HomeMy WebLinkAboutExhibit 2CITY OF MIAMI
DEPARTMENT OF CAPITAL IMPROVEMENTS
Miamarina Pier No.5 Repairs, B-30325
CONTRACTOR: SHORELINE FOUNDATION, INC.
Exhibit A
Descri"pt�on , ", _
,Justification f
Cost
Finger Pier Timber Pile Replacement
Unforseen Conditions
$4,500.00
Builder's Risk Insurance Policy Renewal
Owner requested change
$32,839.40
Misc. Electrical Room louvered doors with panic device,
emergency light, ice maker panel feeder and breaker,
timber fender, cut of reinforced concrete footing at
electrical room
Owner requested change
$15,770.70
Grand Total
553.110.10
* Due to the unforeseen conditions and owner requested changes, the project completion date was
extended causing the expiration of the Builder's Risk, therefore renewal is necessary.