HomeMy WebLinkAboutExhibit 2Synopsis — Bicentennial Park Mooring Bollards Construction — Phase II Budget Estimated Detail Task Amount Mobilization/Demobilization $104,782 Furnish & Install Prestressed Concrete Piles $431,922 Construct Cast -in-place Pile Caps $164,102 Furnish & Install 35 -ton Mooring Bollards $100,304 Furnish & Install Berthing Fenders $225,400 TOTAL $1,026,510 Contingency (15%) $153,976 GRAND TOTAL $1,180,486 The project is a continuation of the revitalization of the Miami Downtown area and will facilitate the mooring of visiting ships at the Bicentennial Park boat slip. This second phase of the project includes the installation of concrete piles, cast -in-place pile caps, the installation of 35 -ton mooring bollards and the installation of berthing fenders and associated costs.