File ID: 08-00736 Type: Resolution Status: Passed
Enactment #: R-08-0400 Enactment Date: 7/10/08
Version: 1 Introduced: 6/16/08 Controlling Body: Office of the City
Clerk
A RESOLUTION OF THE MIAMI CITY COMMISSION, WITH ATTACHMENT(S), AUTHORIZING
AN INCREASE TO THE PROFESSIONAL SERVICES AGREEMENT ("PSA") DATED MAY 11,
2004, WITH PROFESSIONAL ENGINEERING AND INSP. CO., INC., D/B/A BUREAU VERITAS
NORTH AMERICA, INC., FOR ADDITIONAL WORK NECESSARY FOR THE ORANGE BOWL
STADIUM DEMOLITION PROJECT, B-30153, AND OTHER MISCELLANEOUS
ENVIRONMENTAL ENGINEERING PROJECTS AS NEEDED CITYWIDE, IN AN AMOUNT NOT
TO EXCEED $200,000, THEREBY INCREASING THE TOTAL AMOUNT OF THE PSA FROM
$500,000 TO $700,00; AUTHORIZING THE CITY MANAGER TO EXECUTE AN AMENDMENT,
IN SUBSTANTIALLY THE ATTACHED FORM, FOR SAID PURPOSE; ALLOCATING FUNDS AS
NEEDED FROM VARIOUS CAPITAL PROJECT ACCOUNTS.
WHEREAS, pursuant to Request for Qualifications No. 02-03-163, issued on May 21, 2003, in accordance with Florida
Statute 287.055 and Section 18-87 of the Code of the City of Miami, Florida, as amended, to secure a qualified outside
consultant to provide Environmental Engineering Services ("Services") for miscellaneous projects as needed Citywide, the
City of Miami executed a Professional Services Agreement ("PSA") with Professional Engineering and Insp. Co., Inc.,
("PEICO"), d/b/a Bureau Veritas North America, Inc., for the provision of said Services on a continuing basis in an amount
not to exceed $500,000; and
WHEREAS, to date, the Capital Improvements Program ("CIP") has issued forty-eight (48) work order authorizations for the
contract totaling $496,133; and
WHEREAS, the remaining contract balance of $3,867, is not sufficient to cover the costs to complete additional work
required on the Orange Bowl Stadium Demolition Project, B-30153 ("Project"); and
WHEREAS, in consideration of PEICO's familiarity with the Project and a desire to maintain continuity of work, it is CIP's
recommendation that it is in the City of Miami's best interest for PEICO to continue providing Services for the Project; and
WHEREAS, the anticipated new work includes site assessment services required by the Department of Environmental
Resources Management and the Code of Miami -Dade County and additional unforeseen contamination issues; and
WHEREAS, due to the increase in costs, it is necessary to execute Amendment No. 1 to the PSA with PEICO, thereby
increasing the PSA in an amount not to exceed $200,000, from an original $500,000 to a total not to exceed amount of
$700,000, with funds available as needed from the appropriate capital project accounts utilizing the contract;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI, FLORIDA:
Crystal Report Viewer
Section 1. The recitals and findings contained in the Preamble to this Resolution are adopted by reference and
incorporated as if fully set forth in this Section.
Section 2. An increase to the PSA dated May 11, 2004, with PEICO, d/b/a Bureau Veritas North America, Inc., for
additional work necessary for the Project, and other miscellaneous environmental engineering projects as needed Citywide,
in an amount not to exceed $200,000, thereby increasing the total amount of the PSA from $500,000 to $700,00, is authorized,
with funds allocated as needed from various capital project accounts.
Section 3. The City Manager is authorized{ 1 } to execute an Amendment, in substantially the attached form, for said
purpose.
Section 4. This Resolution shall become effective immediately upon its adoption and signature of the Mayor. {2}