HomeMy WebLinkAboutR-79-0371RESOLUTION NO... 79 3 7 1 A RESOLUTION ACCEPTING THE COMPLETED WORK PERFORMED BY CHARLES F. SMITH AND SON, INC. AND THE TRAVELERS, INDEMNITY COMPANY AT A TOTAL COST OF $970,772.98;'ASSESSING $11,460.00 AS LIQUIDATED DAMAGES FOR OVERRUN OF CONTRACT TIME; AND AUTHORIZING A FINAL PAYMENT OF $83,021.32 FOR EAST BRADDOCK SANITARY SEWER IMPROVEMENT SR-5410-C- (centerline %sewer) IN EAST BRADDOCK SANITARY SEWER IMPROVEMENT`. DISTRICT SR-5410-C (centerline sewer) WHEREAS, there exists, a contract dated December 6, 1976 between the City of. Miami and Charles F. Smith. and Son, Inc. and The Travelers Indemnity Company; and WHEREAS, the work has been satisfactorily completed, and Charles F. Smith and Son, Inc. and The Travelers Indemnity` Company have furnished the required documeflts certifying that all bills for labor and materials have been paid in full, in connection with the aforesaid contract;' and WHEREAS, liquidated damages for overrun of contract time should be deducted from the final payment duethe contractor and the indemnity company; and WHEREAS, the City Manager and the Department of.Public Works recommend that the completed work be accepted and final payment made to the contractor and the indemnity company; NOW, THEREFORE, BE IT RESOLVED .BYTHE �COMMISSION �yOF DOCU..M ►U 1110LX THE CITY OF MIAMI, FLORIDA: , ITEM NO. f �� Section:1. The completed work performed by Charles F. Smith and Son, Inc. and The Travelers Indemnity, Company' for li ne EAST BRADDOCK ,SANITARY SEWER IMPROVEMENT SR-54lo-C (center sewer) in the EAST BRADDOCK SANITARY SEWER IMPROVEMENT DISTRICT SR-5410-C (centerline sewer) at a total cost of $97.0,772.98 is hereby approved. Section 2. That liquidated damages in the amount of $11,460.00 for overrun of contract time shall be from the balance due the contractor and the deducted indemnity company. CITY COMMISSION MEETING OF MAY 2 L 7 9 - 3.7 Section 3. The proper officialsof The City of Miami are hereby authorized to pay .Charles F. Smith'and Son, Inc. and The Travelers Indemnity Company, after all adjustments are.. made, a balance of $83,021.32 as full and final payment for all work performed and 'all materials furnished in:connection with EAST BRADDOCK SANITARY SEWER IMPROVEMENT SR-5410'-C (centerline sewer) in the EAST BRADDOCK SANITARY. SEWER IMPROVEMENT DISTRICT SR-5410-C centerline sewer). PASSED AND ADOPTED this 22 day of May 1979. ATTEST: Ralph��.;Ongi City Clerk :PREPARED 'AND APPROVED BY: Assistant City Attorney APPROVED AS TO FORM AND CORRECTNESS City A orney Maurice A. Ferre MAURICE -A. FERRE MAY O R 79- 37 1 CIT't OF MIAMt, r LORICIA F;eorese Donald W. Cather Director Department f�l f'r�2 CUF3'Ic MaEMQRANDUM EAST BRADDOCK SANITARY SEWER IMPROVEMENTSR-5410-C (centerline sewer) Resolution for. Final Paymerit Less Liquidated Damages ncFGRENCESt .. (For Commission Meeting of May 22, 1979) Charles F. Smith and. Son, Inc. and The Travelers Indemnity Company;` have completed the project consisting of construct- ing new sanitary sewage system using 8" through "12",main- line pipe, 6 house laterals,": together with all necessary �� appurtenances, in an area, bounded' by N. 1,10 25-39 Streets from N. W. 7-17 Avernues. This was, a unit price contract in the amount of,$1,033,643o00,_but the" completed contract amount is $970,772.98 less $1i,460.00 as liquidated damagesfor overrun of contract time. Itis now in order for the Commission to accept the completedwork and authorize final payment, after all conditionsare met. THE DEPARTMENT OF PUBLIC WORKS RECOMMENDS THE ADOPTION OF A RESOLUTION ACCEPTING THE COMPLETED WORK PERFORMED BY CHARLES F. SMITH AND SON, INC. AND THE TRAVELERS INDEMNITY COMPANY AT A TOTAL COST OF $970,772.98; ASSESSING $11,460.00 AS LIQUIDATED DAMAGES FOR OVERRUN OF CONTRACT TIME; AND AUTHORIZING A FINAL PAYMENT OF $83,021.32"`FOR EAST BRADDOCK SANITARY SEWER IMPROVEMENT SR-5410 C ,(CENTERLINE SEWER) IN THE EASTBRADDOCK SANITARY SEWER IMPROVEMENT DISTRICT SR-5410-C (CENTERLINE SEWER). 371 JOB NAME: CONTRACTOR JOB SCOPE REASON FOR WORK SOURCE OF FUNDS PROJECT HISTORY CONTRACT TIME STARTED CONTRACT TIME SCHEDULED, COMPLETION DATE ACTUAL COMPLETION DATE BID CONTRACT FINAL COST FINAL CONSTRUCTION FACT SHEET FOR THE CITY MANAGER East . Braddock Sanitary Sewer (centerline) mprovement SR-5410-C Son, Inc. and The Travelers Charles F. Smith and Indemnity Company Construct new sanitary sewage system using 8" thru 12" mainline pipe,.6 house laterals, together with all necessary ;appurtenances ''in;an area bounded by N W. 25-39 Streets' from N. W. 7-17 Avenues • sanitary sewers to unsewere(. area Bids Received:;'"10/28/76 Contract Awarded: 11/11/76 Preconstruction"Meeting: 12/21/76 days plus 15 days delay due to 6 days delay due to relocations rain and utility (175 calendar days over contract time at $100.00per day for liquidated damages-= 17,500.00. Negotiations with Bonding Co. and contractor have reduced this figure to $11,460.00) liquidated damages) CURRENT Resolution to accept corlpleted work, assess liquidated ITEM FOR damages in the amount of11,460.00, and authorize CONSIDERATION final payment to the contractor and The Travelers Indemnity Company.