HomeMy WebLinkAboutR-78-0788RESOLUTTON No,
A RESOLUTION ACCEPTiNC • ' HE COMPLETED •WORK
PERF0t14LD BV ROBBER LLECTRIC CO:3•IlC, AT
A TOTAL COST OP $105, 766 .00 FOIE THE
' .
� 1
E•1
tt j TjRT E, LVSPORTS I+'TELD LIC HTIN( 3
GJ��i'���� A�bA58fl5nT�,zi+ir, A r-INAL pAVririlT or
DOCU M ENTS
FOLLOW"
WHEREAS, there exists' a contract dated ,January 14 3
1978 bet4teen The City or }Miami and Rosser Electric•Company 3
Inc.;. and
WHEREAS, the work has been satis fact_ri.l.y completed,
and Rosser Electric Company, Inc. has furnished the required
documents certifyinf; that all bills f'or labor and materials
have been maid in full in connection with the aforesaid
contract; and
WHEREAS, the Cite Ma.narer and the Department of
I'ubl,_ic ':}orris; recommend that the completed work be accepted
and final na.vm ant made to the contractor;
:!nvi, THEREFORE, BE TT RESOLVED BV THE CoWISSION
OF THE (TT.,, OF MIA I, FLORIDA:
Section 1. The comnleted work performed by Rosser
Electric Company, Inc. for R0FFRT E. LEE - SPORTS FIELD
LIC;1{ ING ;,t a total cost of $105,766.00 is hereby approved.
Section 2. Thproper officials of the City of
Miami are hereby authorized to pair $10, 658.50 to Rosser
Electric Company, Inc. as cull and final payment for all.
work performed and all materials furnished in connection with.
ROBERT E. LEE SPORTS FIELD LIGHTING
PASSED AND. ADOPTED this 14th
ATTEST:
6
ONOIE', CITY'cLE}K
AND APPROVED D BY
,e
OBE F, Ci A K
ASSISTANT CITY ATTORNEY
,rvae
day
of December , 1978.
Maurice A. Ferre
MAURICE A: FIBRE, MAYO R
- APRR VED•A,S TO F AND CORRECTPNiES.S
JEO
fir_ 1
14 F, KN07,.
ATTORNEY'
SON.
EE l ING OF
DEC4 4197.8
REsQuIOM
ioseph R, Cirassie
City Manager
Donald W, Cather
Director
Department or
November 22 1978 8=2708
ROBERT E, LEE = SPORT
FIELD LIonT Nd . Final
Payment Resolution
(for Decetnber 14, 1978
Commission Meeting)
Rosser Electric Company, Inc, has completed the project
consisting of constructing; sports field lighting, including
poles and controls at the athletic field adjoining; Robert E.
Lee Junior High School, N, W. 31 Street and 5 Avenue. The
original contract amount was for $110,675 00, but the
completed contract amount is $105,766,00, and it was com-
pleted on time.
It is now in order for the Commission to accept the completed
work and authorize final payment, a"ter all conditions are
met..
THE DET'ARTMENT OF PUBLIC WORKS RECONMENDS THE ADOPTION
OF A RESOLUTION ACCEPTING THE COMPLETED WORK AND AUTHORIZING
A FINAL PAYMENT OF $10,658.50 TO ROSSER ELECTRIC COMPANY,
INC. FOR ROBERT E. LEE - SPORTS FIELD LIGHTING.
REASON
oR_ itom
SOURCE OF.
FUNDS
PROJECT
HISTORY
CONTRACT
TIME
,START :D
CONTRACT
TIME
SCHEDULED
COMPLETION
DATE
'ACTUAL
COMPLETION
DATE
BID AMO1JNT•
-
CONTRACT
FINAL -COST
CURRENT
ITEM FOR
CONSIDERATIO1
FC)R
PF r�I+�V +��fi1A�F
Robert R. Lee Sports Pield Lighting 13=2708
Rosser Electric CoMpanV Ind.
Construct sports field lighting including boles and
controls at the athletic field adjoining R. E. Lee Junior
}irh School, located at N. W. 31 Street and 5 Avenue.
Provide lighting for night titrie activities.
Second ?ear Federal Comtrunity Development Bloch Grant
Fund
Bids Received: 9/30/77
Contract Awarded: 12/15/77
Preconstruction Meeting: 2/13/78
3/27/78
65 Working days plus 7 days delay from rain and
37 days delay in receiving concrete
Holes.
8/25/78
8/25/78
$110,675.00
$105,766.00
Resolution to
final payment
accent completed work and authorize
to the contractor.