HomeMy WebLinkAboutExhibit BEXHIBIT B
FLORIDA INLAND NAVIGATION DISTRICT
WATERWAYS ASSISTANCE PROGRAM
PROJECT COST ESTIMATE
(See Rule Section 6613-2.005 & 2.008 for elisibility and funding ratios)
PROJECT TITLE: Dinner Key Mooring Field Project Phase II
APPLICANT: City of Miami Department of Public Facilities
Project Elements
Quantity Estimated
Applicant's Cost
FIND Cost
(Please list the MAJOR project elements and
Cost
provide a general cost break out for each one.
(Number and/or Footage)
For Phase i Projects, please list the major
elements and products expected)
Project Management
$50,000
$37,500
$37,500
Removal of debris (engines, tires, etc.) and
$150,000
$75,000
$75,000
vessels from bay bottom
Hardware and installation of 225 moorings
$427,500
$213,750
$213,750
@ $1,900 each
Lighted regulatory field buoys 80 @ $750
$60,000
$30,000
$30,000
Navigational aids and signs
$10,000
$5,000
$5,000
Harbormaster's office, restrooms, showers,
$81,000
$40,500
$40,500
lounge
Work vessels to transport to mooring and
$20,000
$10,000
$10,000
for maintenance
Facility customer service vessel
$20,000
$10,000
$10,000
Pickup truck
$15,000
$13,045
$1,955
Utility work cart
$4,000
$3,480
$520
VHS radios, transformers, antennas, etc.
$4,000
$3,480
$520
**TOTALS=
Form No. 90-25 (New 10/14/92, Revised !-_)
$841,500 441,755 $424,745
Agenda - 10 -