HomeMy WebLinkAboutR-79-0459OF THE CITY OF MIAMI
Manager and the Department of
the completed work be accepted
contractor;
NOW, THEREFORE, BE IT RESOLVED BY THE COMM
"DOCUMENT 6tY
ITEM NO.
Section 1. The completed work performed b
onstruction Co., Inc. for ROADS STORM SEWER PROJECT - 1977
t a total cost of $240,713.18 is hereby approved.
Section 2. The proper officials of The City of
Miami are hereby authorized to pay $24,071.32 to Persant
Inc. as full and final payment for all work
performed and all materials furnished in connection` with ROADS
STORM SEWER PROJECT 1977.
PASSED AND ADOPTED this 25th day of June
Construction Co.
"SUPPORTIVE
DOCUMENTS
FOLLOW"
RESOLUTION NO. ' 7 9 4 5 9
A RESOLUTION ACCEPTING THE COMPLETED
WORK 'PERFORMED BY THE PERSANT CONSTRUCTION
CO., INC. AT A TOTAL COST OF $240,713.18
FOR ROADS STORM SEWER PROJECT 1977;
AND AUTHORIZING A FINAL PAYMENT OF
$24,071.32
WHEREAS, there
1978 between The City of Miami and Persant
nc . and
WHEREAS,
exists a contract dated July 25,
Construction.
the work has been satisfactorily
and Persant Construction C
documents certifying
have been paid in full in connection with the aforesaid
contract; and
WHEREAS, the City
Public Works recommend that
and final payment made'
•
completed,
Inc, has furnished the required
that all bills for labor and materials
the
FLORIDA::
Persant
LPH G. ONGIE, CITY CLER
PREPARED AND APPROVED BY:
ROBERT F. CLARK
ASSISTANT CITY ATTORNEY
Maurice A. Ferre
MAURICE A. FERRE, M A Y 0
APP
AS TO F
r
r.,
1979.
M AND CORRECTNESS::
GEO,idi . KNOX,
CIT 7 ATTORNEY
COMMISSION
MING OF
IN 2 5 1979
IIIESOIAMON Z. 9 ' 4 5 9
53
Donald W. Cather
Director
Department
/"i
C T? "l `-IIAf-11,
ivJT;1.R. F'1GZ: i-/1 iA11DU74
f Public Works`
c,C+GLv31JNC>:
May 25, 1979 FILE: B-54.28
•
ROADS STORM SEWER PROJECT - 1977
Resolution for Final Payment
(For Commission Meeting
June 25, 1979.)
Persant Construction Co., Inc has completed the projec
consisting of constructing 3,667' of 3'-wide covered ditch,
288' of 2'-wide covered ditch, and 1,855' of 151 concrete
pipe,'in,the area -,bounded, tS.'W.';12 Avenue.
between S. W. 11;Street and the F.E.C. Railroad. The
original contract amount -is $265 ',607.50, but,the"completed„
contract amount is $240,713.18, and -it 'was.' coMpletedon
.time. .
It is now in order for the.. Commission to accept the completed
work and authorize final Payment, 'after all conditions are
met. •
THE DEPARTMENT OF PUBLIC WORKS RECOMMENDS THE ADOPTION OF
A RESOLUTIONACCEPTING THE COMPLETED WORK, AND AUTHORIZING
A ; FINAL PAYMENT OF $24 , 071.32 TO PERSANT CONSTRUCTION CO.,
INC. FOR ROADS STORM SEWER PROJECT 1977.
"SUPPORTIVE
DOCUMENTS
FCLL ,,vVr,
459
JOB NAME
CONTRACTOR
JOB
SCOPE
REASON
FOR WORK
SOURCE OF
FUNDS
PROJECT
HISTORY
CONTRACT
TIME
STARTED
CONTRACT
TIME
SCHEDULED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
BID AMOUNT.
CONTRACT
FINAL COST
FINAL CONSTRUCTION FACT SHEET
FOR THE CITY MANAGER`,
Roads Storm Sewer Project - 1977 B=-5428'
Persant Construction Compa.ny, Inc.
Construct 3667 ft. of 3-foot wide covered ditch,;
288 ft. of 2-foot wide covered ditch, 1855 ft. of
15" concrete pipe in an area -bounded by I-95 to
S. W 12 Avenue between S. W. 11 Street - and the
FEC
Provide drainage a
locations of greatest neec
Storm Sewer G. 0 . Bond Funds
Bids, Received: 6/6/78
Contract Awarded: ' 6/22/78
Preconstruction Meeting: 9/6/7,
9/29./78
100 I,rorling days plus
3/14/79
3/14/79
$265,607.50
$2k0,713.18
2 days delay
CURRENT
ITEM FOR
CONSIDERATION Resolution to accept completed work
final payment to the contractor.
due ,to
rain.
and authorize
79; 459