Date: December 14, 2023
Proposal: # B23-068
To: Mr. Brian Zeltsman
Community Redevelopment Agency
Director of Architectural & Dev
819 NW 2nd Avenue
Miami, FL 33136
305-679-6804 (Tel)
305-679-6835 (Fax)
E-mail: Bzeltsman@a miamigov.com
Attention: Mr. Brian,
We appreciate the opportunity to submit a proposal on your firm's project.
If you have any questions, please do not hesitate to contact me at (754) 245 — 0102.
Respectfully, Austin Akinrin
Project: Mt. Zion Miss. Baptist Church - HVAC Replacement
Location: 301 NW 9th Street, Miami, FL 33136
1600 N.W 3RD AVENUE,
BLDG. D4
MIAMI, FL 33136
Architectural Plans By: N/A
Dated: N/A
Sheets: N/A
Engineering Plans By: N/A
Dated: N/A
Sheets: N/A
Bofam Construction Company, Inc., a General Contractor, submits the following proposal in compliance of only the
structural Bid Documents stated above and in accordance with the following terms and conditions. This proposal expires if
not accepted within 30 calendar days of the proposal date unless extended in writing. This bid is subject to and
conditioned upon the use of the A.I.A. document A401 Subcontract Agreement between Contractor and Subcontractor, 1997
edition, or other terms and conditions acceptable to Bofam Construction Company, Inc. This proposal may be modified or
withdrawn any time prior to final contract acceptance by Bofam Construction Company, Inc. This proposal is contingent
upon Bofam Construction Company, Inc. review and acceptance of Prime Contract. This proposal is contingent upon Bofam
Construction Company, Inc. receiving acceptable contract terms and conditions. By acceptance of Bofam Construction
Company, Inc. Proposal, it is agreed that this proposal is to be included in the contract.
This proposal is predicated upon Bofam Construction Company, Inc. work being completed before 3/31/2024, subject to the
following conditions. Completion after 3/31/2024 may be subject to a negotiated price increase. This proposal is based on
availability of materials, if materials are unavailable or delayed Bofam Construction Company, Inc. will be held harmless and
not in default. This proposal is based on reasonable stability in material prices, it is agreed should material prices rise beyond
5% based on today's material prices in any period, the cost of this project will be adjusted accordingly. All materials are
subject to monthly cost adjustments.
Page 1 of 3
BOFAM CONSTRUCTION COMPANY, INC
General Contractors, Estimators & Roofing Contractors
CGC 062660 & CCC 1329221
(Certified DBE, CSBE, SECTION 3)
TEL: (754) 245-0102
FAX: (305) 675-9269
AUSTIN@BOFAMINC.COM
1600 N.W 3RD AVENUE,
BLDG. D4
MIAMI, FL 33136
This proposal is contingent and conditioned upon acceptance by Bofam Construction Company, Inc. of receipt and review of
final signed and sealed Architectural and Engineering documents and subject to review and acceptance of final approved
building plans.
Scope of Work:
We propose to supply labor, material, equipment, and accessories within the building footprint during normal working hours, 40-hour
workweek, to complete the below components based according to the above submitted Architectural and engineering drawings for the
above sum as follows:
Quotation:
Scope of Work: Furnish all permits, labor, materials, equipment and services for the removal and replacement of existing
HVAC system to include demolition, and redesign of a new HVAC. Works as per Mechanical and Electrical Engineer
specifications, and in accordance with the Florida building codes and regulations.
Base Price:
Mobilization & General Conditions $7,500
Mechanical/Electrical Engineering $5,950
Permits & Permitting Processing $2,500
HVAC Subcontractor (See attached) $187,750
Total HVAC Replacement $203,700
Specific Exclusions:
1. Permit fees & AHJ Fees (if applicable) 2. Bonding (If required)
PAYMENT: Owner agrees to pay Contractor (BCC, Inc.) initial mobilization payment of 35% for materials and equipment
required for the works. 35% in -progress inspection and 30% payment of remaining balance upon approved final inspection
from the City/County inspector.
Specific Notes: This is a preliminary proposal pending the review of final Architectural and structural permit sets.
All changes required by the building agencies having jurisdiction shall be the owner's responsibility.
This proposal may be withdrawn and/or revised in (Fifteen) 15 days if not accepted the undersigned owner accepts the above
job at the price quoted and agrees to pay for said work as it progresses or as per agreed payment schedule specified herein.
In the event of legal dispute, if any sums due are collected by suit or demand of an attorney or collection agency then the
defaulting party shall pay all costs, including reasonable attorney's fees.
Sincerely,
Austin Akinrin,
President.
Page 2 of 3
BOFAM CONSTRUCTION COMPANY, INC
General Contractors, Estimators & Roofing Contractors
CGC 062660 & CCC 1329221
(Certified DBE, CSBE, SECTION 3)
TEL: (754) 245-0102
FAX: (305) 675-9269
AUSTIN@BOFAMINC.COM
1600 N.W 3RD AVENUE,
BLDG. D4
MIAMI, FL 33136
Authorized Signature: Construction Materials are
commodity based and priced at time of delivery proposal price may increase due to material costs.
ACCEPTANCE OF PROPOSAL: The above prices, specifications and conditions are satisfactory and accepted. You are
authorized to do the work as specified and payments will be made as described above.
Date of Acceptance; / 2023, Signature: X
Page 3 of 3
SUB CONTRACTOR BID #1
EXPANCIONES 4D LLC
OSCAR ROA
3905 N Nob Hill Rd, Unit 503
SUNRISE FL, 33351
(786) 560 6891
expancionesd@gmail.com
CONTRACTOR:
Bofam Construction Co,
1600 NW 3 Avenue
Miami, FL 33136
PROJECT ADDRESS:
to
301 NW 9 Street.
Miami FI. 33136
Demolition and disposal
Installation of (3) 20 ton package units. RUUD
brand. Installation of 3 separate thermostats.
Installation of ducts according to requirements.
County and city permit.
No impact fee included.
WORK ESTIMATED
011
DATE
Total
12/ 12/ 2023
187.750,00
If there is any change based on engineering calculations the estimate may be revised.
SUBCONTRACTOR BID #2
Climate Care Air Conditioning
November 20, 2023
To: BOFAM Construction
1600 NW 3 AVE,
Miami FL 33136
15111 SW 140 PL Miami FL 33186
PH: 305 962 3563 FAX: 786 732 7109
info(aI)climatecareac.com License:
CAC1818446
Job: Mount Zion Chiller
301 NW 9 ST.
Miami FL 33136
We are pleased to provide our proposal for Mount Zion Chiller Project.
Scope of work:
Demolition
Remove existing equipment.
Install new brand Split System DX 80 Tons
Complete refrigerant charge
Crane Services
Start up and check for proper operation.
Disposal old equipment
This proposal includes all material, labor and supervision to accomplish the above -described work.
Total Cost: $225,000.00 (Two Hundred Twenty -Five Thousand and 00/100)
Excludes: Permits, High and Low Voltage wiring, any demolition, excavations, concrete pads, condensate
drain/piping, Kitchen Hood, Roof Work, Controls, any Painting, Smoke Detectors, Drywall, Cutting, Patching,
Overtime, Commissioning, scaffold to install ductwork and grilles in elevated areas and any other work not listed
herein.
Contractor name/signature & date
TERMS & CONDITIONS
Terms of Payment: The contract price shall be paid in progress payments, which does not include finance charges of any kind, according to the
following schedule: 45% mobilization to be rendered to contractor prior to start of work; 45% for equipment purchase and 10% upon final
inspection.
Permissible delays: Sub- Contractor shall be excused from any delay in the completion of the work to be performed under this Contract caused
by acts of God, inclement weather, acts or omissions of Owner or of owner's agents, employees or independent contractors, material shortages,
strikes or other labor troubles, acts ofpublic utilities, acts ofpublic bodies or inspectors, extra work, charges requested by Owner, failure by
owner to make payments promptly, or other circumstances or contingencies unforeseen by Contractor and beyond Contractor's reasonable
control.
Right to stop work: Contractor shall have the right to stop work if any payment, including any payment for extra work, is not made to
Contractor as agreed in this Contract. If any payment required under this contract is not made when due, Contractor may keep the Project idle
until such time as all payments due have been made. Additionally, the contractor may stop work if prevented from working by the owner in any
way including but not limited to the following actual seclusion from job site, changing or modifying any approved and/or permitted construction
plans.