, an
adjacent lot.
The School Board committed to providing $11.89 million for the Facility, and the City committed to
providing $23.51 million, which led to execution of a Guaranteed Maximum Price Agreement in the
total amount of $35,400,000 with Pirtle Construction Co., Inc., as one of the qualified responders to
the School Board's RFQ, issued October 17, 2005.
The City further entered into an Assignment, Assumption and Amendment Agreement, dated April
14, 2008 by and between the School Board and the City and acknowledged and agreed to by Pirtle,
and an Interlocal Agreement, dated as of April 11, 2008 with the School Board for the design,
construction, funding and contingencies of a co -located Police College and Law Enforcement
Officers Memorial High School in an amount not to exceed $37,470,000, and authorizing the City
Manager to execute any additional agreements as deemed necessary to establish the ongoing
responsibilities of both parties pursuant to the Interlocal Agreement to accomplish the construction,
funding, and contingencies of the Facility.
At the time of execution of the Interlocal the City did not have sufficient funds to implement FF&E
which had been originally contemplated.
The City has identified the funds and thus wishes to make payment for the $1,255,038 in FF&E
installed, including the installation of a furniture package, in the amount of $1,066,264, and its
electrical infrastructure, in the amount of $188,774. An emergency procurement and waiver of
competitive sealed bidding requirements is recommended for these items as an emergency
procurement per § 18-90.
The City also wishes to authorize Pirtle Construction Company, Inc., to perform forthcoming City
requested additional work, including an IT switchgear upgrade, technology boards, memorial signs,
and tactical training mats, in the total amount of $104,383, for the non-FF&E items. A waiver of
competitive sealed bidding requirements is recommended for these items per §18-85 as being not
practicable or advantageous to the City .
The City thus requests authorization for the procurement and payment, for both the emergency and
non-emergency additional work, to Pirtle Construction Company, Inc., in the total not to exceed
amount of $1,420,950.
Your signature below will signify your concurrence with the above recommendation and your
adoption of and concurrence with these of these findings as your own justification that an emergency
exists as the FF & E items for the waiver of competitive bidding procedures and authorize
compensation to the Pirtle Construction Co., Inc., for the additional work as to the other prospective
work and materials detailed as competitive bidding is not practicable nor advantageous to the City in
this particular instance.. Additionally your signature below indicates you have made all findings
required by the Procurement Code and the signature of the CFO indicates his professional
certification that sufficient funds exist.
Approved: 7
rl i , City Manager
Certification f Fu valla if'
Lar n , en irector of Management and Budget
C: Glenn Marcos, Chief Procurement Officer
Gary Fabrikant, CIP Assistant Director
Nelson Cuadras, Project Manager