This Amendment No. 1 to the Professional Services Agreement dated July 9, 2009, (the
"Agreement"), between the City of Miami, a municipal corporation of the State of Florida
("City"), and Leo A. Daly Company, ("Consultant") a Nebraska corporation, for the provision of
Architectural and Engineering Services for the Stadium Site Parking Project ("Project") is entered
into this day of , 2009.
RECITALS
WHEREAS, on July 9, 2009, pursuant to RFQ No. 08-09-017 and Resolution No. 09-
0200, adopted by the City Commission April 23, 2009, the City and the Consultant entered into
the Agreement, in the amount of $4,899,642.60, for the Scope of Work described therein; and
WHEREAS, on April 15, 2009, the City, Miami -Dade County ("County") and Marlins
Stadium Developer, LLC ("Stadium Developer") entered into a Construction Administration
Agreement ("CAA") which provides, among other things, for the construction of the Baseball
Stadium and the Project; and
WHEREAS, the CAA evidences the parties' intent to seek Leadership in Energy and
Environmental Design (LEED) Silver Certification for the Baseball Stadium ("LEED
Certification"), and provides that the County and the City are each responsible for the payment of
50% of the incremental cost to achieve LEED Certification, beyond the $1,000,000 to be
provided by the Stadium Developer on behalf of Major League Baseball; and
WHEREAS, the CAA further provides that the City may deduct from its obligation to
contribute 50% of the incremental cost to achieve LEED Certification, any amounts paid by the
City above those required to construct the Project that will assist in obtaining LEED Certification
for the Stadium; and
WHEREAS, the Stadium Developer has requested the City, and the City wishes, to assist
the Stadium Developer in achieving LEED Certification; and
WHEREAS, the City wishes to increase the Scope of Services of the Agreement in order
to include design integration and coordination of LEED credits required in the parking garages
and to have the parking structures support a Photovoltaic Generation System, required in order
for the Stadium to achieve LEED Certification ("Additional Services"); and
WHEREAS, this Amendment No. 1 will increase the total compensation payable under
the Agreement by $435,000, from $4,899,642.60 to an amount not to exceed $5,334,642.60, to
cover the cost of the Additional Services; and
ors0ocument 199780 (2).doc
NOW THEREFORE, for the considerations of the foregoing, the parties hereby amend the
Agreement as follows:
Additional Services: The Additional Services are described in Exhibit "A" to this
Amendment. The PSA is hereby amended to include the Additional Services.
2. Compensation: The amount of compensation payable by the City to Consultant shall be
increased by $435,000, for the provision of the Additional Services, and shall be paid as
provided in the PSA.
All other terms and conditions of the Agreement are in operative force and effect and remain
unchanged.
THE CITY OF MIAMI, FLORIDA
ATTEST:
By:
Priscilla A. Thompson, City Clerk
APPROVED AS TO LEGAL FORM
AND CORRECTNESS:
L-02
Julie O. Bru, City Attorney
ATTEST:
Corporate Secretary
(Affix Corporate Seal)
CITY OF MIAMI, FLORIDA, a
municipal Corporation of the State of
Florida
By:
Pedro G. Hernandez, P.E.,
City Manager
APPROVED AS TO INSURANCE
REQUIREMENTS:
By:
LeeAnn Brehm,
Risk Management Director
CONSULTANT
LEO A. DALY COMPANY
By:
Agustin J. Barrera, Managing Principal
ors:Document 199780 (2).doc 2