HomeMy WebLinkAboutExhibit 2Synopsis — Bicentennial Park Mooring Bollards Construction — Phase II
Budget Estimated Detail
Task
Amount
Mobilization/Demobilization
$104,782
Furnish & Install Prestressed Concrete Piles
$431,922
Construct Cast -in-place Pile Caps
$164,102
Furnish & Install 35 -ton Mooring Bollards
$100,304
Furnish & Install Berthing Fenders
$225,400
TOTAL
$1,026,510
Contingency (15%)
$153,976
GRAND TOTAL
$1,180,486
The project is a continuation of the revitalization of the Miami Downtown area and will facilitate the
mooring of visiting ships at the Bicentennial Park boat slip. This second phase of the project includes the
installation of concrete piles, cast -in-place pile caps, the installation of 35 -ton mooring bollards and the
installation of berthing fenders and associated costs.