HomeMy WebLinkAboutExhibit 1AMENDMENT NO.1 TO CONSTRUCTION CONTRACT
REPLACEMENT OF FIRE STATION NO. 11
B-60452
This Amendment No. 1 to the Contract dated October 24, 2008 (the "Contract")
between the City of Miami, a municipal corporation of the State of Florida ("CITY"), and
NAC Construction, Inc. ("CONTRACTOR") for the project entitled "Replacement of Fire
Station No. 11, B-60452," ("PROJECT") is entered into this day of
, 2009.
RECITALS
WHEREAS, the Contract was entered into pursuant to the approval of the City
Commission by Resolution No. 08-0501 in the amount of $3,024,000, for the Scope of
Work, included in the original Contract Documents for the PROJECT,
WHEREAS, a ten percent owner's contingency was also awarded, for a total
award value of $302,400; and
WHEREAS, this Amendment No. 1 is now necessary, approved pursuant to R-
, amending the award value by $448,000, which consist of a change order in the
amount of 286,292 and owner requested changes in the amount of $161,708, which
includes $115,233 for an alerting system, $31,416 for new uninterrupted power source
and two circuit panels, and unforeseen conditions such as $15,059 for an FPL pole
relocation; and,
NOW THEREFORE, for the considerations hereinafter set forth:
The Agreement dated October 24, 2008, is hereby amended as follows:
ADDITIONAL WORK is hereby revised to include all labor, materials and
equipment required to perform the additional work, consisting of change order
items, including an alerting system, new uninterrupted power source and two
circuit panels, relocation of an FPL pole, development of a site to house
temporary trailers for the firemen to utilize during construction, and temporary
signalization for the temporary trailer site.
2. AWARD VALUE is hereby increased by an amount not to exceed $448,000,
thereby increasing the total award value to Three Million, Seven Hundred
Seventy -Seven Thousand, Four Hundred Dollars and no cents ($3,774,400).
All other terms and conditions of the Contract are in effect and remain unchanged.
ATTEST
By:
Priscilla A. Thompson, City Clerk
CITY OF MIAMI,
By:
Pedro G. Hernandez, City Manager
APPROVED AS TO LEGAL FORM AND APPROVED AS TO INSURANCE
CORRECTNESS REQUIREMENTS:
By:
Julie 0. Bru, City Attorney
ATTEST:
By:
Corporate Secretary
(Affix Corporate Seal)
By:
LeeAnn Brehm,
Risk Management Director
CONTRACTOR
NAC Construction, Inc.
By:
Nestor Castellon, President
2